Crowd Funded New Construction Diary

Crowd Funded New Construction Diary

Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes

Thank you @J Scott for starting the new construction diary.  It's been our inspiration to do one of our own now.  In this thread we are going to track the progress of our first Crowd Funded new construction project in Austin, TX

1122 Linden

So let's play a little catch-up since we've already done quite a bit of work getting to where we are.

DEAL ANAYLSYS

So the main thing we're looking for here is a 20%+ gross margin on the total cost of the project from a financial point of view.  Trees, flood plains, and other due diligence items can impact costs and the size we can build, but we'll get to those later.  Exits for new construction in the area show an exit price of $235/sqft.  The lot size is 181' by 51' = 9231 sqft.  The 40% Floor to Area Ratio regulation allows 3692 buildable interior square feet.  Since the frontage is greater than 50' and the lot size is greater than 7000 sqft, the City of Austin will allows us to build a duplex.  So we can do roughly two sides at 1800 sqft each.  $235 * 1800 = target exit price of $423,000 per side.

Our project cost is $110/sqft = $110 * 3600 = $396,000 for both sides, $198,000 per side.

7% in closing costs is $59,200 which includes both sides.

There were no demo costs on this lot so we don't have to add anything there.

This makes our max land cost to reach a 20% gross margin $260,000.  We were able to purchase the lot for less than that price, so it's good to go assuming we don't have any gotchas in the due diligence.

DUE DILLIGENCE

These are the items we check for in doing a new construction project.  They may differ in your area, so keep in mind this is specific to Austin.  Some may be the same, and there may be others in your market that we don't deal with.

1. Flood Zone

We check the City of Austin GIS database on line to see if there is a flood zone on the property.  There are two zones to worry about.  The 100 year and the 25 year.  If there is any 25 year flood zone on a property, we'll likely pass unless it is very small and only at the edge of a property and the house can be well above it.  A 25 year flood zone will trigger flood insurance for sure and is a big warning light.  The 100 year flood zone is ok in some areas.  Higher end buyers may not be willing to buy something in a 100 year flood plain, but lower end home buyers may be fine with it.  If any part of the house is in the 100 year flood zone, we always build the finished floor elevation to be 1 foot above that elevation, so even in a 100 year flood event, the house will stay dry.  In such a case we will use a pier and beam design, as they can be cheaper to build tall versus a slab.

1122 Linden is not in any flood zone, 25 or 100 year.

2. Lot Size

Here, we are looking for how much space we have to build and how big of a house we can build. The rules for Austin for SF-3 zoning (most common residential zone) are that you can build 40% of the lot area as enclosed space. So it's pretty easy to figure out how big of a house we will be allowed to build. If the lot is over 7000 sqft and has 50' or more of frontage we can build a duplex which increases the value of a lot substantially assuming that duplex condos sell in that market. In Austin we don't sell a duplex as a single transaction. We make a small HOA and sell them off individually to retail buyers. This doesn't work in every market, but it does in East and South Austin.

1122 Linden is 9200 sqft, a very large lot that gives us lots of options.

3. Trees

The City of Austin has a tree code that prevents building too close to some types of trees.  Our architect will do this feasibility study to determine if trees can be removed or built around.  Some trees can be removed, others if large enough will make a certain amount of space around them unbuildable.  There are rules for building a slab foundation vs a pier and beam foundation near a tree as well.  You can build pier and beam closer to a protected tree than a slab because the impact to the root zone is not as significant.  A tree in the wrong place can make some lots entirely unbuildable.  So this is an important step.

1122 Linden has some trees, but they are mostly on the borders of the lot.  Given the large size of the lot we can work around them.

4. Survey

It's always nice to get a survey but we rarely get one from the seller, much less one that is a full tree and topo survey.  The tree survey is required for the aforementioned reason.  The topo survey is important for determining the exact elevation lines if a flood zone is in play as well as determining the slope in the lot.  The City of Austin also has what it calls McMansion rules that prevent you from building above a certain height.  However if you have even a slightly sloped lot, where the top of that virtual tent is can mean the difference from being able to build one story or two.  So if you get this wrong, even though you have 40% FAR you might not be able to build two stories to achieve it.  This is where a good architect comes in to ensure that a design can fit inside that virtual tent.

This also creates another problem at the foundation.  To maximize your space you may be tempted to lower the elevation of your foundation.  On a super flat lot not in a flood zone, this is probably ok.  However if you have any slope to your lot there is going to be water drainage when it rains.  You must be very careful that you can still achieve 6 inches of exposed foundation  regardless of the slop of the lot to ensure proper drainage, otherwise you will end up with a leak and a wet house.  Ripping out carpet and hardwoods after the fact is a messy and expensive process.  So making sure your drainage plan is sufficient is paramount.  The topo survey will help you figure this out.

The 1122 Linden survey shows a very flat lot with all of the trees marked.  We may have to use some pier and beam near the trees, and slab elsewhere.

5. CC&Rs + Deed Restrictions + HOAs

Many of the lots we look at were platted in the 1930s, 40s, and 50s.  Some of the deed restrictions are actually on the plat!  So you have to look everywhere.  These restrictions may include items like only single family homes may be built in this neighborhood, or the servants quarters must be separate, or no people of color are allowed to live here (they are that old).  That type of restriction is obviously outdated and illegal.  The ones we care about are ones that restrict building size or type. 

If you don't pay attention to these, you can risk building your project and have someone complain half way through to the city.  This can lock your project up and potentially force you to tear it down.  If no one complains, and you get it done and sold, you got lucky.  I've seen some builders do this, but I would never risk the $400,000 to $650,000 required to build some of these projects on getting lucky.

For 1122 Linden, there were no restrictions on building type or size.

PRE STARTS

The key expenses you need to cover in addition to the land acquisition are as follows:

1. Architectural Design - We include this cost in our $110/sqft.  This is usually a fixed $/sqft for this service.

2. Engineering Design - We include this cost iin our $110/sqft as well.  This is also usually billed in $/sqft of design.  It is very important to use a good engineer with good insurance and a long track record.  Money spent on good engineering is better than money spent on a warranty in my opinion.  A good foundation and framing design will keep you from having a call back 9 years from now (Foundation warranties are usually 10 years) with a costly failure.  Don't skimp on foundation and framing.  Do it right, and use the engineer's insurance to offload your risk for a foundation failure.  Your reputation is on the line here too.

3. Soil analysis - This is required for the engineer to be able to build the right type of foundation.  East Austin has inconsistent soils, so this is particularly important where we build.

4. Permit fees - The City takes their cut

5. Utility hookup fees - If you are building a duplex where a single family house used to be, you are likely going to have to upgrade the water and waste water taps.  If it is single family, you may be able to simply re-use an old tap and save some money.

6. Builders Risk Insurance - This can usually be purchased in 24 hours if you have a good relationship with an insurance company, so I usually wait to buy this almost the day before construction starts or the day before we close a loan with a lender which will want to make sure they are an additionally insured on the policy.  I only buy insurance for my cost to build, not on the retail amount.

7. Demolition - If there is a pre-existing structure to demolish, you will need to pay for this as well.  Be sure to check with the title company and your lender that it is ok to demo any structure before a loan is issued.  The reason for this being that banks always want to be in first position on the property and a mechanics lien from a demo company would put them in second position if you don't pay the demo company.  Banks will usually be ok with this if you get a lien release along with the work and have a good relationship with them.  Before you demo, make sure to disconnect all of the utility lines!  A good demo company will do this for you, but as the owner, you may need to call the utility company to start the process.

1122 Linden has covered all of the above steps.  We have crowd funded the capital for the entire project so we do not have a bank for this project.  We have purchased the land, designed a building, had the foundation and framing engineering done, created a permit set, submitted it to the City of Austin and we expect our permit to be approved this week!

There is an old slab that needs to be removed which we plan on doing around the time we get our permit.

The rough schedule is as follows.  November and December are holiday months, so those are typically slow in the building business.

7/10 - Receive permit

8/15 - Complete Foundation

9/15 - Complete Framing

10/31 - Complete Mechanicals

12/15 - Complete Finish out

1/15 - Complete punch list, clean, photo, and list

13Reply
267 views

Most Popular Reply

Investor · Round Rock, TX · Member since 2010 · 8k+ posts · 4k+ votes
12y

Regarding impervious coverage questions above we do really strange things like "stripe" the driveways, get the CO, and THEN fill in the rest of the driveway to maximize interior footage.  You have to do crazy things in the COA to get the footage you want with the magical tent items and such.  

See this reply in the discussion

85 Replies

Jump to latestLatest
  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    UPDATE:

    So we go out to pull the old driveway and slab from 50 years ago on this lot and there is still an active gas line on it!  Even though there is no service, you still need to have the lines pulled.  This was a bit of a surprise to me because I wasn't expecting there to be an active line on a lot that hasn't had a structure for decades.

    This is a big deal though.  You want to make sure all of the utilities are pulled and you get an OK from your local utility before doing any demo work, even pulling up a driveway.  Ripping open a gas line can be life threatening.

  • Investor · Round Rock, TX · Member since 2010 · 8k+ posts · 4k+ votes
    12y

    Never a dull moment!

  • Developer · Garland, TX · Member since 2008 · 8k+ posts · 4k+ votes
    12y
    Originally posted by @John Blackman:

    Ripping open a gas line can be life threatening.

    Same with buried power. And if you really want an uprising, buried fiber.  

    Beyond the utility providers, check HERE.

     
  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    @Derek Carroll 

    We have done both where we have it under contract and where we have already purchased the land.  For iFunding we need to put our equity in at closing of the raise.  It many cases we have already spent that $10k in prestart expenses which count as equity.

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    We received our notification from the Gas company one day after they said it would be complete that it was all clear.  We had some people parking on the lot, so we left signs up for one day and they listened.  It was clear today and we have scraped off the old remains of the foundation and driveway.  We've got a tree in the back that is not protected and will need to come down before we can start the forms for the foundation.

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    After clearing the lot and getting ready to pour the foundation, our builder discovered a slight discrepancy in the foundation plan which required a small change from engineering.  It was the difference in using a concrete back deck or a wood one.  We went with wood because it looks nicer in my opinion, is cheaper, and has a smaller impact on our impervious coverage ratio.  Win-win all around. 

    With that little item taken care of, we started forming the foundation last week and we are making good progress this morning.  Today I even have a video for you.

    Pre-Start last week:

    https://www.youtube.com/watch?v=LuWWGmx56ZM

    This morning:

    https://www.youtube.com/watch?v=9ADy0XTkb7E

    This is WEEK 1 of an active project.  We're aiming to get the following items completed this week.

    • Form up the foundation
    • Dig exterior foundation beams
    • Complete the plumbing rough
    • Termite treatment

    Next week we will add steel, seal the foundation in plastic and hopefully pour assuming we can find a time slot with our concrete provider.

    We are working off our first draw which is only 1/5th of the land purchase price so our loan to equity ratio is a tiny 20%.

  • Isle Of Palms, SC · Member since 2013 · 38 posts · 18 votes
    12y

    Congratulations @John Blackman and @Bryan Hancock on getting this deal together.

    And thank you for sharing all of this information. This is an awesome thread and I can't wait to see how it plays out.

    Good Luck!

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    WEEK 1

    At the end of the week the forms have been completed.  We were waiting on the form survey which was completed before digging beams.  You don't want to commit to any of the hard work until you know the form survey is correct and you're building the right size foundation and house.  Next week we should be able to get the plumbing rough in after the beams are dug which is happening today, sorry no photo of that, check in next week.  There is a small chance we could pour next week, but everything would have to go perfectly.

    Completed this week:

    Forms complete

    Form survey complete

  • Flipper/Rehabber · Tulsa, OK · Member since 2013 · 15 posts · 5 votes
    12y

    Thank you @John Blackman and @Bryan Hancock  for sharing your roadmap from start to finish! Way Cool.

    I just found these threads and your listings of "Feasibility" action items and "post Feasibility" next-steps' saved me tons of time from documenting this for an Investment Summary today!

    'Great stuff for anybody considering this field, that it all starts with modeling your desired profit margin and working backwards within the market fundamentals and city codes to see if you can get there with current sale prices without speculation. 

    You also exposed many of the specific COA "tiger pits" to avoid! Like FAR, (McMansion) , Legacy tree, impervious cover, Flood Plains, setbacks, etc...You didn't even mention Black Capped Vireo's or Salamanders!

    Overall a great reminder that this is a Spreadsheet business and that the way you eat an elephant is one bite at a time!

    Cheers,

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    WEEK 2

    We dug the exterior beams this week.The ground is especially hard and the plan calls for deeper beams than most due to the large number of corners in the slab design which has been slow moving.  We are still aiming to pour next week.

    Complete this week

    • Dug beams

    To Complete next week

    • Plumbing rough
    • Install steel
    • Termite treatment
    • Pour foundation

    Blocking Issues

    • None

    Pictures

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    WEEK 3

    This has been a bit of a lost week.   Our plumber is backed up and his scheduled slot was Friday.  It rained.  He is scheduled to do the plumbing rough on Monday.

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    12y

    WEEK 4

    Overview

    The plumbing rough has been completed, but our city inspector did not show on Wednesday as planned.  So we will not be able to install steel and pour until that inspection is done.  We do have a nice video this week though.  Hopefully we'll have some poured concrete next week.

    Work Items
    Complete this week
    • Plumbing rough complete
    To Complete next week
    • Install steel
    • Termite treatment
    • Pour foundation

    Blocking Issues

    • None

    Video

    https://www.youtube.com/watch?v=ACrKp2JHHxc

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    WEEK 5

    We had a new problem I haven't faced before this week, so maybe you can learn from this event.  We were all ready to get our foundation inspection and the city came out and told us we were going to pop the McMansion tent based on our form survey.

    Well it turns out surveyors sometimes make mistakes and they had labeled the finish floor elevation a foot higher than it was supposed to be.  So on the ground our foundation was one foot lower than on the survey.  So the city inspector says fix your ____ and call me when it's done.

    Good thing for us we have a survey company that is really fast.  In most cases this might take a week for the surveyor to find a time to visit the site, make the change and get you a new survey.  Ours had it done the same day, but we still had to wait for the inspector to come out again which he did. 

    However by the time we ironed out that wrinkle, it rained for the rest of the week.  This is a perfect example where even a one day delay can turn into a 1 week delay.

    Lesson:

    Double check the paperwork.  It's tempting to think that just because you paid for something it's done right.  People are not perfect.  Inspect everything.  Trust and verify.

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    WEEK 6

    The plastic is installed and the steel is on site, the termite treatment is complete, the pre-pour inspection is scheduled for Monday 9/29 and the pour is scheduled for next Tuesday 9/30.  So next week I should have some pretty slab pictures.  For now I've got steel, plastic, and forms.

    Complete this week

    • Plastic installed
    • Steel delivered
    • Termite treatment

    To Complete next week

    • Install steel
    • Pour foundation

    Blocking Issues

    • None

    Video

    http://youtu.be/yuGeAERGYA0

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    WEEK 7

    Overview

    Slab poured, and framing lumber is scheduled for delivery on Monday.  We're going vertical next week.

    Work Items

    Complete this week

    Slab poured

    To Complete next week

    Lumber delivery

    Start framing

    Blocking Issues

    None

    Schedule
    1/31 - Target date to do survey if title comes back in time. - COMPLETE
    2/3 – Survey performed - COMPLETE2/4 – Survey docs delivered, feasibility start - COMPLETE

    2/21 - Have site plan rough ready and approved by COA arborist - PARTIAL, waiting on arborist

    2/24 - Complete material submission for iFunding - COMPLETE

    4/21 - Designs complete and handed to engineering - COMPLETE

    5/13 - Engineering complete - COMPLETE

    5/29 – Permit paper is ready to submit - COMPLETE

    5/30 - Submit permits to the city - COMPLETE

    6/25 - Submit response to city feedback on permits - COMPLETE

    6/30 - Permit approved - COMPLETE

    8/8 - Gas lines removed, slab demolished, start foundation - ON TRACK

    8/11 - Tree removed - COMPLETE

    8/29 - Foundation complete - DELAYED, plumber behind schedule, and rain delays

    10/10 - Framing complete

    1/31 - Complete construction

    3/31 - Units sold

    Pictures

    Video

    http://youtu.be/wqtWF8K_Y-A

  • Investor · Round Rock, TX · Member since 2010 · 8k+ posts · 4k+ votes
    11y

    Looking good!

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    Week 8

    Overview

    The first floor framing is complete.Next week is the second floor!

    Work Items
    Complete this week
    • Lumber delivered
    • First floor framed
    To Complete next week
    • Install trusses
    • Start on second floor framing
    Blocking Issues
    • None
    Schedule
    1/31 - Target date to do survey if title comes back in time. - COMPLETE 2/3 – Survey performed - COMPLETE 2/4 – Survey docs delivered, feasibility start - COMPLETE

    2/21 - Have site plan rough ready and approved by COA arborist - PARTIAL, waiting on arborist

    2/24 - Complete material submission for iFunding - COMPLETE

    4/21 - Designs complete and handed to engineering - COMPLETE

    5/13 - Engineering complete - COMPLETE

    5/29 – Permit paper is ready to submit - COMPLETE

    5/30 - Submit permits to the city - COMPLETE

    6/25 - Submit response to city feedback on permits - COMPLETE

    6/30 - Permit approved - COMPLETE

    8/8 - Gas lines removed, slab demolished, start foundation - ON TRACK

    8/11 - Tree removed - COMPLETE

    8/29 - Foundation complete - DELAYED, plumber behind schedule, and rain delays

    10/10 - Framing complete - DELAYED

    1/31 - Complete construction

    3/31 - Units sold

    Pictures

    Video

    http://youtu.be/1XQkb0xKaa4

  • Karen MargraveBusiness Member
    Moderator
    Realtor, General Contractor, and Developer · Redding, CA · Member since 2009 · 7k+ posts · 4k+ votes
    11y

    Looking good! Not knowing anything about Texas and your weather (except I know it gets HOT in summer) what is the rainfall there like in winter, will you have a lot of delays? Though once it's enclosed it should be ok right? 

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    When it does rain in Texas, it's hard and fast.  So we're not likely to have long stretches of rain.  Most of it happens in the spring too, so we should be ok.  Rain usually doesn't delay us that much.

  • Developer · Garland, TX · Member since 2008 · 8k+ posts · 4k+ votes
    11y

    Any updates, John?

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    Week 11

    Overview

    This week we were actually rained out most of the time, but this is a bit of a late update so we have last week's framing progress in here too.

    We spent this week finishing out the core framing and doing a window review. Next week we should get onto siding and window installation. The sewer yard lines were installed, but have not been inspected yet.

    Work Items Complete this week

    1. Complete rafters
    2. Stairs installed
    3. Roof supports and garage walls installed
    4. Sewer yard lines complete

    To Complete next week

    1. Start cornice
    2. Windows delivered
    3. Start wall sheathing and roof decking
    4. [stretch] start siding

    Blocking Issues

    None

    Schedule

    8/29 - Foundation complete - COMPLETE

    10/10 - Framing complete - COMPLETE

    2/31 - Complete construction

    4/31 - Units sold

    Pictures

    Video

    http://youtu.be/53253GiCTWE

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    Week 14

    Overview

    Steady progress on the exterior, we should be onto mechanicals next week.

    Complete this week

    • Windows 65% complete
    • Started Tyvek
    • Started siding
    • Complete roof decking

    To Complete next week

    • Dry in roof
    • Complete tyvek and siding
    • Start mechanicals

    Blocking Issues

    • None

    Schedule

    1/31 - Target date to do survey if title comes back in time. - COMPLETE

    2/3 – Survey performed - COMPLETE

    2/4 – Survey docs delivered, feasibility start - COMPLETE

    2/21 - Have site plan rough ready and approved by COA arborist - PARTIAL, waiting on arborist

    2/24 - Complete material submission for iFunding - COMPLETE

    4/21 - Designs complete and handed to engineering - COMPLETE

    5/13 - Engineering complete - COMPLETE

    5/29 – Permit paper is ready to submit - COMPLETE

    5/30 - Submit permits to the city - COMPLETE

    6/25 - Submit response to city feedback on permits - COMPLETE

    6/30 - Permit approved - COMPLETE

    8/8 - Gas lines removed, slab demolished, start foundation - ON TRACK

    8/11 - Tree removed - COMPLETE

    8/29 - Foundation complete - COMPLETE

    10/10 - Framing complete - COMPLETE

    2/31 - Complete construction

    4/31 - Units sold

    Pictures

    Video

    http://youtu.be/KXeUwSCr54A

  • Haverhill, MA · Member since 2009 · 293 posts · 157 votes
    11y

    @John Blackman thanks for this awesome thread. I just stumbled upon it today but it was a great read. I look forward to keeping track as this progresses. 

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    1122 Linden Project Status - 12/05/2014


    Budget Status: GREEN
    Schedule Status: GREEN
    Construction Week: 15
    Estimated CO Date: February, 2015
    Estimated Market Ready Date: March, 2015

    Overview
    The siding should be completed over the weekend and we can move onto interior mechanicals next week. This is typically where we can have some slowdowns with inspections and fixing punch lists and then waiting for re-inspections. We should be able to get the bulk of the mechanical work done in the next two weeks. Lots of great progress this week on the exterior, and no blockers.

    Work Items Complete this week
    • Install windows
    • Tyvek complete
    • Roof dried in
    • Siding is complete
    • Processed another draw this week
    • Plumber started top out

    To Complete next week
    • Plumbing top out
    • Start HVAC
    • Start electrical rough
    • Install shingle roof
    • Start exterior paint prep

    Blocking Issues
    • None

    Schedule
    1/31 - Target date to do survey if title comes back in time. - COMPLETE
    2/3 – Survey performed - COMPLETE
    2/4 – Survey docs delivered, feasibility start - COMPLETE
    2/21 - Have site plan rough ready and approved by COA arborist - PARTIAL, waiting on arborist
    2/24 - Complete material submission for iFunding - COMPLETE
    4/21 - Designs complete and handed to engineering - COMPLETE
    5/13 - Engineering complete - COMPLETE
    5/29 – Permit paper is ready to submit - COMPLETE
    5/30 - Submit permits to the city - COMPLETE
    6/25 - Submit response to city feedback on permits - COMPLETE
    6/30 - Permit approved - COMPLETE
    8/8 - Gas lines removed, slab demolished, start foundation - ON TRACK
    8/11 - Tree removed - COMPLETE
    8/29 - Foundation complete - COMPLETE
    10/10 - Framing complete - COMPLETE
    12/19 - Mechanicals complete
    2/31 - Complete construction
    4/31 - Units sold

    Pictures

  • Developer · Austin, TX · Member since 2010 · 371 posts · 284 votes
    11y

    1122 Linden Project Status - 1/9/2015

    Budget Status: GREEN


    Schedule Status: GREEN
    Construction Week: 18
    Estimated CO Date: March, 2015
    Estimated Market Ready Date: April, 2015

    Overview
    We passed the electrical inspection. Plumbing valves are being replaced this week due to some minor vandalism which has pushed that inspection off to next week. HVAC, plumbing and framing inspections will be done concurrently. We will be issuing a new draw next week.

    Work Items

    • Complete this week
    • Security pre-wire
    • Installed shingle roof
    • Metal roof on garage
    • Passed electrical inspection
    • Exterior paint complete

    To Complete next week

    • Issue new draw
    • Pass remaining mechanical inspections
    • Insulate pending inspections
    • (stretch) Start sheetrock

    Blocking Issues
    None

     
    Schedule
    1/31 - Target date to do survey if title comes back in time. - COMPLETE
    2/3 – Survey performed - COMPLETE
    2/4 – Survey docs delivered, feasibility start - COMPLETE
    2/21 - Have site plan rough ready and approved by COA arborist - PARTIAL, waiting on arborist
    2/24 - Complete material submission for iFunding - COMPLETE
    4/21 - Designs complete and handed to engineering - COMPLETE
    5/13 - Engineering complete - COMPLETE
    5/29 – Permit paper is ready to submit - COMPLETE
    5/30 - Submit permits to the city - COMPLETE
    6/25 - Submit response to city feedback on permits - COMPLETE
    6/30 - Permit approved - COMPLETE
    8/8 - Gas lines removed, slab demolished, start foundation - ON TRACK
    8/11 - Tree removed - COMPLETE
    8/29 - Foundation complete - COMPLETE
    10/10 - Framing complete - COMPLETE
    12/19 - Mechanicals complete - COMPLETE
    3/15 - Complete construction
    5/15 - Units sold


    Pictures