Rehab contingency on a 1-4 rental: size it by what you can't see yet

Rehab contingency on a 1-4 rental: size it by what you can't see yet

Realtor · Columbus, Franklin County · Member since 2026 · 226 posts · 80 votes

A flat 10% contingency line is common on rental rehab budgets, and it is usually wrong in one direction or the other. On a cosmetic turn in a newer house it can be more cushion than you need. On an older double with original plumbing and wiring behind plaster, it can be gone before demo is finished.

How I'd size it instead:

  1. Split the scope into seen and unseen. Paint, flooring, fixtures and cabinets are seen: the bid is the bid. Anything behind walls, under floors or underground is unseen.

  2. Put the contingency against the unseen items, not the total budget. A big cosmetic budget doesn't need a big cushion. A small budget on a house with a sewer line of unknown age does.

  3. Buy information before closing. A sewer scope, an electrician's look at an older panel and wiring, and a check of the roof decking often cost less than the surprise they rule out.

  4. Decide ahead of time what happens when contingency gets used. Change orders get priced in writing before the work starts, and if the cushion is spent, something from the nice-to-have list comes out.

  5. Underwrite with the contingency fully spent. If the deal only works when nothing goes wrong, it doesn't work.

How do you set contingency on older 1-4 units: a flat percentage, by system, or something else?

0Reply
64 views

2 Replies

Jump to latestLatest
  • Flipper/Rehabber · Tacoma, WA · Member since 2026 · 57 posts · 9 votes
    5h

    There's a third bucket between seen and unseen: work you can see, but whose method is set by the year the house was built. On an older Columbus double that usually means lead paint.

    For housing built before 1978, EPA's Renovation, Repair and Painting rule requires a certified firm and lead-safe work practices once a job disturbs more than 6 sq ft of painted surface per room inside or 20 sq ft outside (40 CFR 745.83), and window replacement counts as a renovation at any size. So scraping and repainting original trim, swapping out old windows, or opening plaster for that rewire stops being a commodity bid. Containment, specialized cleaning and cleaning verification get added, and the pool of contractors who can legally do the work gets smaller. In a tenant-occupied unit the firm also has to hand the occupants EPA's Renovate Right pamphlet before work starts.

    Because that line is predictable from the build year, I'd price it in the base scope rather than the contingency. If the contingency is quietly carrying lead-safe practices, it's already half spent before anything behind the walls shows up.

    In practice: ask every bidder for their RRP firm certification and a separate line for containment and cleanup. If a bid on a 1920s double doesn't mention it, treat that as a scope gap, not a cheaper bid.

    On the older doubles you see around Columbus, are bids coming back with RRP line items, or does it mostly get left out on smaller jobs?

  • Real Estate Consultant · Massapequa Park, NY · Member since 2026 · 29 posts · 7 votes
    5h

    Good framework, BJ. I would size it by system, not by a flat percentage, for the same reason you laid out. A flat number hides where the risk actually sits.

    In the Estimate Review work we do, the step that catches the most trouble is comparing the bids line by line against one written scope before any money moves. On an older 1-4, that is where the gaps usually show up: a sewer line that was never scoped, a panel that needs work, or lead-safe work that one bidder priced and another left out. Yi makes a good point on that last one. If it is predictable from the build year, it belongs in the base scope, not in contingency.

    I would also hold the contingency separate from the base budget and treat it as spent when you underwrite, the way you said. And tie each draw to work that is finished and checked, not to a date on the calendar. That way the contingency stays available for what you genuinely could not see, instead of getting used up on scope that was never written down in the first place.

    How are the Columbus bids you see handling the sewer scope and the panel, as separate lines or folded into a lump sum?