Industrial/Flex Property- Day in the Life, Building a Flex Prop

Industrial/Flex Property- Day in the Life, Building a Flex Prop

Henry ClarkPro Member
Developer · Member since 2020 · 4k+ posts · 4k+ votes

Primarily do Self Storage.  As I have looked around several cities, I have come across Industrial Flex, Contractor Garages and Contractor Incubator buildings.

We have 4 acres set aside on a 4 lane road with 15,000 Vehicle Traffic Count per day. This is an 8 acre site.  We built Phase 1 as self storage 230 units on the back side.  Phase 2 will be 200 self storage units.  However a mix will be 12 x 40 with electricity to support our Contractor Incubator buildings.  Phase 3 which is along the road will be what I call Contractor Incubator buildings.

Site selection:

Normally you would select a site for a particular investment.  In this case we could do 630 Storage units in this location, but we do not feel the market will support that.  Thus we saved the road frontage and a separate access for this endeavor.  We are lucky, this is a perfect site.  4810 South 35th street, Council Bluffs, IA if you want to Google.  Veterans highway which is the 4 lane in front of us goes East (Council Bluffs) and West (South Omaha and Downtown Omaha).  Interstate 80 and Highway 75 which are tied to Veterans run North and South.  The actual location does not have a street light, but has two turn in/out lanes both to cross the street and to get off the street.  The entrance to the location is on a slow dead end street, giving you a chance to approach the highway.  With the internet, Contractors (electricians, plumbers, hvac, landscapers, etc don't need a location on the main drag anymore.  Plus they don't bring their customers to their shops.  Another big plus for this location, is the major Electrical Supply house and Welding Supply house are on our highway nearby, thus we get a lot of contractor traffic.  Just need to clean some brush and move the Orange Storage container we are using during construction.  Otherwise we have access, zoning, water, sewer, electrical and Ground project ready.

Market:

I will document the market next time.  This will be harder, since I have a "proven" method for Self Storage. I need to come up with one for Contractor buildings.

Product (building/services):

Competition:

Facility Costs:

Revenue Stream:

Financing:

Marketing:

Insurance:

Pros/Cons:

If I'm missing a topic, just let me know to add.

8Reply
410 views

Most Popular Reply

Developer · Tuscumbia, AL · Member since 2019 · 111 posts · 99 votes
5y

@Henry Clark

I'd stay away from the common bathroom. Stick 1 in each bay or for the time being, you can just rough-in the plumbing until you get a tenant. In the whole scheme of this project, the restroom will be least of the costs.

CB

See this reply in the discussion

47 Replies

Jump to latestLatest
  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    5y

    Stuck in bureaucracy. 

    Still waiting for the SBA to release the front 4 acres for the contractor development.  Its part of the collateralization for the Storage buildings.  With Covid, most of their people have been pulled off "business" loans and moved over to process PPP payments.  Also they are not used to releasing collateral, normally there is not enough.

    Option is to wait until they get to it and assume they will release.  Due to the appraisal they have far more collateral than they need.  Current interest rate is 2.66%, with 20 year fixed/amort with them.

    Or my local bank who is processing this SBA loan has a new program of 5/10/15/20 year fixed rates.  Normally they only do 5 year terms, with different amort periods.  15- 4.00%; 20- 4.22%.

    Hate to give up 2.66% and take on 4.22%.  Would be about $200,000 over the loan life.  But I could start my project sooner.

    I'm probably going to wait on the SBA loan.  Juggling two Self Storage projects that are in the Build or Rent up phase (exposed).  So I might hold off pulling the trigger on this Contractor bay project.

    If I don't make the building order by about March and lock in a contractor, won't be able to do this year.  All of the contractors are already booked through June, and metal looks like it will come under shortage from China suppliers due to Covid reduced shipments.  Once the economy opens up, there will probably be a log jam at the west coast ports trying to unload.  So tight supplies of rubber duckies or Steel will be prolonged into 2022.  If someone knows someone at the government have them prioritize what comes into the country to help the economy.

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    5y

    SBA released the front 4 acres.  Won't get any building done this year, but starting to do planning.  Below is an engineering plat of the buildings we plan to do. 

    The two long left to right building foot prints at the top are our 2nd phase of our self storage buildings.  Have decided to make the bottom one into Flex buildings.  45 deep x 25 wide.  12 x 14 tall doors.  Metal walk through door with window above.  Will have some electricity and individually metered.  No set parking out front.

    The six square/rectangle buildings at the bottom will be the larger Flex buildings.  70x70 or 70x100.  Will divide.  At this time plan to use a building from Sukup.  My Electrician is also a rep for them.  Did some early quotes on different sizes and he was far less expensive than another company.  Buildings are comparable quality and this contractor has done significant work for me.  Will have water, sewer, electric. Stub out commode, bathroom sink, shop sink, coffee area sink and water.

    Subject to cost estimates will probably build the long building above.  Then the first three buildings below, since this is a new market and product for me.  This will reduce the risk and anxiety as we rent up.

    Have erected building quote, door quote ($10k per door, chain, insulated, installed.  Have 48 drive thru doors.  wow).  Getting concrete pad and roads, electrical, sewer, water.  The plan above has a lot of concrete driveway and parking.  Have to see if the numbers will allow.  Plan to give so many parking spots to the units, and then the rest have to be rented.  We have Location/Location.  The extra concrete driveways and parking should help set us apart.

    As noted above, this 4 acres was appraised at $580,000.  Banker says this collateral is good for project up to $2mm.  So won't need to put any cash down.

    Plan to go for a $1 per sqft/month.  They pay insurance (us additional insured), water, electric, maintenance.  Have to figure out if/what we do for deposit or early out charge.  3 to 5 year leases.  We will cover Property taxes, sewer, grounds keeping (very little other than snow removal).  Will split improvement costs with them (hvac, bathroom, offices, etc).  They must leave in place.

    Have to get actual building prints to submit, along with engineering for Electric, water, sewer.  Want to get a Fire Marshall determination if Sprinklers are needed. 

    We added more buildings from original layout.  Engineer said I need to dig out Storm pond 2 more feet.  Will do that in October.  Use for fill.

    Google is building a really large distribution center 1 mile down the road.  See if that has any impact.

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    4y

    Talked with Fire Marshall.  Need to build at 5,000 square foot or below, or need to install fire sprinklers or 3 hour fire wall.  Decided to make all of the buildings 50 x 100.

    Just met with Engineer on redesign building layouts.  Now that we have the final footprints, he will move forward drafting water, sewer, electrical, external sidewalk and road layouts.

    Have excavation contractors digging 2 feet out of Storm pond to meet new building and parking sizes.  Using this dirt on site to raise building sites 1 foot.  This will help with drainage since this area of our complex allows surface run off versus storm sewer to the Storm pond.  Not ready to build, but want this dirt work done while its dry in the fall, and will let the ground settle over winter with a freeze/thaw cycle.

    My metal building contractor called and said the manufacturer is no longer going to do Metal buildings, they are going to concentrate on their grain handling side of the business.  Need to find another building manufacturer.  Right now, metal building prices are about 40% higher than a year ago.

    This project will be built in 3 phases over a period of 3 to 5 years.  This is to test this Flex building market out.  Also to make sure we don't overextend financially, especially during this economic period.  All of our Storage locations are in the positive cash flow stage, with our last location in the Rent up phase.  We have also paid down a lot of debt this last year, through our Subdivision sales.  So we can take on a little more risk.  Have been asking all of my realtors, contractors, Steel contacts and bankers what their crystal ball looks like.  Most are pulling back buying new equipment, starting new developments, or contracting further out.  They plan to see what happens next year.  We plan to build 2 of the 6 buildings next year.  Each building will be potentially divided for 2 to 4 tenants.  Have 4 different types of businesses/tenants I want to focus on, to start with.  Also at three of our Storage locations demand is high and we are 100% rented.  We have or will buy extra ground, thus will add storage at two of these sites next year.  Will raise rental rates to compensate for higher building costs.  Can do this since all competition is at 100% occupancy.  Customers would have to drive 20 to 40 miles away for less expensive rents.

    Short-term 1 to 3 years thought process.  Let's say interest rates are around 4%.  I'm okay investing up to 7% with a sharp pencil.  Stop investing at 9%.  Right now Inflation is more of an issue than interest rates.  Inflation being around 40% on my materials, plus long lead times.  All of my contractors are short staffed right now and having to pay more.  They are busy into the foreseeable future.  When supply chain straightens out, investors stop backing off investing, interest rates stay moderate; my next concern will be finding contractors once the economy comes back with pent up demand.  My decisions are based more on our personal Risk management, with the overall economy as a backdrop.

    Longterm thought process.  The US is a financial powerhouse because of the following simple items:  a.  Rule of Law, versus Rule of Man; b.  Property rights; c.  Patent/Copy rights protection; d.  Natural resources.; e.  Stable Government comparatively.  These items might sound simple, but most countries don't have these.  Don't see any of these changing.  The only one I see being significantly threatened is the Patent/Copy right protection overseas.  So definitely keep investing.  Plus with our Storage business we have about a 3 year timeline where we will have more than enough equity to take any Financial Collateral issues should the economy go down (40% recession).

    Usually I say:

    Start small and Make Your Big Mistakes Early.

    Now, make sure you are doing a Risk Assessment both on the investment you're looking at, and also your overall Financial position.

  • Investor · Bellevue, WA · Member since 2017 · 2 posts · 1 vote
    4y

    Amazing. Thanks for the details.

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    4y

    Got quotes in on Buildings, Sewer, water, roads, electric, everything else.  We were going to do just the first two buildings out of the six.  Although the project comes in profitable, not enough for us.  Have other projects that have a greater return and lower risk factor.  Long road to get to this stage. Thus, we are not going to do this project or this type of investment for now.  Will look at another alternative.

    We got two quotes for the metal buildings.  Ranged from $530,000 to $630,000 for the two buildings "total" of 10,000 square feet.  This only included the buildings erected, pads and doors.  16 foot ceiling, 50 x 100, 25 foot divider walls, Commercial steel ADA walk through doors, 5 inch concrete floor no rebar, Garage doors 14 tall clear height x 12 wide and Insulated roof and sidewalls.  Both builders would be clearspan steel, national mfgs.

    The Electric ($139k) and Sewer ($107k)  ran $245,000 which really blew up the project.  Sewer was a little higher since we were going to have to put a "Grinder" lift station in, since the sewer line was elevated to high coming into our property.

    You see the drawing above.  We are going to do the long white tube above. This is in three sections and will use a traditional Storage building scheme.  Without Water or sewer.  Electric plugins will be on the outside.  We won't meter.  Thus I want control outside how much electric and lights get used.  These will have 14 foot clearance at the doors. Insulated panel doors 14 tall by 12 wide, not the roll up storage doors.  Steel ADA walk through doors, with window above.  This achieved twice 19,000 square feet and about twice the revenue as the Traditional Contractor buildings above, thus they came in very profitable, since the buildings were less expensive and not the added Water/Sewer costs and less Electricity and metering.  These won't meet certain types of flex building contractors, but we have less risk and a higher potential profit window.

  • Harvey LevinPro Member
    Property Manager · Indianapolis, IN · Member since 2012 · 209 posts · 162 votes
    4y
    Quote from @Henry Clark: thank you for all the details. I have meeting for week after next to start looking for either a site or existing building to repurpose for a similar concept. 
     

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    4y

    @Harvey Levin

    Love the hunt and the underwriting part of the deal.  Did a quick look in your area and you have a lot of potential sites.  You're in a target rich environment.  I love having more than one property to make offers to.   Give them a three day offer and move on.  Pick the oldest/hungriest listing first.

    3000 N. German Church Rd- Roads on two sides.

    3701 N. German Church Rd- favorite, rectangle with long side facing the road, and two way turn into property

    12233 Pendleton Pike

    5251 W56th street

    8500 W 10th St- Favorite, I love dirty.  Low priced, good location.  Some bulldozer and dirt work and the land value increases by a multiple of 4; once you put a building on it.  The increase appraised value, gives you the collateral for your next deal with that bank, no cash down.  Check on low ground though.  Use the dirt on site to raise, plus you get a pond.  Two way turn in access.

    These will all go good for contractor locations or family oriented martial arts, dance, day care, etc.

  • Harvey LevinPro Member
    Property Manager · Indianapolis, IN · Member since 2012 · 209 posts · 162 votes
    4y

    Thank you for looking at this!!!  

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    4y

    Update.  Had final building designs, quotes, and financing ready to go.  No down payment needed due to appraised equity in existing land.  Decided to pull the plug on this project.  Would be a year before we locked in final financing and not comfortable being at 7% up to 9%.  

    Also did an overall financial review of all of our assets, stocks/bonds, farm ground etc.  Decided to start to reduce debt going into the next 2 years.  Might miss out on 2 years of rent, but will not have added debt, and will be financially unconcerned for the next two years.

  • Member since 2020 · 14 posts · 2 votes
    3y

    @Henry Clark Wow, just read this whole thread now. Very interesting from the start. Do you have another update or I assume you are still on hold with this project with current rates and material costs?

    Also, care to take a look at my Rochester and Syracuse, NY area to see what you think for the contractor garage concept I am interested in?


    Thanks

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    Getting building plans update for permitting. The one issue that might pop up is Fire suppression systems.  We did not include.  Would be about $70,000 more for a Dry system.  

    Plans should be ready when we get back.
     Enjoying ourselves at Lobster Fest in Placencia. 

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    That was lunch.  Bush chicken tonight?

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    @John B..  Look on loopnet in the areas you’re interested.  Look for the oldest listings and the nastiest properties.  Don’t worry about price.   Check zoning to fit your needs.  Make lowball offers with 2 day windows.   Subject to 90 day inspection and 45 day close.  Secure with $10,000 deposit.    Make a post or pm me.  

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    We have been looking at two options.  Several independent buildings on one side of the property or Storage type buildings on the storage side of the property.  Got engineering drawings for buildings and land layout back.  Made first pass through on Deal analysis.  Decided to go with the Storage type buildings.  The cost for the Contractor buildings with water/sewer and bigger framed buildings was going to be too much and also with less revenue than the storage type buildings.  

    Made a first pass through doing Deal analysis.  Occupancy 85%; $1/sqft rental; Occupancy 85%; $.75/sqft rental; Occupancy 50%; $1/sqft rental.  I like to stress test an investment, for us and when talking with the Bank.

    Banker and I will go over next week.

    Submitted the plans for building permit.

    Will do three different posts showing the different stress analysis.

    We have a few of the items still out for quote, thus our figures could move some.  Sprayfoaming; concrete.  Will summarize at the end.

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    Deal Analysis 1:

    Occupancy 85%; $1/sqft rental.

    Contractor 3 bldgs Status:
    Buildings Pitzer           714,136 quote
    Doors Pitzer                130,842 included
    Electrical Kreifels          29,927 Quote
    Plumbing Kreifels           15,000 Outside water hydrant
    Spray foam Heartland  150,000 Waiting on estimate
    Rds/park/sidewalk Trent 180,000 estimate
    Gate Amer Fence               25,000 Quote
    Security MHS                     15,000 rough
    Land grading ????               10,000 minimal
    permits City                      10,000 rough
    Signs Jo Designer                 1,000 rough
    Engineering HGM               10,000 plug
    Land own already                      0 already own
    Constr/Rent up Interest   91,000 $1.3mm at 7%
    Estimate:                       1,381,905
    No downpayment 0 Storage Appraisal ??????
    Financed Balance           1,381,905

    Revenue:
    Units 18
    SQ ft 1080
    Rate per SQFT 1
    months 12
    occupancy 0.85
    Annual Revenue: 198,288
    Insurance               3,000 rough
    Property Tax          21,143 1.053%
    Maintenance                 0
    Electrical                1,800
    Interest 0.07         96,733


    Depreciation 20 years 69,095

                                6,516
    Income Tax:         1,629 25.00%

    Net Income          4,887


    Cash flow:           73,982





    Cashflow above: 170,716 B4 P/I



    P/I payment
    7%/20 years $1,380,000 10,699 per month
    12
    128,388 P/I annual

    170,716 Annual cash flow before P/I

    42,328 Excess cash flow above P/I

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    Deal Analysis 2:

    Occupancy 85%; $.75/sqft rental

    Buildings Pitzer            714,136 quote
    Doors Pitzer                  130,842 included
    Electrical Kreifels            29,927 Quote
    Plumbing Kreifels             15,000 Outside water hydrant
    Spray foam Heartland     150,000 Waiting on estimate
    Rds/park/sidewalk Trent 180,000 estimate
    Gate Amer Fence              25,000 Quote
    Security MHS                    15,000 rough
    Land grading ????              10,000 minimal
    permits City                     10,000 rough
    Signs Jo Designer                1,000 rough
    Engineering HGM              10,000 plug
    Land own already                     0 already own
    Construction/Rent up Interest 91,000 $1.3mm at 7%
    Estimate:                   1,381,905
    No downpayment                     0 Storage Appraisal ??????
    Financed Balance         1,381,905

    Revenue:
    Units 18
    SQ ft 1080
    Rate per SQFT 0.75
    months 12
    occupancy 0.85
    Annual Revenue: 148,716
    Insurance               3,000 rough
    Property Tax         21,143 1.053%
    Maintenance                 0
    Electrical               1,800

    Interest 0.07        96,733


    Depreciation 20 years 69,095

                       -43,056
    Income Tax: -10,764 25.00%

    Net Income -32,292


    Cash flow: 36,803





    Cashflow above: 133,537 B4 P/I



    P/I payment
    7%/20 years $1,380,000 10,699 per month
    12
    128,388 P/I annual

    133,537 Annual cash flow before P/I

    5,149 Excess cash flow above P/I

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    Deal Analysis 3:

    Cost is the same as in Analysis 1 and 2:

    Revenue:
    Units 18
    SQ ft 1080
    Rate per SQFT 1
    months 12
    occupancy 0.5
    Annual Revenue:    116,640
    Insurance                  3,000 rough
    Property Tax             21,143 1.053%
    Maintenance                     0
    Electrical                   1,800
    Interest 0.07            96,733


    Depreciation 20 years 69,095

                       -75,132
    Income Tax: -18,783 25.00%

    Net Income -56,349


    Cash flow: 12,746





    Cashflow above: 109,480 B4 P/I



    P/I payment
    7%/20 years $1,380,000 10,699 per month
    12
    128,388 P/I annual

    109,480 Annual cash flow before P/I

    -18,908 Excess cash flow above P/I

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    Summary of our stress test:

    Analysis 1:  on an investment of $1,381,000 not including land.  Land is around $250,000; which we already own.  We will have a cash flow of $42,000 after P/I and all costs and income taxes.  At 85% occupancy; $1/sqft rental per month.

    Analysis 2:  Cash flow of $5,000 after P/I and all costs and income taxes.  At 85% occupancy; $.75/sqft rental per month.

    Analysis 3:  Cash flow of negative ($19,000) after P/I and all costs and income taxes.  At 50% occupancy; $1/sqft rental per month.

    What is the return?  Using analysis 1 total cost with land is $1.63mm with a cash return of $42,000= 2.5% return.  These are metal buildings and will maintain their value with low maintenance.  So, as we are paying down principal, we are also building equity.  Principal paydown will average $69,000 per year.  Thus, our adjusted return is $42,000 plus $69,000= $111,000 per year.  $111,000/$1.63mm= 6.8% return after all costs and income taxes.

    2.5% or 6.8% is not a very good return based on the investment strategies we use.  

    The land is already being paid for as part of our Phase 1 self-storage, so we will take that out of the equation, the $250,000.  $1.63mm becomes $1,381,000 total costs.  $42,000/$1,381,000= 3.0%; $111,000/$1,381,000= 8.0%.  Returns are better, but still not great.

    Potential income/cashflow swings:

    A.  If we hit 100% occupancy that will add gross $35,000 to revenue and about $26,000 cash flow and after-tax profit.  All surrounding rentals of this type in our area are fully rented.  Ours will be better due to its location/access/wider parking and internal road widths.  Adds 1.9% to returns.

    B.  Used Interest 7%.  If it swings to 5% that would be $26,000 more income and cash flow per year.  Adds 1.9% to returns.

    C. NNN- we do not plan to seek NNN leases. The $1 per sqft is near the top of the market. Plus, there will be no water/sewer/minimal electric in the units. They will be required to carry full insurance coverage and name us as "Additional Insured".

    D.  We could or might be required pay down on the $1,381,000 loan balance.  Say 10% for this SBA loan or $138,000.  On top of our contributions of the land $250,000.

    E. Cash on Cash return of say the land of $250,000. $42,000/$250,000= 16.8%; or $111,000/$250,000= 44.4% COC.

    Risk analysis:

    1.  We did the three-deal analysis.  Downside risk is minimal.

    2.  This investment must stand on its own, but we have our other investments to offset any mishaps.

    3.  This deal is not a home run for the types of deals we have been doing.  But our risk is sitting out and having Building costs go up; or financing (7%) costs go up. My crystal ball says we have a recession, thus Building costs will come down, but I don't want to plan on it.  Financing cost (7%) could go down, which we could refinance.  Or they could go up and we would not do the deal at 9% which is our deal cut off point.

    4.  Although we already own the land free and clear.  We don't need this investment.  We have other investment projects that would have greater returns.

    Will see how the permit process goes and if any new costs pop up.  Also waiting on some firm quotes.  Discuss things with our banker. Key is to firm up the larger numbers.  The permit process will help identify any missing cost items.

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    3y

    Moved some dirt in this week to fill a low spot.  While the weather is good and dirt is dry.  Will rent a skidsteer later and spread out.

  • Attorney · Long Island, NY · Member since 2023 · 5 posts · 6 votes
    2y

    Hey Henry,

    Anything new with this project? Still holding off on the flex space build?

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    2y

    Steadily progressing.  Have permit approved.  Getting updated quotes for building, road, electric.   Winter is here so won’t do anything this winter. Too cold to pour concrete.  

    Bank is checking on numbers.  Although this will be a construction interest only. Then convert to a fixed, so don’t know final terms.  This is our main bank so financing is assured, just terms.  Hoping not to put anything down.   Have equity built up already in existing property.

    We always do a cost of failure.  Example:  rent $1/sf planned but what if $.80?  Planned 90% occupancy but what if 70%?  Still cashflow positive at the failure levels.  

    We have several projects and potential projects always going.  This project has taken the back seat, not because it’s bad, but the other projects were better and the customer base is more familiar than flex customers.  

    My only hesitancy is financial.  The interest rate say 8% I can deal with.  The cost is a one time deal.  Could wait to see if it goes down, but I think it will only go higher, even in a recession for this project.  Concrete for example. We have some massive projects in the area.  They dictate concrete availability and pricing.  One project we ordered 12 truckloads for the day but they only gave us three and that was at 4pm on a hot day.  But that’s part of developing.  Some people develop and others are investors.

    What’s it look like in your area?  What kind of projects?

    We will actually do two different types of builds here.  Starting with the low risk low cost option.   The other phase will be a higher priced build.  

  • Henry ClarkPro Member
    OP
    Developer · Member since 2020 · 4k+ posts · 4k+ votes
    2y

    @Michelle Murtha   If your interested in development.  Make a post in the Commercial section.  Title it Deal 1.

    Leave it blank.  Put @my name.  

    I’ll take you thru 5 deal analysis.  The first one will take two weeks.  Then 1 week each.


    After that start reading books, watching podcasts, joining groups, looking for a mentorship program.  