Rehab contingency on a 1-4 rental: size it by what you can't see yet
A flat 10% contingency line is common on rental rehab budgets, and it is usually wrong in one direction or the other. On a cosmetic turn in a newer house it can be more cushion than you need. On an older double with original plumbing and wiring behind plaster, it can be gone before demo is finished.
How I'd size it instead:
Split the scope into seen and unseen. Paint, flooring, fixtures and cabinets are seen: the bid is the bid. Anything behind walls, under floors or underground is unseen.
Put the contingency against the unseen items, not the total budget. A big cosmetic budget doesn't need a big cushion. A small budget on a house with a sewer line of unknown age does.
Buy information before closing. A sewer scope, an electrician's look at an older panel and wiring, and a check of the roof decking often cost less than the surprise they rule out.
Decide ahead of time what happens when contingency gets used. Change orders get priced in writing before the work starts, and if the cushion is spent, something from the nice-to-have list comes out.
Underwrite with the contingency fully spent. If the deal only works when nothing goes wrong, it doesn't work.
How do you set contingency on older 1-4 units: a flat percentage, by system, or something else?