How I Build a Flip Rehab Budget From Scratch: Line by Line

How I Build a Flip Rehab Budget From Scratch: Line by Line

Andrew BoscoBusiness Member
Rental Property Investor · NH · Member since 2023 · 444 posts · 419 votes

Most investors who lose money on a flip don't lose it because they picked the wrong neighborhood or misjudged the ARV. They lose it because they built the rehab budget wrong. Either they missed a line item entirely, or they used numbers from two years ago that don't reflect what labor actually costs today.

I walked through a live rehab scope with a coaching group last week on a distressed single-family in New Hampshire. A 960-square-foot ranch, listed at $189,000, assessed at $260,000. Good bones — new mechanical systems installed in 2024, public water, sewer, and natural gas. Significant deferred maintenance: pipes burst over winter, water damage, full plumbing replacement needed, new roof, no garage, heavy tree coverage.

We built the budget line by line. Here's exactly how I do it — and the specific numbers we landed on.

Start With the Non-Negotiables

Every flip has a set of costs you cannot avoid once you've committed to the scope. On this property, those were:

Roof replacement: On a property this size in NH, a new roof runs approximately $10,000. That's not negotiable — the property needs one, and buyers will flag it on inspection if you try to leave it.

Full plumbing replacement: Pipes burst means you're replacing the system. In today's NH market, fixtures and all, budget $20,000. I've seen investors try to spot-repair this. It costs more in the long run and creates liability.

New kitchen: A basic but functional kitchen replacement — new cabinets, counters, appliances — runs approximately $10,000 on a property this size. Not a designer kitchen. A clean, updated kitchen that passes the buyer sniff test.

New bathroom: $8,000 for a full bath refresh. New tile, vanity, fixtures. Budget this regardless of current condition — if everything else is updated and the bath looks original, it will hold back your ARV.

These four items alone account for roughly $48,000 of the scope. Everything else is built on top of this base.

The Middle-Cost Items Most Investors Underestimate

Once the non-negotiables are covered, the budget typically goes off the rails in three areas:

Plumbing fixtures and rough-in: I include this separately from the full plumbing line — rough-in for a new bathroom in the basement, if you're adding one, has its own cost. Budget it independently.

Flooring: LVP is running approximately $3 per square foot installed in most NH markets right now. On a 1,000-square-foot property, that's $3,000. Carpet is cheaper but often not appropriate for the resale spec you're targeting. Budget the LVP unless you have a specific reason not to.

Landscaping and exterior: This is where I see the most under-budgeting. I walked this property on Google Street View before running a single number. The comps — properties that sold at $385,000 to $400,000 in the same neighborhood — had cleared lots and manicured curb appeal. This property had heavy tree coverage and an overgrown lot.

Tree removal runs $10,000 or more depending on size and access. General landscaping to get competitive: another $2,500 to $5,000. The first budget draft had $2,500 for landscaping. The real number was closer to $15,000.

(Note: Image recommendation — a side-by-side photo showing a cleared lot comp versus the subject property's tree coverage would be effective here.)

The Line Item Everyone Forgets: Interior Painting

I saved this for its own section because it's the single most commonly missed item I see.

Interior painting has increased significantly. In the NH market, painters are currently charging approximately $5 per square foot. A year or two ago, that number was $2 to $3 per square foot.

On a 1,000-square-foot property, that's $5,000. On a 1,500-square-foot flip, $7,500. On a 2,000-square-foot property, $10,000.

When we built the initial budget live with the coaching group, painting wasn't on the sheet. We came up with $72,000. When we added it back in, the number became $88,000 to $90,000.

That $16,000 to $18,000 gap is material. At $189,000 acquisition and $88,000 in rehab — you need your ARV assumptions to hold at $385,000 or better just to have a reasonable margin at conventional financing. At hard money rates, the deal gets tight.

The fix is simple: add a painting line item to every budget, use current rates, and do it before you finalize your offer — not after.

Don't Skip the Structural Contingency

Every rehab budget should include a structural contingency line. Not because you necessarily expect structural issues — but because you will sometimes find them.

On this property, I built in $2,000 as a minimum. On larger properties or anything with a known foundation concern, that number goes up. But zero is not an acceptable number. If you've walked the property and confirmed everything looks clean, the contingency may not get touched. That's a good outcome. What you're protecting against is the $3,000 discovery mid-project that wasn't in the scope.

The Completed Budget

For the property we analyzed, here's where we landed:

  1. Roof: $10,000
  2. Siding (painted, not replaced): $6,000
  3. Landscaping and tree removal: $12,500–$15,000
  4. Full plumbing replacement: $20,000
  5. LVP flooring: $3,000
  6. New bathroom: $8,000
  7. Kitchen: $10,000
  8. Interior painting: $5,000
  9. Sheetrock and drywall repairs: $2,000
  10. Structural contingency: $2,000
  11. Dump fees: $500–$1,000

Total: approximately $79,000–$82,000 before the basement scenario. Add the basement finish with bedroom and bath: $88,000–$92,000 total.

The Bottom Line

A flip budget isn't a document you build once at the start and forget. It's a working tool you refine as you learn more about the property. The line items in this article aren't definitive — costs vary by market, contractor relationships, and property condition.

What is consistent: the properties that perform on a flip are the ones where the investor knew their numbers before they made the offer. The surprises that kill margin are usually things that were knowable — if you'd walked the street, updated your labor rates, and remembered to put painting on the sheet.

Build the budget like the margin matters. Because it does.

Andrew Bosco - Candor Investment Group529 Reviews
3Reply
274 views

5 Replies

Jump to latestLatest
  • Northwest Indiana · Member since 2024 · 83 posts · 34 votes
    5mo
    Quote from @Andrew Bosco:

    Most investors who lose money on a flip don't lose it because they picked the wrong neighborhood or misjudged the ARV. They lose it because they built the rehab budget wrong. Either they missed a line item entirely, or they used numbers from two years ago that don't reflect what labor actually costs today.

    I walked through a live rehab scope with a coaching group last week on a distressed single-family in New Hampshire. A 960-square-foot ranch, listed at $189,000, assessed at $260,000. Good bones — new mechanical systems installed in 2024, public water, sewer, and natural gas. Significant deferred maintenance: pipes burst over winter, water damage, full plumbing replacement needed, new roof, no garage, heavy tree coverage.

    We built the budget line by line. Here's exactly how I do it — and the specific numbers we landed on.

    Start With the Non-Negotiables

    Every flip has a set of costs you cannot avoid once you've committed to the scope. On this property, those were:

    Roof replacement: On a property this size in NH, a new roof runs approximately $10,000. That's not negotiable — the property needs one, and buyers will flag it on inspection if you try to leave it.

    Full plumbing replacement: Pipes burst means you're replacing the system. In today's NH market, fixtures and all, budget $20,000. I've seen investors try to spot-repair this. It costs more in the long run and creates liability.

    New kitchen: A basic but functional kitchen replacement — new cabinets, counters, appliances — runs approximately $10,000 on a property this size. Not a designer kitchen. A clean, updated kitchen that passes the buyer sniff test.

    New bathroom: $8,000 for a full bath refresh. New tile, vanity, fixtures. Budget this regardless of current condition — if everything else is updated and the bath looks original, it will hold back your ARV.

    These four items alone account for roughly $48,000 of the scope. Everything else is built on top of this base.

    The Middle-Cost Items Most Investors Underestimate

    Once the non-negotiables are covered, the budget typically goes off the rails in three areas:

    Plumbing fixtures and rough-in: I include this separately from the full plumbing line — rough-in for a new bathroom in the basement, if you're adding one, has its own cost. Budget it independently.

    Flooring: LVP is running approximately $3 per square foot installed in most NH markets right now. On a 1,000-square-foot property, that's $3,000. Carpet is cheaper but often not appropriate for the resale spec you're targeting. Budget the LVP unless you have a specific reason not to.

    Landscaping and exterior: This is where I see the most under-budgeting. I walked this property on Google Street View before running a single number. The comps — properties that sold at $385,000 to $400,000 in the same neighborhood — had cleared lots and manicured curb appeal. This property had heavy tree coverage and an overgrown lot.

    Tree removal runs $10,000 or more depending on size and access. General landscaping to get competitive: another $2,500 to $5,000. The first budget draft had $2,500 for landscaping. The real number was closer to $15,000.

    (Note: Image recommendation — a side-by-side photo showing a cleared lot comp versus the subject property's tree coverage would be effective here.)

    The Line Item Everyone Forgets: Interior Painting

    I saved this for its own section because it's the single most commonly missed item I see.

    Interior painting has increased significantly. In the NH market, painters are currently charging approximately $5 per square foot. A year or two ago, that number was $2 to $3 per square foot.

    On a 1,000-square-foot property, that's $5,000. On a 1,500-square-foot flip, $7,500. On a 2,000-square-foot property, $10,000.

    When we built the initial budget live with the coaching group, painting wasn't on the sheet. We came up with $72,000. When we added it back in, the number became $88,000 to $90,000.

    That $16,000 to $18,000 gap is material. At $189,000 acquisition and $88,000 in rehab — you need your ARV assumptions to hold at $385,000 or better just to have a reasonable margin at conventional financing. At hard money rates, the deal gets tight.

    The fix is simple: add a painting line item to every budget, use current rates, and do it before you finalize your offer — not after.

    Don't Skip the Structural Contingency

    Every rehab budget should include a structural contingency line. Not because you necessarily expect structural issues — but because you will sometimes find them.

    On this property, I built in $2,000 as a minimum. On larger properties or anything with a known foundation concern, that number goes up. But zero is not an acceptable number. If you've walked the property and confirmed everything looks clean, the contingency may not get touched. That's a good outcome. What you're protecting against is the $3,000 discovery mid-project that wasn't in the scope.

    The Completed Budget

    For the property we analyzed, here's where we landed:

    1. Roof: $10,000
    2. Siding (painted, not replaced): $6,000
    3. Landscaping and tree removal: $12,500–$15,000
    4. Full plumbing replacement: $20,000
    5. LVP flooring: $3,000
    6. New bathroom: $8,000
    7. Kitchen: $10,000
    8. Interior painting: $5,000
    9. Sheetrock and drywall repairs: $2,000
    10. Structural contingency: $2,000
    11. Dump fees: $500–$1,000

    Total: approximately $79,000–$82,000 before the basement scenario. Add the basement finish with bedroom and bath: $88,000–$92,000 total.

    The Bottom Line

    A flip budget isn't a document you build once at the start and forget. It's a working tool you refine as you learn more about the property. The line items in this article aren't definitive — costs vary by market, contractor relationships, and property condition.

    What is consistent: the properties that perform on a flip are the ones where the investor knew their numbers before they made the offer. The surprises that kill margin are usually things that were knowable — if you'd walked the street, updated your labor rates, and remembered to put painting on the sheet.

    Build the budget like the margin matters. Because it does.

    Great break down of the process!The math never lies.


  • Drew SygitBusiness Member
    Property Manager · Royal Oak, MI · Member since 2012 · 12k+ posts · 9k+ votes
    5mo

    Well done!

  • Contractor · TX · Member since 2022 · 21 posts · 4 votes
    5mo

    Looks great 

  • Member since 2011 · 152 posts · 113 votes
    5mo

    My method of organizing a rehab for a flip or even for turning over an apartment is to carefully scrutinize every aspect of every surface/room/feature of the property. Make a list everything from the smallest task to the largest such as "remove the old robe hook from the inside of the bath door" to "full exterior paint job" for example. I typically dictate these notes into my phone, email it to myself, clean up the text, and then print it out. From this list I make a separate materials list and contractor list. The detailed list for a contractor to use to bid as well as to follow throughout the job is derived from this list. My point is that such a process will yield an accurate budget.

    I detail this process in my book "Build Real Estate Wealth: Enjoy the Journey of Rental Property Investment."

  • Contractor · NYC/Los Angeles · Member since 2019 · 91 posts · 55 votes
    5mo

    This is the right way to think about a budget. You have to start with systems and risk before you even look at the finishes. On a distressed property I never let paint or flooring or cabinets drive the first pass. I start with the roof and structure and water intrusion and electrical and plumbing and HVAC and sewer and drainage. Those are the items that stop a project or force expensive rework.

    One thing I always add is a confidence rating next to every line item. For example if I have a bid in hand for the roof I mark it high confidence. If the HVAC is an unknown until startup or if the electrical panel is visible but the walls are closed I mark those low. That tells me exactly where the budget is solid and where the contingency actually needs to sit.

    I also separate the cosmetic scope from the market positioning scope. Some upgrades are mandatory to hit your exit price while others are just nice to have. When a deal gets tight that separation keeps you from cutting the wrong things and hurting your ARV.

    For a small ranch sequencing is everything. If the roof and mechanicals and rough trades are not settled first you are just asking for finished surfaces to get damaged. A clean budget is not just a list of prices. It is a plan to make sure you do not spend the same dollar twice.