Who Should Make the Rehab Budget?
You find a property. The purchase price looks good. The ARV looks even better. It needs work, but that's fine. You've done the numbers.
You figure the rehab at $80,000. Then the real numbers start coming in and $80,000 begins looking suspiciously like $120,000.
The deal may still work. But it's not the deal you thought you were buying. That's essentially the situation in the topic I was given to think about today.
And it got me wondering about something more basic: Who exactly should make the rehab budget?
I can make one. I'm the investor. I've seen properties. I know approximately what roofs, kitchens, bathrooms, flooring and HVAC cost. I can measure square footage, price materials and look at previous projects. But I'm not necessarily the guy who's going to do the work. So I bring in a contractor. That should solve the problem.
Except now we have another problem. The contractor wants the job. If he walks the property and tells me: "This thing is a mess. Don't budget $80,000. You're looking at $120,000, maybe more., he may be giving me excellent advice. He may also have just talked me out of buying the property - and himself out of a $120,000 job.
So what's his play? I'm not accusing contractors of dishonesty. I'm asking about incentives. If three contractors want the job, there's naturally some pressure to give me the best number. And unfortunately, the best number before closing is usually the lowest one.
One guy says $82,000. Another says $95,000. The third says $118,000. Which one do I want to believe? Probably the first guy. Not necessarily because I think he's the best contractor. Because $82,000 makes my deal work.
Then I close. The dumpster arrives. Materials are ordered. Half the place is demolished. His crew and equipment are on site. And that's when the conversation changes.
"Now that we've opened this wall..."
"The electrical is worse than it looked."
"Those pipes should really be replaced while we're here."
"That wasn't included in the original estimate."
"We can leave it, but I wouldn't recommend it."
Some of that is completely legitimate. You cannot see through walls. But my negotiating position is also completely different now. Before closing, contractors were competing to get onto the property. Once the place is torn apart and somebody's crew and equipment are already there, changing contractors costs me money and time. Now he calls the shot a little more than I do.
So perhaps getting three estimates doesn't solve the problem either. If I automatically choose the lowest, I've simply created an auction in which everybody has an incentive to tell me what I want to hear.
And there's another uncomfortable participant in this little conspiracy: me. If I need the rehab to be $80,000 for the deal to make sense, I'm hardly an impartial judge of whether the $80,000 estimate is realistic. The $120,000 contractor might be the expensive idiot. Or he might be the only person in the room telling me the truth. I won't know until later.
So who should make the budget? Should I pay a contractor only to estimate, with the explicit understanding that he's not bidding for the work? Should I hire an independent construction estimator? Should I get three or four bids and ignore the lowest one? Should I rely primarily on costs from my previous rehabs? Should I have my regular contractor estimate projects precisely because he knows he'll get future work and doesn't have to win this particular job? Or should the answer be some combination of all of these?
And maybe we're making another mistake by asking for one number in the first place. Perhaps a rehab budget should have three numbers:
What I genuinely expect it to cost;
What it could reasonably cost if things go wrong, and:
At what number does the deal stop making sense?
That last one interests me most. If this is a fantastic deal with an $80,000 rehab, still a good one at $100,000 and merely less profitable at $120,000, fine. But if $80,000 makes me money and $100,000 wipes out the profit, I don't really have a rehab-estimating problem. I have a deal with almost no room to be wrong.
And construction seems like a particularly bad place to require everybody to be exactly right. So, especially those of you who do a lot of rehabs: Who do you trust to establish your rehab budget before you own the property? And how do you get a realistic number from people who know that the lower their number is today, the more likely there will be a job tomorrow?
- Drago Stanimirovic