The vendor who ghosted mid-turn — what I changed in my scope letter
Mid-turn, third week, the painter stopped answering. Not a fight, not a dispute — just silence. The unit sat half-painted for nine days while I called, texted, and finally paid someone else to finish it. The turn ran three weeks long, the tenant's move-in slipped, and I ate the vacancy.
I was angry at the painter. Then I looked at what I'd actually given him: a text message that said "paint the 2-bed, $1,400" and a start date. No scope, no schedule, no payment terms, no consequence for disappearing. I hadn't hired a vendor. I'd made a wish.
Here's what my scope letter has now, on every job

, even the small ones:
1. The work, in plain sentences. Not "paint unit" — every room, every coat, what gets prepped, what gets left alone. If it's not written down, it doesn't exist, and "I thought that was included" is a conversation you will lose.
2. The schedule, with dates. Start date, finish date, and what happens if the finish date slips — a daily number, agreed in advance. Nobody likes the clause. Everybody respects it once it's there.
3. The payment, tied to milestones. A third to start, a third at the midpoint I can see with my own eyes, a third when I walk it and sign off. The vendor who wants it all up front is telling you something. Listen.
4. The walkthrough, before the final check. I walk every job before the last payment clears. Ten minutes, phone photos, a short list of what still needs doing. The vendors who do good work love this — it proves they did good work.
The next painter got the same one-page letter. He finished a day early. Same trade, same market, same money — the only thing that changed was the paper.
What's in your scope letter that you learned the hard way?