Every investor has a price for everything. Bad roofs, dated mechanicals, and even cracked drywall can usually be solved with a simple credit or price adjustment.
Then there are the structural or environmental landmines where experienced guys won't even bother asking for a re-trade.
They just terminate the contract and eat the option fee.
Whether it’s horizontal foundation shearing on an older block-and-beam, an unpermitted load-bearing span, compromised sewer mains under concrete, or severe drainage grading that pools water right into the crawlspace.
For those actively taking down projects right now: what is the single inspection red flag that is an immediate contract termination for you, no matter how cheap the seller is willing to go?
For me it's active structural movement that an engineer won't bless — horizontal foundation shearing, major differential settlement, or a compromised load-bearing wall. Cosmetic stuff, roofs, HVAC, even sewer lines all have a price, and you can negotiate those. But structural issues in our Memphis clay soil can turn into open-ended money pits, and if a structural engineer says 'run,' I listen. The other one is unpermitted additions over living space — not because it can't be fixed, but because the liability and insurance implications make it a different deal entirely. Everything else, I'll negotiate. Those two, I walk.
Alejandro, the worry with these is that you can't price what you can't see the end of. For me the walk-away isn't always the defect itself, it's signs that someone already tried to hide it.
- Fresh paint or new drywall only on the lower part of basement walls, or only on one wall. That usually means water, and someone wanted it gone before the showing.
- Foundation cracks that were patched and then cracked again. One crack has a price. A crack that keeps coming back means the movement hasn't stopped.
- Water coming in with no clear source and no record of a fix. If the seller can't tell you where it comes from, you're buying a guess.
- Unpermitted work tied into structure or electrical, like a removed wall or a finished basement with no permits. Fixing it can mean opening everything back up.
Any one of those alone might be negotiable with an engineer's or contractor's written number. Two together, I'd walk.
@Alejandro Lopez For me it’s an active foundation or structural failure that can’t be scoped with a single contractor bid. Horizontal shearing, or movement that is still ongoing, is the clearest example.
A cheap price doesn’t change the math, because the real cost is the unknown. Once the engineer opens it up, a $15K problem can turn into a $60K one, and a credit only covers what you can see on inspection day. Structural issues also affect financing, insurance, permitting, and resale. I can’t fix that with a number, and the next buyer will find it too.
Compromised sewer mains under a slab are a close second, for the same reason. You can’t price what you can’t see, and the repair means breaking concrete and sometimes dealing with soil contamination.
My rule is this: if I can’t get a firm, written scope and bid from a licensed pro within the inspection window, I walk. Losing an option fee hurts, but it costs far less than inheriting someone else’s problem.
Curious what everyone else’s hard line is, especially anyone who’s taken a “cheap enough” deal on a structural issue and regretted it.
Alejandro, I've honestly never had an inspector find something that was a nonstarter for me.
Most significant issues with a house, I should be able to see before I ever make an offer. Foundation cracks, sloping floors, water stains, an old roof, drainage problems and obvious DIY work usually show up if you take your time on the walkthrough. If I see something that concerns me, I'd rather bring a contractor out or price it into my offer upfront than find out about it during the option period.
The things I can't see are where the inspection really earns its money. Even then, they usually don't make me walk. If I have the sewer scoped and it needs to be replaced, I don't kill the deal. I get a quote, ask for the credit and move forward. A sewer line is a known repair with a price tag.
So for me, the inspection is more about confirming what I expected, catching what I couldn't see and putting a number on it. If the seller won't work with me on a legitimate issue like that, that's when I'd consider walking.
Mine is not a single defect, it is a layout I cannot fix. Most of my Memphis BRRRR deals only work because the house finishes as a 3BR or better — Section 8 pays $1,395 to $1,950 for 3BR+, and my ARV target is $180K to $265K. If the structure or the lot blocks the conversion — no legal way to add the bedroom, no room to turn a carport or garage into a master — I walk on the spot. A bad roof has a price. A house that can never become a 3BR has no price that fixes my rent. Everything else is just a number in the rehab budget.
Mine is anything I can't get a firm, written number on. Most findings are just math — a roof, a furnace, even a sewer line with a camera report and a real quote can be priced into the deal. What walks me away is active structural movement where nobody will commit to a scope: a foundation that's been patched and re-cracked, or water coming in from a source nobody can identify. If three contractors give me three different fixes and three different prices, that's not a repair, that's an open-ended liability, and no seller credit covers it.
The practical test I use on walkthroughs: can this be scoped, bid in writing, and verified when it's done? If yes, negotiate. If the honest answer is 'we'll know once we open it up,' the price would have to assume the worst case — and at the worst-case number, the seller almost never still wants to sell. That's when eating the option fee is the cheap option.