For investors working rehabs in Duval and the surrounding counties right now: how are you paying your contractors?
I'm curious what's actually working on mid-size jobs in Jacksonville:
Do you pay on a draw schedule tied to finished phases, like demo, rough-ins passed, drywall, finish, final? Or on dates?
Do you hold back a final payment until the City of Jacksonville final inspection is signed off, or until the punch list is done?
When you vet a new contractor, do you stop at MyFloridaLicense.com and a certificate of insurance, or do you also check the city's contractor search and past permits?
I run a Florida home services marketplace, so hiring and paying contractors safely is the problem I think about every day. I'd like to hear how local investors handle it on real projects, especially anyone who got burned once and changed how they pay.
Good questions, Jason. In the estimate reviews I do, the draw schedule works best when it is tied to finished phases you can verify, not to dates. Demo done, rough-ins passed, drywall done, finish done, final inspection signed off. Each draw should match the line items in the written scope for that phase, so you can check the work against the scope before you pay. I would hold back a final payment until the punch list is done and the final inspection is signed off, and write that into the agreement up front. For vetting, a license check and a certificate of insurance are a start, but I would also ask for past permits and recent references, and compare the bid line by line against the scope so you know what is included and what is an allowance. That is the part that usually causes the payment disputes later.
Ioannis covered the draw schedule well. I'd add lien waivers. Get a signed waiver from the contractor and every sub with each draw, before the next check goes out. Florida also has a final payment affidavit for the end of the job, so ask your title company or attorney how it applies to you. Keep the first deposit small, and pay big material suppliers directly. That way a missed sub payment can't turn into a lien on your property.
Jason, adding two Florida-specific pieces to what Ioannis and Mazen said.
Keep a log of every Notice to Owner you receive. Under Florida's lien law, those are the subs and suppliers who can still lien the property even after you've paid the GC, so that list tells you exactly whose lien releases you need with each draw.
And record the Notice of Commencement early. On most permitted jobs in Florida it has to be recorded, with a copy posted at the site, before the first inspection. If it isn't, the first inspection can get turned away and every phase behind it slides, which pushes your first draw back too.
On the holdback, I'd tie the final payment to both the city's final inspection and the punch list, since the final inspection doesn't check finish quality. Not legal advice, so worth confirming the details with your title company or a construction attorney.
Thanks Ioannis, Mazen and Jaxon, this is really helpful. Tying draws to finished phases with a holdback until final inspection seems to be the common thread here. Jaxon, do you keep the Notice to Owner log yourself or does your title company track it?
On the certificate of insurance: call the agent listed on it and confirm the policy is active, since a COI is only a snapshot. Check that it shows general liability and workers' comp (or a valid exemption), and ask to be named as additional insured. Get a fresh one before each job, because policies can cancel mid-project.
Short answer: I'd pay on finished phases, but I'd treat the county record as the milestone, not the contractor's word.
Before the first draw, pull the Notice of Commencement from the Duval County Clerk's official records. In Florida it has to be recorded and posted on site before the first inspection, and it lapses after one year unless the notice says otherwise. If a long rehab runs past that date, payments made after expiry are treated as improper, so the date belongs on your draw calendar.
On the final payment: hold it until the City of Jacksonville permit shows the final inspection signed off, not until the contractor says the punch list is done. Those are two different things, and only one of them is in the public record.
Lien waivers are the part most people skip. Under Florida §713.20 you can ask for a waiver before you pay the GC, and once a sub has served a Notice to Owner you need that waiver before each payment. Pay the GC without it and you can end up paying the same work twice.
This is not legal advice. Have a Florida construction attorney confirm the timing against your contract.
When the permit record and the contractor's invoice disagree on scope, which one do you go with?
Good question, Yi. I would go with the permit record and the written scope of work, not the invoice on its own. The invoice is a billing document. The permit record and the signed scope are the record of what was agreed and approved. If they disagree, I would pause that line item, ask the contractor to explain the difference in writing, and only pay it once the scope is corrected or the change is agreed in writing. Paying the invoice as written can turn a scope gap into a dispute later, and the permit record is what an inspector or lender will check against.