Build to Rent - Duplex #1 on a $5,000 City Infill Lot in Waterloo, Iowa
I've owned rentals and run property management (EPM Iowa) and a flooring/kitchen/bath company in Waterloo/Cedar Falls for years. This is my first ground-up build to rent. The goal is four duplexes by the end of 2027 if this one pencils out the way I think it will. I'll post updates here as it goes, the good and the mistakes.
The Lot
The City of Waterloo sells vacant infill lots to builders. I bought one for $5,000. It's 90' wide x 128' deep, zoned R-2, in the Maywood neighborhood. The development agreement gives back the $5,000 lot cost plus $7,500 per unit after the certificate of occupancy, so $20,000 total. I also got an option on the lot next door for another $5,000 once this one is done.
The Product
Side-by-side duplex, 3 bed / 2 bath each side, attached garage each side, slab on grade, simple gable roof. Two independent 2x4 stud walls with Type X drywall for the 1-hour fire separation.
Budget
My target is $325,000 actual cost. Right now my working budget is $336,000, so I'm about $11,000 over and still cutting. The bid package I sent to the bank came in at $369,316. The difference is mostly concrete and dirt work:
Concrete: $25,456
Dirt work, water and sewer: $13,625
Shell materials (trusses, framing, roofing, siding, windows): $72,068
Getting two or three bids on every line has been worth thousands. And multiple bids helps me see if one contractor missed something.
Financing
Local bank: 7.05%, 5-year fixed, 25-year amortization, 80% LTV. At $280,000 borrowed, that's about $23,855/yr in principal and interest.
Rough Numbers (conservative)
Rent: $1,500/side = $36,000/yr. This is conservative, I think I can get closer to $1800 per side.
Taxes: $4,500/yr. Also get a step down 10 year tax abatement on the lot improvements.
Insurance: $2,500/yr
NOI before vacancy and maintenance: about $29,000
Debt service: about $23,855
The bank wants 1.30 DSCR, which is about 1.22 at $280K, so I'll put more cash in to get there.
Mistakes and Surprises So Far
Lot coverage. R-2 caps lot coverage at 35% (building plus garage). My first plan was 281 sq ft over. The city caught it right before concrete. I shrank the building to 78'-2" x 51'-7" and moved it back to 50' from the front. Check lot coverage before you draw anything, not just setbacks.
Addresses. I had four different address numbers floating around on bids, utility forms, and insurance. Get the official address issued early.
Unit size vs. lot coverage fight each other. The city wants big units and a small footprint. Doing that on one story is tight.
Timeline
Lot closed Nov 6. Dirt work started the week of Nov 16. Footings start today, Nov 19. Goal is concrete done by Dec 1 and framing after that. This is Iowa, so winter and getting power hooked up in time are the biggest risks.