The vendor who ghosted mid-turn — what I changed in my scope letter

The vendor who ghosted mid-turn — what I changed in my scope letter

Investor · Member since 2026 · 92 posts · 20 votes

Mid-turn, third week, the painter stopped answering. Not a fight, not a dispute — just silence. The unit sat half-painted for nine days while I called, texted, and finally paid someone else to finish it. The turn ran three weeks long, the tenant's move-in slipped, and I ate the vacancy.

I was angry at the painter. Then I looked at what I'd actually given him: a text message that said "paint the 2-bed, $1,400" and a start date. No scope, no schedule, no payment terms, no consequence for disappearing. I hadn't hired a vendor. I'd made a wish.

Here's what my scope letter has now, on every job

, even the small ones:

1. The work, in plain sentences. Not "paint unit" — every room, every coat, what gets prepped, what gets left alone. If it's not written down, it doesn't exist, and "I thought that was included" is a conversation you will lose.

2. The schedule, with dates. Start date, finish date, and what happens if the finish date slips — a daily number, agreed in advance. Nobody likes the clause. Everybody respects it once it's there.

3. The payment, tied to milestones. A third to start, a third at the midpoint I can see with my own eyes, a third when I walk it and sign off. The vendor who wants it all up front is telling you something. Listen.

4. The walkthrough, before the final check. I walk every job before the last payment clears. Ten minutes, phone photos, a short list of what still needs doing. The vendors who do good work love this — it proves they did good work.

The next painter got the same one-page letter. He finished a day early. Same trade, same market, same money — the only thing that changed was the paper.

What's in your scope letter that you learned the hard way?

0Reply
217 views

6 Replies

Jump to latestLatest
  • Member since 2025 · 25 posts · 7 votes
    2d

    Solid list. A few more things worth putting in a turn scope letter:

    • Photo-based scope. Attach the move-out photo of each item to be fixed, so "patch and paint living room" means the same thing to both of you. Those photos also double as your before shots for the deposit itemization.

    • A communication clause: an end-of-day text with a progress photo, and what happens after 2 business days of no contact (you can bring in someone else, and payment covers only completed milestones).

    • Materials: who buys them, paint brand, color, and sheen written down, and who keeps the leftovers.

    • Access and lockup: lockbox code changes after the job, who locks up, and where the thermostat gets left.

    • Punch list against the next tenant's move-in condition report, so "done" and "documented as ready" happen on the same walkthrough.

    The other half is a backup vendor for each trade. The letter sets expectations, but a second name on your list is what actually protects the move-in date.

    • Investor · Member since 2026 · 92 posts · 20 votes
      1d

      Logan, the photo-based scope is the one I'm stealing first — "patch and paint living room" means nothing until both of you are looking at the same photo. Same for the 2-day no-contact clause; mine says the same thing in plainer words now. The backup vendor point is the real lesson though — the letter sets the expectation, but the second name is what saved my move-in date the second time around. I keep one backup per trade on the same page as the letter now.

  • Property Manager · Denver, CO · Member since 2026 · 32 posts · 13 votes
    1d

    Nine days of silence with a half-painted unit and a move-in already on the calendar is rough.

    The piece I'd add is on the leasing side, since the vacancy is what actually cost you. I wouldn't set the new lease to start the same day the scope letter says the work finishes. Leaving 5 to 7 days between the finish date and move-in gives you room for the walkthrough, the punch list and a cleaner, and if the vendor runs a few days late nobody's move-in slips.

    Same idea with the incoming tenant. I'd tell them up front the date depends on the work being signed off, and send a quick update at your midpoint check so they aren't hearing about a delay the week they're packing.

    +1 to Logan on having a backup for each trade too. Did the new tenant stick around through the delay or did you have to relist?

  • Monroe, Orange County · Member since 2026 · 29 posts · 9 votes
    1d

    Good list. The one that changed things for us was paying in milestones tied to photos: demo done, rough-in done, final. A vendor who knows the next payment depends on a photo of finished work tends to show up. We also put a "start by" date in writing, not just a "finish by" date, because the ghosting usually happens before the job really starts.

  • Real Estate Broker · Rochester, NY · Member since 2026 · 60 posts · 20 votes
    1d

    YES! But what about the bigger issue at hand. Where does that one page scope live? In your google drive? In a file folder on your computer? Hopefully, it lives in your property management software.

    I built out my operating platform to write up a detailed scope of work based on the project, whether that's a bathroom remodel or a unit turnover, and tied it to the property/unit. And I can send that scope to any contractor in my Contractor List, or solicit bids from Contractors by simply adding their email address.

    I can't tell you many arguments that process has saved me from - and I don't have to explain that to you!

    But the bigger issue that I see here is where does all that live?

  • Leo SteinBusiness Member
    Property Manager · Orange County, CA · Member since 2025 · 348 posts · 85 votes
    3h

    Willson, that mid-turn ghost is painful because vacancy is what you actually eat. I would keep your four points and add a couple we use on Orange County turns. Put photos of each item in the scope so "patch and paint" means the same thing to both of you. Tie payments to milestones you can see. Write a start-by date as well as a finish date, and a simple rule after two business days of silence so you can bring in the backup without a fight.

    Leave a few days between signed-off work and the new lease start so the punch list and cleaner do not collide with move-in. Tell the incoming tenant up front that the date depends on walkthrough sign-off, and update them at the midpoint check. A backup name per trade on the same page as the letter is what actually protects the date. The paper sets expectations. The second vendor is the safety net. Happy to compare notes by message.