Which fix & flip mistake have you seen hurt a project the most?

Which fix & flip mistake have you seen hurt a project the most?

Charles WalkerBusiness Member
Real Estate Consultant · Member since 2025 · 32 posts · 2 votes

A lot of flips do not get into trouble because of one catastrophic event. The margin often gets chipped away by several smaller misses that compound.

Seven areas I think are worth stress-testing before moving forward with a project:

·   Acquisition price: Did you leave enough room for the project to absorb normal variability?

·   Repair budget: Is the scope complete, and is there enough contingency for items that show up after demolition?

· ARV: Are you using relevant comparable sales, or the value the deal needs in order to work?

·   Contractor: Have you vetted workmanship, references, scheduling, licensing or insurance where applicable, and the ability to finish?

·   Renovation level: Are the finishes appropriate for the neighborhood, price point, and target buyer?

·   Holding costs: What happens if the project takes two, three, or four months longer than planned?

·   Exit strategy: If the resale plan changes, is there a realistic Plan B?

For example, if a $60,000 rehab turns into $78,000, $18,000 of the projected margin is gone before considering any other changes. If an expected $400,000 resale becomes $375,000, that creates another $25,000 difference. The point is not the specific numbers; it is how quickly several modest misses can stack up.

Which of these has caused the most trouble in your projects, and what process do you use to catch it before closing?

0Reply
748 views

7 Replies

Jump to latestLatest
  • Real Estate Agent · Kansas City · Member since 2018 · 4k+ posts · 3k+ votes
    3w

    Not scoping the sewer. Always do that

    • Charles WalkerBusiness Member
      OP
      Real Estate Consultant · Member since 2025 · 32 posts · 2 votes
      3w

      Good point, Caleb.

      A sewer camera inspection belongs on the due diligence checklist. An unexpected sewer line repair can hit both the rehab budget and the timeline, cutting into the projected profit.

      One of my sons is a plumber. He was just telling me about a simple repair that should have cost about $250 turned into a minimum $3,000 repair because of issues that could not be seen initially.

      Have you had a project where a missed sewer issue became a major expense?

  • James JonesPro Member
    Investor · Collierville, TN 38017 · Member since 2017 · 842 posts · 605 votes
    3w

    The two that have hurt me most across 236 properties:

    1. Under-scoping the rehab, especially missing conversion costs. I convert 2/1s to 3/1s and 3/1s to 4/2s, usually adding 400-650 sq ft or turning a carport or garage into a master bed and bath. That's where the margin lives, but you have to scope it fully upfront, permits included. The $60K-to-$78K drift you described is exactly how a deal dies - by inches, not by one catastrophe.

    2. Buying the wrong ARV. I buy under $100K in Memphis ZIPs like 38109 and 38114 with ARV $180K-$265K. The ARV has to come from real sold comps, not the number the deal needs to work. If I can't prove ARV on comps, I pass.

    The fix for both is the same: a ruthless buy box. 3BR+, 1% rule, Section 8 rents $1,395-$1,950. If the deal doesn't fit the box, no amount of optimism fixes it.

    • Charles WalkerBusiness Member
      OP
      Real Estate Consultant · Member since 2025 · 32 posts · 2 votes
      3w

      James, "the ARV has to come from real sold comps, not the number the deal needs to work" is a point worth emphasizing.

      Your conversion examples also show why the rehab scope needs to account for the finished layout and permit requirements upfront. Adding a bedroom or bath changes more than the square footage.

      A clearly defined buy box gives you a reason to pass before optimism starts rewriting the numbers.

      With your Memphis conversions, which cost is most often overlooked when investors prepare their initial rehab budget?

  • Crystal SmithPro Member
    Moderator
    Real Estate Broker · Chicago, IL · Member since 2014 · 2k+ posts · 1k+ votes
    2w

    Total reliance on recently sold properties within the past 6 months to determine ARV and not monitoring the contingent or pending that will eventually become the comparables for selling the property once the property goes on the market later.

    • Charles WalkerBusiness Member
      OP
      Real Estate Consultant · Member since 2025 · 32 posts · 2 votes
      2w

      Good point Crystal. Closed sales show where the market has been, while pending and contingent listings can help indicate where it is heading—although the final sale price is not confirmed until closing.

      That makes monitoring the market throughout the rehab just as important as establishing the initial ARV. A project can stay on budget and still lose margin if buyer demand or pricing shifts.
      If it is a REHAB that takes longer than expected the difference may be even greater.

      What signals do you watch most closely—price reductions, days on market, or how quickly comparable properties go under contract?

  • Ryan BrownPro Member
    Real Estate Agent · Louisville, KY · Member since 2022 · 32 posts · 5 votes
    3d

    Charles, you listed holding costs, but nobody has really talked about it yet, and I think it's the one that sneaks up on people the most: time.

    Every month the project runs long, you're paying for it, and on a hard money loan that adds up fast. Say you borrow $250,000 at 12%. That's about $2,500 a month in interest alone. Add taxes, insurance and utilities and you're probably near $3,000 a month. A flip planned for four months that takes seven just cost you around $9,000, and that's before any extension fees if you run past the loan term.

    The rehab is only part of it. The clock keeps running after the work is done too. In my market, Louisville, nearly 1 in 4 active listings has been sitting 90+ days right now. If you budgeted 30 days to sell and it takes 90, that's two more months of payments on top of any delays during the rehab.

    It also stacks with the other misses you listed. The contractor runs late, so the timeline slips. The market softens while you wait, so the ARV drops. Then the house sits, so you cut the price. Each one hurts on its own, but together they can wipe out a deal.