The kitchen cabinets are brand new. The electrical work is half done. The seller says the house is “almost finished.”
I’d bring a contractor and have them price two things separately: what it’ll cost to finish and what it’ll cost to redo. I’d also check the permit and inspection history before counting any of the work as complete.
A half-finished flip can be a good find. It depends on how much of the work you can actually keep.
What’s the first thing you’d check before buying someone else’s unfinished flip?
Hi Mykah — great question, and I'd put permits at the top of the list, but right next to it I'd put a full inspection of the work that's already been done. With an unfinished flip, the risk isn't just what's left to finish — it's whether the work already in the walls was done right, and a good inspector can tell you a lot about that. I'd also get a contractor's bid for both finishing the work and redoing any of it, because the cheaper number isn't always the real one. And check for unpaid bills or liens before you close, since an unfinished project can come with contractor debts attached to the property. Price it as if you'll be fixing someone else's shortcuts, and if the numbers still work after that, it can be a real opportunity.
Mykah, I've bought two unfinished flips, and honestly I'm not in a hurry to buy a third. They can work, but they're almost always more trouble than they look, and your point about the cost to finish versus the cost to redo is the right place to start.
The first thing I'd check is what's behind the new finishes. Brand-new cabinets and fresh drywall look like progress, but they can also hide the very work you most need to see: wiring, plumbing, framing and any water damage. If the previous owner closed up walls before rough-in inspections, you may end up opening them again whether you want to or not. Kerry is right that permits come first. Look up the permit history yourself instead of trusting the seller, and if work was done without permits, assume you'll pay to have it inspected or redone.
The second thing is why the flip stopped. People usually don't walk away from a project that's going well. They ran out of money, fell out with a contractor or found a problem bigger than they planned for. Each of those can follow you. Unpaid contractors can file liens, and if the previous owner ran into a foundation or sewer issue, it's still there for you. Run a title search for liens and ask directly who did the work and whether they were paid in full.
What I took away from both of mine is to price it like a full rehab, not a partial one. Give the existing work only as much credit as you can verify, assume some of it gets torn out and leave a bigger contingency than normal. If the deal still works on those numbers, great. If it only works because the house is "almost finished," I'd let someone else find out what "almost" means.
From the lending side, I'd add getting lien waivers from every sub, not just the GC. Half-finished electrical with no final waiver is how you end up inheriting someone else's lien. And if the last owner pulled permits and walked, a lot of lenders won't fund rehab draws until those get closed out or transferred to your contractor, which in some Florida counties eats a few weeks on its own.
Agree on permits first, but I'd go one level deeper: pull the inspection history on each permit, not just whether a permit exists.
A few things I'd look for on the city portal before counting any work as done:
Which rough-ins actually passed. If drywall is up but rough electrical or plumbing never passed, you may be opening walls back up, and that cost belongs in the "redo" column.
Failed inspections with open corrections. Those are known problems the seller may not mention.
The expiration clock. Many permits lapse after a stretch with no passed inspection (often around 6 months). A stalled flip can mean re-applying and paying again.
Unpaid subs. Ask for lien waivers from whoever did the work so far, and have title check for recorded mechanic's liens. A sub who wasn't paid on a stalled job is a common surprise.
Then put a time cost on it, not just a repair cost. If getting the permits back in good standing adds 30 to 45 days before you can even request a draw, that holding cost is part of the price.
My first request to the seller would be a stage record. That means a photo of each stage taken before it was closed, with the date. Behind new cabinets, this is the only way to see wiring and pipes without opening walls.
With a price per stage, the buyer, the contractor and each trade know what is closed, what is open and what comes next. Nobody waits for another trade, and nobody argues over "almost finished".
On your side, do draws follow stages like this, or a percentage of completion?
The biggest advantage of a stage record is knowing exactly what you're paying for. Without dated photos and inspection approvals, even brand-new work should be treated as unverified until a contractor has checked it. I'd also want to know who completed each stage and whether the subcontractors were paid in full. It makes a big difference when you need to decide what can stay and what needs to be redone.
Love what you're working on, Mykah. Feel free to send over a connect request. I'd be happy to intro you to a lender I partner with wo offers custom financing options for deals like this.
We call those investor specials! I actually have an alert when one gets listed on my Redfin app.
Check for permits. If there is none on file then walk away unless its already down to the studs.
If down to the studs already, check the foundation and overall structural integrity.
Was looking at an investor special the other day with a detached Garage converted to an ADU. Turns out the ADU was illegal and city wanted it converted back to a garage or get a variance, so a Stop Work Order was issued. If it was in a "better" zipcode I would of worked the deal but because it wasn't its a easy pass
Most times a simple conversation with the listing agent will get you the story. Don’t be scared to ask for your price based on the risk involved.