Anyone really interested in construction??

Anyone really interested in construction??

Real Estate Investor · the villages, FL · Member since 2008 · 5k+ posts · 3k+ votes

I just replied to a thread and it made me wonder. I'm not on BP very often any more, but I still have a vast experienced history. One thing I haven't seen much is a how to or step by step approach to actually building a home with info from start to finish. I've probably done close to 100 spec homes in 3 different states. I assure you it isn't rocket science.
I currently have 2 under const in UT and a couple more in so TX. I've also built in OR and CA at other times. I'm not a general contractor, just a speculator. There are many ways to make money on your own home with proper knowledge and location.
If there is enough interest, I'd be willing to post regular reports on the process. If not enough interest, no problem either. Have a good day. Rich

4Reply
939 views

Most Popular Reply

Contractor · Denver, CO · Member since 2009 · 399 posts · 166 votes
14y

I think this thread has done a great job outlining the basic steps needed to build a house. It has also shown great examples of the potential profits available in spec home building. I would caution anyone who is considering building their first spec home to do your homework. Unless you are a GC, you probably don't want to start two new businesses at the same time. One business being spec home building and the other being General Contracting.

Here is a more detailed list of construction items you will have to consider when building a new home. I believe somewhere in this thread, absorption rate was mentioned and that could be the most important statistic to know. Just like a flip, you need to have multiple exit strategies for a spec home.

This list was poached from contractortalk.com

House/with attached Garage

General Conditions
Finalize plans and develop estimate with owner, architect
Sign contract and notice to proceed

Apply for Permits
Secure foundation permit
Secure framing permit
Secure electrical permit
Secure plumbing permit
Secure HVAC permit
Secure miscellaneous permits

Site Work
Clear and grub lot
Excavator estimated houly
Skid steer estimated hourly
Trucking estimated hourly

Topsoil stripping
Skid steer estimated hourly
Trucking estimated hourly
Pavement and sidewalk removal
Skid steer estimated hourly
Trucking estimated hourly

Rough grading
Skid steer estimated hourly
Relocation of existing natural drainage
Excavator estimated houly
Skid steer estimated hourly
Removal of unsuitable soil
Skid steer estimated hourly
Trucking estimated hourly

Access roads
Skid steer estimated hourly
Trucking estimated hourly

Detours

Protection of existing structures and utilities

Environmental considerations

Install temporary power service

Install underground utilities

Foundation

Locate building

Survey

Install batter boards

Excavate for foundations

Excavator estimated houly

Drilling for garage piles
Skid steer estimated hourly
Trucking estimated hourly

Forming

Footings
Total lineal feet of footing
Total width of footing
Total thickness of footings
Total cubic meters of footings

Foundations walls
Total lineal feet of walls
Total width of walls
Total height of walls
Total cubic meters of walls

Grade beams
Total lineal feet of beam
Total width of beam
Total height of beam
Total number of 12"x12' concrete pile
Total cubic meters of beams and piles

Cure basement walls for 7 days
Strip basement wall forms
Waterproof/insulate basement walls
Perform foundation inspection
Backfill foundation
Skid steer estimated hourly

Framing house and attached garge
Install 1st floor joists
Mud sill achor bolts
Sill gasket
2x6 Treated mud sill
2x10 Spruce 4 ply beam
3" Adjustable steel telepost
2x10 Spruce joisting
2x10 Spruce rim joists
2x2 bridging
Single joist hangers/nails
Double joist hangers/nails
3 1/4" coated nails
Lay 1st floor decking
3/4" T&G Fir sheating
1 1/2" flooring screws
Sub-floor adhesive
Frame 1st floor walls

Exterior walls
Top, bottom and cap plates 2x6 spruce
2x6 spruce studs 92 5/8"
3/8" spruce sheathing
2x10 spruce 2 ply header with 2x6 backer
2x6 garge door rough frame and Brick moulding
3 1/4" coated nails
1 1/2" sheathing staple
House wrap (Tyvek) and tape
3/8" house wrap staples

Interior walls
Top, bottom and cap plates 2x4 spruce
2x4 spruce studs 92 5/8"
2x4 spruce single plate door header

Plumbing wall
Top, bottom and cap plates 2x6 spruce
2x6 spruce studs 92 5/8"
3 1/4" coated nails

Cap plate and exterior wall backing poly flashing
2x10 Spruce 4 ply beam
2x6 drywall backing
Install 2nd floor joists
2x10 Spruce joisting
2x10 Spruce rim joists
2x2 bridging
Single joist hangers/nails
Double joist hangers/nails
3 1/4" coated nails
Lay 2nd floor decking
3/4" T&G Fir sheating
1 1/2" flooring screws
Sub-floor adhesive

Frame 2nd floor walls

Exterior walls
Top, bottom and cap plates 2x6 spruce
2x6 spruce studs 92 5/8"
3/8" spruce sheathing
2x10 spruce 2 ply header with 2x6 backer
3 1/4" coated nails
1 1/2" sheathing staple
House wrap (Tyvek) and tape
3/8" house wrap staples

Interior walls
Top, bottom and cap plates 2x4 spruce
2x4 spruce studs 92 5/8"
2x4 spruce single plate door header

Plumbing wall
Top, bottom and cap plates 2x6 spruce
2x6 spruce studs 92 5/8"
3 1/4" coated nails

Cap plate and exterior wall backing poly flashing
2x10 Spruce 4 ply beam
2x6 drywall backing

Interior stairs and landings

Complete roof framing

Manufactured Roof trusses and gables 24" o.c.
2x6 gable ladders and fascia
2x6 fasica
Cardboard insulation baffels
2x4 truss bracing and strapping
2x4 ridge blocking
1/2 roof sheathing
1/2 sheathing clips
3 1/4" coated nails
2" sheathing staples
3/8" insulation baffle staples
Conduct framing inspection

Dry In

Shingles
210 Asphalt shingles
Ice and water shield
Asphalt ridged cap
1 1/4" shingle nails
Aluminum gable flashing
Roof vents

1st floor exterior doors
Front door 36/80 6 panel with side lite
Weiser brush nickel passage and deadbolt
Back door 36/80 6 Panel
Weiser brush nickel passage and deadbolt
Garage man door to house 36/80 6 panel with closer
Weiser brush nickel passage and deadbolt
Garage doors 9x7 Barcol inusulated with Genie opener

1st floor windows

2nd floor windows

Exterior Finishes

Eaves
Aluminum vented soffit (white)
Aluminum fascia
5" Gutter and down spouts
Stucco
Scaffolding
1 1/2" styrofoam insulation
Stucco base coat
Stucco finish coat
Parging
Stone work
Shingle gables

Exterior Decks and Stairs

Utility Rough-Ins and Complete Concrete
Rough-in plumbing
Conduct rough-in plumbing inspection

Place concrete for basement floor

Rough-in electrical
Conduct rough-in electrical inspection

Rough-in HVAC
Conduct rough-in HVAC inspection

Rough-in communication - phone, cable, computer, alarm

Interior Finishes

Insulation
Wall insulation - 1st floor
R20 fiberglass batt 6ml vapor barrier
Wall insulation - 2nd floor
R20 fiberglass batt 6ml vapor barrier
Ceiling insulation - 2nd floor
R40 Blown in cellulose 6ml vapor barrier
Conduct insulation inspection
3/8" vapor barrier Staples
Tuck tape
Acostical chalking

Drywall
Install drywall - 1st floor walls
Install drywall - 1st floor overhead
Install drywall 2nd floor walls
Install drywall 2nd floor overhead
Tape and float 1st floor drywall
Tape and float 2nd floor drywall

Paint
Texture all except entry and kitchen - 1st floor
Paint all except entry and kitchen - 1st floor
Hang wallpaper entry and kitchen - 1st floor
Texture all - 2nd floor
Paint all - 2nd floor
Paint exterior siding & trim work

Cabinets
Install 1st floor - kitchen cabinets
Install 1st floor - master bath and guest cabinets
Install 2nd floor - hall bath and private bath cabinets
Install chair rails, crown moldings, trim

Finish Plumbing
Complete 1st floor - kitchen plumbing
Complete 1st floor - master bath and guest plumbing
Complete 2nd floor - hall bath and private bath plumbing
Conduct finish plumbing inspection

Finish Electrical
Complete 1st floor circuits to service panel
Complete 2nd floor circuits to service panel
Conduct finish electrical inspection
Complete communications wiring - phone, cable, computer, alarm

Finish HVAC
Complete 1st floor - zone 1 HVAC
Complete 2nd floor - zone 2 HVAC
Conduct HVAC inspection

Carpet, Tile and Appliances
Tile entry, kitchen and baths
Carpet 1st floor
Carpet 2nd floor
Install appliances

Landscaping and Grounds Work
Pour concrete driveway and sidewalks
Install backyard fence
Sod and complete plantings - front yard
Sod and complete plantings - backyard

Final Acceptance

Complete final inspection for certificate of occupancy

Cleanup for occupancy

Perform final walk-through inspection

Complete punch list items

See this reply in the discussion

116 Replies

Jump to latestLatest
  • Real Estate Investor · Chicago, IL · Member since 2008 · 318 posts · 30 votes
    14y
    Originally posted by Rich Weese:
    I just replied to a thread and it made me wonder. I'm not on BP very often any more, but I still have a vast experienced history. One thing I haven't seen much is a how to or step by step approach to actually building a home with info from start to finish. I've probably done close to 100 spec homes in 3 different states. I assure you it isn't rocket science.
    I currently have 2 under const in UT and a couple more in so TX. I've also built in OR and CA at other times. I'm not a general contractor, just a speculator. There are many ways to make money on your own home with proper knowledge and location.
    If there is enough interest, I'd be willing to post regular reports on the process. If not enough interest, no problem either. Have a good day. Rich

    Rich,
    I would definitely be interested in reading/hearing about your reports. Have you given any thought on writing a new construction checklist or maybe a basic pdf on the steps.

    Im not a GC but I have done more than my fair share of rehabs and new construction is something I would like to get into without relying on my GC soley.

    Any info you can provide would be GREATLY appreciated :)

  • Real Estate Investor · the villages, FL · Member since 2008 · 5k+ posts · 3k+ votes
    14y

    Hi Adrian,
    As I stated before, I'm not on BP much any more, and leaving tuesday on a 7 week RV trip to find cooler weather! Yellowstone, Glacier, Jackson Hole, Missoula, Couerdalene, and the Canadian rockies. Just very busy. I've pretty much punted on the homes I'm currently building to my GC in TX and GC in UT. Rich
    p.s. I don't know about a checklist. I'm not a licensed GC and there are probably some on BP that would do a better job.

  • Contractor · Denver, CO · Member since 2009 · 399 posts · 166 votes
    14y

    I think this thread has done a great job outlining the basic steps needed to build a house. It has also shown great examples of the potential profits available in spec home building. I would caution anyone who is considering building their first spec home to do your homework. Unless you are a GC, you probably don't want to start two new businesses at the same time. One business being spec home building and the other being General Contracting.

    Here is a more detailed list of construction items you will have to consider when building a new home. I believe somewhere in this thread, absorption rate was mentioned and that could be the most important statistic to know. Just like a flip, you need to have multiple exit strategies for a spec home.

    This list was poached from contractortalk.com

    House/with attached Garage

    General Conditions
    Finalize plans and develop estimate with owner, architect
    Sign contract and notice to proceed

    Apply for Permits
    Secure foundation permit
    Secure framing permit
    Secure electrical permit
    Secure plumbing permit
    Secure HVAC permit
    Secure miscellaneous permits

    Site Work
    Clear and grub lot
    Excavator estimated houly
    Skid steer estimated hourly
    Trucking estimated hourly

    Topsoil stripping
    Skid steer estimated hourly
    Trucking estimated hourly
    Pavement and sidewalk removal
    Skid steer estimated hourly
    Trucking estimated hourly

    Rough grading
    Skid steer estimated hourly
    Relocation of existing natural drainage
    Excavator estimated houly
    Skid steer estimated hourly
    Removal of unsuitable soil
    Skid steer estimated hourly
    Trucking estimated hourly

    Access roads
    Skid steer estimated hourly
    Trucking estimated hourly

    Detours

    Protection of existing structures and utilities

    Environmental considerations

    Install temporary power service

    Install underground utilities

    Foundation

    Locate building

    Survey

    Install batter boards

    Excavate for foundations

    Excavator estimated houly

    Drilling for garage piles
    Skid steer estimated hourly
    Trucking estimated hourly

    Forming

    Footings
    Total lineal feet of footing
    Total width of footing
    Total thickness of footings
    Total cubic meters of footings

    Foundations walls
    Total lineal feet of walls
    Total width of walls
    Total height of walls
    Total cubic meters of walls

    Grade beams
    Total lineal feet of beam
    Total width of beam
    Total height of beam
    Total number of 12"x12' concrete pile
    Total cubic meters of beams and piles

    Cure basement walls for 7 days
    Strip basement wall forms
    Waterproof/insulate basement walls
    Perform foundation inspection
    Backfill foundation
    Skid steer estimated hourly

    Framing house and attached garge
    Install 1st floor joists
    Mud sill achor bolts
    Sill gasket
    2x6 Treated mud sill
    2x10 Spruce 4 ply beam
    3" Adjustable steel telepost
    2x10 Spruce joisting
    2x10 Spruce rim joists
    2x2 bridging
    Single joist hangers/nails
    Double joist hangers/nails
    3 1/4" coated nails
    Lay 1st floor decking
    3/4" T&G Fir sheating
    1 1/2" flooring screws
    Sub-floor adhesive
    Frame 1st floor walls

    Exterior walls
    Top, bottom and cap plates 2x6 spruce
    2x6 spruce studs 92 5/8"
    3/8" spruce sheathing
    2x10 spruce 2 ply header with 2x6 backer
    2x6 garge door rough frame and Brick moulding
    3 1/4" coated nails
    1 1/2" sheathing staple
    House wrap (Tyvek) and tape
    3/8" house wrap staples

    Interior walls
    Top, bottom and cap plates 2x4 spruce
    2x4 spruce studs 92 5/8"
    2x4 spruce single plate door header

    Plumbing wall
    Top, bottom and cap plates 2x6 spruce
    2x6 spruce studs 92 5/8"
    3 1/4" coated nails

    Cap plate and exterior wall backing poly flashing
    2x10 Spruce 4 ply beam
    2x6 drywall backing
    Install 2nd floor joists
    2x10 Spruce joisting
    2x10 Spruce rim joists
    2x2 bridging
    Single joist hangers/nails
    Double joist hangers/nails
    3 1/4" coated nails
    Lay 2nd floor decking
    3/4" T&G Fir sheating
    1 1/2" flooring screws
    Sub-floor adhesive

    Frame 2nd floor walls

    Exterior walls
    Top, bottom and cap plates 2x6 spruce
    2x6 spruce studs 92 5/8"
    3/8" spruce sheathing
    2x10 spruce 2 ply header with 2x6 backer
    3 1/4" coated nails
    1 1/2" sheathing staple
    House wrap (Tyvek) and tape
    3/8" house wrap staples

    Interior walls
    Top, bottom and cap plates 2x4 spruce
    2x4 spruce studs 92 5/8"
    2x4 spruce single plate door header

    Plumbing wall
    Top, bottom and cap plates 2x6 spruce
    2x6 spruce studs 92 5/8"
    3 1/4" coated nails

    Cap plate and exterior wall backing poly flashing
    2x10 Spruce 4 ply beam
    2x6 drywall backing

    Interior stairs and landings

    Complete roof framing

    Manufactured Roof trusses and gables 24" o.c.
    2x6 gable ladders and fascia
    2x6 fasica
    Cardboard insulation baffels
    2x4 truss bracing and strapping
    2x4 ridge blocking
    1/2 roof sheathing
    1/2 sheathing clips
    3 1/4" coated nails
    2" sheathing staples
    3/8" insulation baffle staples
    Conduct framing inspection

    Dry In

    Shingles
    210 Asphalt shingles
    Ice and water shield
    Asphalt ridged cap
    1 1/4" shingle nails
    Aluminum gable flashing
    Roof vents

    1st floor exterior doors
    Front door 36/80 6 panel with side lite
    Weiser brush nickel passage and deadbolt
    Back door 36/80 6 Panel
    Weiser brush nickel passage and deadbolt
    Garage man door to house 36/80 6 panel with closer
    Weiser brush nickel passage and deadbolt
    Garage doors 9x7 Barcol inusulated with Genie opener

    1st floor windows

    2nd floor windows

    Exterior Finishes

    Eaves
    Aluminum vented soffit (white)
    Aluminum fascia
    5" Gutter and down spouts
    Stucco
    Scaffolding
    1 1/2" styrofoam insulation
    Stucco base coat
    Stucco finish coat
    Parging
    Stone work
    Shingle gables

    Exterior Decks and Stairs

    Utility Rough-Ins and Complete Concrete
    Rough-in plumbing
    Conduct rough-in plumbing inspection

    Place concrete for basement floor

    Rough-in electrical
    Conduct rough-in electrical inspection

    Rough-in HVAC
    Conduct rough-in HVAC inspection

    Rough-in communication - phone, cable, computer, alarm

    Interior Finishes

    Insulation
    Wall insulation - 1st floor
    R20 fiberglass batt 6ml vapor barrier
    Wall insulation - 2nd floor
    R20 fiberglass batt 6ml vapor barrier
    Ceiling insulation - 2nd floor
    R40 Blown in cellulose 6ml vapor barrier
    Conduct insulation inspection
    3/8" vapor barrier Staples
    Tuck tape
    Acostical chalking

    Drywall
    Install drywall - 1st floor walls
    Install drywall - 1st floor overhead
    Install drywall 2nd floor walls
    Install drywall 2nd floor overhead
    Tape and float 1st floor drywall
    Tape and float 2nd floor drywall

    Paint
    Texture all except entry and kitchen - 1st floor
    Paint all except entry and kitchen - 1st floor
    Hang wallpaper entry and kitchen - 1st floor
    Texture all - 2nd floor
    Paint all - 2nd floor
    Paint exterior siding & trim work

    Cabinets
    Install 1st floor - kitchen cabinets
    Install 1st floor - master bath and guest cabinets
    Install 2nd floor - hall bath and private bath cabinets
    Install chair rails, crown moldings, trim

    Finish Plumbing
    Complete 1st floor - kitchen plumbing
    Complete 1st floor - master bath and guest plumbing
    Complete 2nd floor - hall bath and private bath plumbing
    Conduct finish plumbing inspection

    Finish Electrical
    Complete 1st floor circuits to service panel
    Complete 2nd floor circuits to service panel
    Conduct finish electrical inspection
    Complete communications wiring - phone, cable, computer, alarm

    Finish HVAC
    Complete 1st floor - zone 1 HVAC
    Complete 2nd floor - zone 2 HVAC
    Conduct HVAC inspection

    Carpet, Tile and Appliances
    Tile entry, kitchen and baths
    Carpet 1st floor
    Carpet 2nd floor
    Install appliances

    Landscaping and Grounds Work
    Pour concrete driveway and sidewalks
    Install backyard fence
    Sod and complete plantings - front yard
    Sod and complete plantings - backyard

    Final Acceptance

    Complete final inspection for certificate of occupancy

    Cleanup for occupancy

    Perform final walk-through inspection

    Complete punch list items

  • Real Estate Investor · the villages, FL · Member since 2008 · 5k+ posts · 3k+ votes
    14y

    See! I knew that would happen! Great job Emilio. Anyone interested in Const, should copy this. Rich
    p.s. This is a better list than mine!

  • Developer · Westfield, NJ · Member since 2012 · 25 posts · 7 votes
    14y

    Rich,

    This is a very interesting topic, I actually have 3 parcel of land right n Newark,NJ in the north side area, much decent than the rest of Newark. I have had them for about 2 years now, and I keep on trying to find the right developer but the numbers dont make sense. It has come down to pretty much cutting them out and taking things into my own hands. I would really like some advise, and experience sharing, if you could please.

    Wish you and yours well,
    John Rod.

  • Investor / Developer / GC · Manassas, VA · Member since 2013 · 229 posts · 39 votes
    12y

    @Rich Weese great post!

    @Emilio Ramirez That's a great list for people to begin with and modify as they do their own projects. I'm guessing your in a colder region than we have here in Virginia.

    To all, other than traditional bank financing for our spec units, what options should we look into? Does anyone have any referral's? We build 2-3 homes a year and clients pay cash (yes, insane) or already have qualified for construction to perm financing. I'm aware of subordinating the owners land to the bank and buy downs. We are a very HOT market and I have several single lots and developments being offered all the time but, my hurdle to spec home building always is (and probably will always be) finacing.

  • Denver, CO · Member since 2012 · 350 posts · 175 votes
    12y

    Thanks for this post @Rich Weese ...Very interested in this topic myself as well.

  • Real Estate Investor · the villages, FL · Member since 2008 · 5k+ posts · 3k+ votes
    12y

    Steve H- You might check with general contractors in your area. I know that here in UT most of the GC's use the SAME private lender on specs and I've used him also. 9% and 2 pts for 6 month loan is going rate. There are probably the same options in your area-most GC's have little cash,imo.

    Douglas- thanks and good luck.Building 4-8 units would be a good way to start, if possible. Rich

  • Denver, CO · Member since 2012 · 350 posts · 175 votes
    12y

    @Rich Weese thinking yes to both haha...for sure my central objective is to break ground by the end of Q3 2014.

  • Real Estate Investor · the villages, FL · Member since 2008 · 5k+ posts · 3k+ votes
    12y

    Brilliant minds think alike.....

  • Developer · Charlotte, NC · Member since 2014 · 208 posts · 101 votes
    12y

    Has anyone ever used preconstruction investors to fund their specs. I used too all the time and it worked great did know if anyone else does the same?

  • Investor / Developer / GC · Manassas, VA · Member since 2013 · 229 posts · 39 votes
    12y

    @Rich Weese thanks for the tip. I'm attending some up coming meetings and will start asking around. Those kind of rates would be acceptable. Cash flow IS king.

    @Kenneth Bell This is a new one to me. Would you happen to have a web link or contact? Thx

  • Developer · Charlotte, NC · Member since 2014 · 208 posts · 101 votes
    12y

    Rich,

    The concept is simple I build and sell to investors pre-construction at a lower price. When we market and sell, they get the spread. It works well in hot markets. I build a spec that pre appraises for 320k I give it to my pre construction investor at 285k he secures construction loan. My marketing team markets right away. When we sell that spread is his. He has the option to sell at whatever price he likes. 60% of my investors had contracts before the CO. Worked well in high demand markets. I made a little less but the leverage was in the house and investors got great returns. Not sure if anyone else used the strategy.

  • Philly Area, PA · Member since 2008 · 297 posts · 27 votes
    12y

    Thanks Rich and everyone else, this is an awesome thread! Roc

  • Developer · Lafayette, LA · Member since 2016 · 11 posts · 0 votes
    7y

    Thank you Rich!

  • Property Manager · San Bernardino, CA · Member since 2014 · 473 posts · 238 votes
    7y
    Originally posted by @Rich Weese:

    .. Any Woman owned mgmt companies there? I'd love to see how she has done. She was one of the best managers I ever had, and she was nearly brand new! Keep posting and welcome to BP. Rich

     I'm happy to see how open minded you are Rich! Many developers that I know would prefer to work with men. I think we should all consider working with more businesses that are owned by women!

Join the conversationCreate a free account to reply, vote on answers and follow this thread.