What’s Causing the Most Construction Delays in 2026?

Most Popular Reply

Divin KanyamaBusiness Member
Accountant · Seattle, WA · Member since 2025 · 241 posts · 83 votes
7mo

Excellent question, @Tracy Thielman. I frequently interact with developers and planners in my area. Most delays are primarily caused by the following:

Permitting: Often, it takes six to twelve months for those fortunate enough to move quickly.

Inflation: Construction costs have soared in recent years, significantly affecting profit margins. Additionally, our region has one of the highest minimum wages nationwide.

See this reply in the discussion

3 Replies

Jump to latestLatest
  • Divin KanyamaBusiness Member
    Accountant · Seattle, WA · Member since 2025 · 241 posts · 83 votes
    7mo

    Excellent question, @Tracy Thielman. I frequently interact with developers and planners in my area. Most delays are primarily caused by the following:

    Permitting: Often, it takes six to twelve months for those fortunate enough to move quickly.

    Inflation: Construction costs have soared in recent years, significantly affecting profit margins. Additionally, our region has one of the highest minimum wages nationwide.

  • Dallas, TX · Member since 2026 · 29 posts · 7 votes
    3mo

    Permitting is the one nobody wants to talk about because it's the hardest to control.

    Financing timing and contractor availability are real, but both have workarounds — you can restructure draws, you can find another sub. A city that's 90 days behind on permit reviews because they're short-staffed or processing a backlog from a surge in applications? There's nothing you can do but wait, and your construction loan is burning the whole time.

    What I see consistently in North Texas — across municipalities from smaller outer-ring cities all the way into established DFW suburbs — is that permit timelines vary wildly even within the same county. One city might turn around a residential permit in three weeks. The city right next door might take four months for the exact same scope of work, because they're running reviews through one overwhelmed department or because they batch approvals through council meetings instead of administrative approval.

    The problem is most buyers and first-time developers don't ask about permit turnaround time before they close on land or start their construction loan clock. That's where projects quietly die — not on the job site, but in the queue.

    The fix isn't complicated but it requires knowing who to call before you're committed: contact the building department directly, ask for current plan review turnaround time, ask if they do over-the-counter permits for any scope of your project, and ask whether your inspector scheduling is done online or through a coordinator. Those four questions alone will tell you how that city actually operates.

  • Investor · Malakoff, TX · Member since 2017 · 2k+ posts · 2k+ votes
    3mo

    This is why I have my own construction company and build outside city limits. Solves 2 of the 3 problems.

Join the conversationCreate a free account to reply, vote on answers and follow this thread.