Paying contractors only for finished work: how do you set up the draw schedule?
Most of the contractor horror stories on here have the same root: money went out ahead of the work. Once a crew has been paid for more than they've finished, you lose most of your leverage to get them back on site.
A simple structure that keeps payments behind progress:
Write the draw schedule into the contract before work starts. Each draw is tied to a milestone anyone can check, like "rough plumbing and electrical passed inspection" or "drywall hung and taped", not "about 50% done."
Put a dollar amount on each milestone that's close to the value of the work in it, so no single draw gets ahead of the job.
Verify before you release. Walk it, or get dated photos and the inspection card if you can't be there.
Keep a holdback until the final punch list is finished and lien waivers are in hand. Many owners hold back 5 to 10%, but some states cap retainage, require it, or set when it must be released, so check the amount and release terms with an attorney.
If materials have to be bought up front, pay the supplier directly or reimburse against receipts instead of handing over a lump sum.
Keep a running total of contract value, paid to date and remaining for each contractor, so you always know if anyone is ahead of their work.
What percentage do you hold back until the final walkthrough, and has a contractor ever pushed back on it?