One of the biggest challenges in a fix-and-flip project is managing expenses once the renovation actually begins.
The original estimate might look solid, but unexpected repairs, material price changes, contractor delays, and additional labor can quickly affect the numbers.
For experienced flippers, how do you build flexibility into your renovation budget?
Do you maintain a fixed contingency percentage, get multiple contractor estimates, or use another approach?
What budgeting lesson has saved you the most money on a renovation project?
Great question, Linda. The two things that have saved the most in the estimate reviews I do are a written scope that every bidder prices the same way, so the totals are actually comparable, and writing down what each bid leaves out, because the exclusions are usually where two totals stop matching. On contingency, a fixed percentage held separately and only released against a named surprise helps, plus a written lead time schedule from the supplier so a draw delay does not force a rushed order. Compare bids line by line on the same scope before you compare the bottom line price.
Linda, I carry 15 to 20 percent contingency on anything older than 1980 and 10 percent on newer stuff, and I never spend it on upgrades. The biggest saver for me has been a walkthrough with the contractor where every line gets a number before demo starts, because vague lines like 'misc repairs' are where budgets blow up. I also open walls and check plumbing and electrical first so the big surprises show up in week one instead of week five. Pay on completed milestones only so you aren't funding a job that's behind.