Say you’re halfway through a flip.The supplier has the cabinets you need, and your contractor can install themnext week. Your next rehab draw is still two weeks out. If you wait, your contractor might already be on another job.
Would you use cash reserves,buy the cabinets with a 0% intro APR business card, or wait for the draw?If you’ve been in that spot, what did you do? Did it keep the job on schedule?
Good day @Nicholas Floyd. The cabinets usually come back with the draw that follows the install, after the inspector signs it off, so the real float is longer than the date on the calendar.
That is why any of these routes works, if the order day records which draw repays it. A 0% card then becomes a bridge with an end date, not an open balance.
When your clients put materials on 0% credit, do they tie the payoff to a specific draw, or does it run until the intro period ends?
Good question, Nicholas. I have seen this timing gap come up a lot on flips. The part I would lock down first is the written order: the cabinet order, the install date, and what happens if the draw date moves. If the contractor can hold the install week in writing and the supplier can hold the cabinets, the decision gets a lot simpler. A second check is the allowance and lead time in the original scope, so the cabinet cost is not a surprise on top of the draw timing. What I would not do is rush the order just to keep the schedule, without that written confirmation from both sides. Curious what others here have done when the draw and the install week did not line up.
Ioannis, I like your point about getting the install week in writing. I’d also ask the supplier if a deposit would hold the cabinets and when the balance is due. That tells you how much cash you actually need to cover until the draw comes through. Have you had suppliers hold an order that way?
Usually yes, if you have the cash and the cabinets are already on the approved budget. Most draws reimburse completed work, so the real risk isn't buying early, it's the cabinets sitting in a garage where the inspector can't count them. Some lenders will fund materials that are delivered and stored on site and some won't until they're installed, so I'd ask yours before you order. Losing your contractor for 3 or 4 weeks usually costs more than floating cabinets for two.
Good day @Nicholas Floyd. The cabinets usually come back with the draw that follows the install, after the inspector signs it off, so the real float is longer than the date on the calendar.
That is why any of these routes works, if the order day records which draw repays it. A 0% card then becomes a bridge with an end date, not an open balance.
When your clients put materials on 0% credit, do they tie the payoff to a specific draw, or does it run until the intro period ends?
Good point, Vladimirs. I’d tie the payoff to a specific draw. With cabinets, I’d confirm which draw covers them before placing the order, then pay the card off when that draw hits. That leaves some room in the 0% period if the inspection gets pushed back. How much time do you usually budget between sign-off and the funds hitting your account?
The client pays at least 40% up front, and then the work goes in small steps. The prep alone is 20 or more: plastic on the floors, tiles off, old adhesive off, walls leveled, chases cut for the new wiring. Each step gets a before and after photo, so the sign-off runs along with the work, not at the end.
When a lender is in the middle it is slower. Do your clients usually line up working capital for that gap, or do they wait it out?
Card, as long as the draw is sized to cover the cabinets and you'd still have reserves left if it slips. Asking this before you're stuck is the right instinct. The detail that tips it is that a lot of draw lenders only reimburse cabinets once they're installed, not while they're boxed in the garage, so getting them in next week is what lets the draw pay for them. Waiting costs you the contractor and pushes that reimbursement back too. The 0% card beats cash because it leaves your reserves for whatever actually goes wrong mid-flip, and an intro period usually runs months, which easily outlasts a draw that comes in a couple weeks late. Short-term money is fine when you can name the check that pays it off.
Thanks, Nicholas. That written tie is what keeps the bridge from turning into a surprise balance later. Let me know how the timing lands once it is in the scope.
Nicholas, if the cabinets are already in the approved budget and the contractor is ready next week, I'd just buy them with cash. A lost install slot usually costs you more than two weeks of float. Get a deposit receipt and a firm delivery date so you aren't paying for cabinets that sit in a garage. I'd skip the 0% card unless you know for sure the draw lands before the promo window ends.
Nicholas, the cash side is well covered here, so one thing on the paperwork side: whatever you pay with, make sure the cabinets get funded on the first draw they show up on, not the one after.
When you pay the supplier, get two things that same day: an invoice that matches the cabinet line on your draw schedule (same scope, same amount), and a lien waiver from the supplier. A lot of people collect waivers from their GC and forget the suppliers. Then take photos right after install: a wide shot of the kitchen plus close-ups.
If any of those is missing, the line usually gets held to the next draw, and your two-week float quietly becomes four or more. That's the scenario where the card or the reserves actually start to hurt.
A lot of rehab lenders will reimburse materials that are paid for and stored on site, or fund a deposit on long-lead items like cabinets and windows, if you ask and show the paid invoice. It just has to be in the draw schedule or approved before you buy.
If your lender won't do that, using reserves could be a way. The money comes back in the next draw anyway, and keeping the contractor on schedule is worth more than two weeks of float especially in this labor market (or how I am experiencing it in Central FL.)
For the next deal, put the long-lead items on their own line in the budget and ask for a materials draw at the start.