Own 4 paid-off lots in Upstate SC: best way to finance spec builds and scale
Hey Guys,
I'm a real estate investor in South Carolina. I own 4 paid-off lots in Upstate SC and plan to build 1,300–1,600 sq ft spec homes on them to sell. Then I want to roll the profits into a larger project in a different area, possibly the Myrtle Beach/Conway side of Horry County. I'm putting my financing together and would love leads and lessons from people who have done this.
What I've looked at so far:
National private lenders (Lima One, Kiavi, Easy Street, etc.): up to 90% of cost, but around 9–10% plus 1–2 points for newer builders
Local banks and credit unions: closer to prime + 1 with about 1 point, but with about 20% down and more paperwork
Using the lots I already own
The lots are free and clear. Which lenders count that land as my down payment, so I bring little or no cash to closing?
Should I put all 4 lots on one loan or builder line, or finance one build at a time?
Build 1–2 first to prove the numbers, or start all 4 together?
For homes this size in Upstate SC, what are you seeing for build cost per sq ft and sale prices?
Traditional leads
Upstate SC community banks or credit unions that like spec construction and offer a builder line of credit
Loan officers who are good on draws and turnaround times
Banks in Horry County that will work with me once I have completed builds to show
Creative leads
Private money lenders active in SC, and what terms you've seen
JV or equity partner setups for the bigger project: money partner plus builder splits, preferred returns
Lot seller financing or subordination for the next project's land
HELOC, a portfolio line or an SDIRA/Solo 401k for down payment or gap funding
Gap or mezzanine funding on top of a first-position construction loan
Spec-specific questions
How did you get past the "no track record" problem on your first builds?
Starter-size homes in the Upstate sell for less, and lenders cap the loan at 70–75% of finished value. How do you keep enough money in the loan?
What do you budget for interest reserves, contingency and carrying costs if the home takes longer to sell?
Any lessons on draw schedules, inspection fees or prepayment/minimum-interest traps to avoid?
Have you pre-sold or used builder-to-buyer contracts to get better bank terms?
One LLC per project or one builder entity, and how does that affect lending as you scale?
For those who moved from a few specs to a bigger project, what did your financing look like at that step, and what do you wish you'd known?
I'd also welcome GC, surveyor or closing attorney recommendations in Upstate SC or Horry County.
Thanks in advance. I'm happy to share what I learn back on this thread.
— Rudy