How are you guys verifying rehab budgets before funding?

How are you guys verifying rehab budgets before funding?

Springfield, Sangamon County · Member since 2026 · 2 posts · 3 votes

Jered here, real estate broker and veteran in Springfield, IL. Wanted to share something I've been working on and get some honest feedback, especially from lenders.

I kept seeing the same thing happen on rehab deals. A loan gets funded off a one page contractor bid or the borrower's own estimate, then the walls come open and the budget is suddenly way off. Now everybody's fighting over draws halfway through the job and the lender's money is sitting in a half finished house.

So I started writing a line item renovation scope before the deal funds. I walk the property and go room by room and system by system, and every item gets a quantity and a cost. The walk takes about an hour and the report is back the next day.

What really sold me on it was a fire loss property. Smoke and water hide a lot of damage and a quick bid would have missed half of it. Having everything written out gave the lender something they could actually underwrite. Since then two six figure rehab deals have been funded off these scopes.

The way I see it, the lender gets a real number to lend against instead of trusting one contractor. Draws are easier because there's a baseline to check progress against. The borrower finds the surprises before closing instead of after demo. And contractors are all bidding the same work, so you can actually compare quotes.

For the lenders on here, what are you doing right now before you fund? Your own inspector, the contractor's bid, something else? And for the rehabbers, has a bad scope ever burned you on a draw?

Curious how others around Central Illinois are handling it.

3Reply
180 views

4 Replies

Jump to latestLatest
  • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 195 posts · 41 votes
    8h

    @Jered Dennis, after funding, I would group the same lines into stages with a price each, and close each stage with dated photos. Extra work found at demo gets its own line with photo and price before anyone starts.

    When the walls open and the scope changes, do your lenders re-approve the changed line, or does it wait until the next draw?

  • Investor · Cuyahoga Falls, OH · Member since 2026 · 24 posts · 3 votes
    7h

    Thank you for asking this so honestly, Jered.

    The move you made, writing a line-item scope room by room, is the one that protects everybody in the deal.

    What I have learned to pay attention to is getting that scope priced line by line before the funding, not after.

    When a contractor has walked the property and every room is priced out, the lender, the rehabber, and the draw schedule are all working from the same numbers.

    That is when the draws stop becoming fights, because everyone already agreed on what each step costs.

    When the numbers and the story match from the start, the funding side tends to go a lot smoother, because the whole chain can trust what is in front of them.

  • Chicago, Cook County · Member since 2026 · 52 posts · 22 votes
    4h

    The worry is always the walls.

    A line item scope helps, but

    only if it says what it

    couldn't see.

    - List the hidden items as

    allowances: subfloor, drains,

    wiring behind plaster.

    - Write down what was not

    opened or tested.

    - Tie each draw to a finished

    stage with dated photos.

    - Price change orders before

    the work starts, not after.

    I've watched a $20K rehab

    turn into $60K, so I'm a big

    fan of writing the unknowns

    down up front.

    Kyle

  • Lender · Milwaukee, WI · Member since 2026 · 24 posts · 16 votes
    3h

    @Jered Dennis From the lender side, a line-item scope is the right starting point, but it's usually one of three things we look at before funding, not the whole answer:

    1. Independent cost review. On larger rehabs most private and bank lenders have their own inspector or a third-party construction consultant check the scope against the plans and local costs. A good scope makes that review faster, but the lender still wants someone with no stake in the deal to sign off.

    2. Contingency, and whose money goes in first. We typically want 10-15% contingency on cosmetic work and more on fire, water or structural jobs. The bigger question is whether the borrower's equity goes in first. If the lender's holdback funds the early work and the borrower's cash is last in, an overrun lands on the lender.

    3. Borrower track record. A first-time flipper with a perfect scope is still a bigger risk than an experienced operator with a rough one, so experience drives leverage and how tight the draw schedule is.

    On draws, the things that protect the money beyond photos: an inspection before each release, draws paid on percent complete by line item rather than on invoices, lien waivers from the GC and major subs with each draw, and a title date-down before later draws so no mechanic's liens slipped in.

    To Vladimirs's question, most lenders want a written change order approved before the extra work starts, with the overrun paid from contingency or new borrower cash, not pushed into the next draw.