building 2 fourplex's, i could use some advice.

building 2 fourplex's, i could use some advice.

Contractor · victoria, bc · Member since 2014 · 79 posts · 22 votes

hello.

I have another thread that recaps my story. I'm building two fourplexes on a property I own in Nanaimo, BC, Canada. i attached a drop box link to the design.

I owe 204k on the property, and is worth approx. 550k. The value should go up when the property is rezoned and I have the development permit. Both should be achieved mid December. My broker figures the property will be worth 700-850k. Ill get a proper appraisal once the development permit comes through.

The estimated build cost is 2.1- 2.5 million and the estimated value after construction is approx. 3.3 to 3.5 million.

all the engineers and consultants costs will total a little under 380k. to date I've paid 150k and have 1000oz of silver to cover larger invoices and I pay the smaller ones out of my wages.

The city of Nanaimo will charge me a little under 200k to get the building permit.

My broker figures that I can pull enough money out of the property after the rezoning to cover whatever I need to get to the construction loan. I don't know if taking out more debt is the right road to go down. I'm told construction loans are hard to come by now adays, and I don't want to put my property in danger by taking debt i cant cover if a construction loan doesn't come through.

I don't know whether I should pause the project, plow through and build the parachute as I fall, or get a partner. I've been told that is at least one person who has had my project put in front of them who wanted in.

has anyone been in a similar position?

I should have been asking questions about my project years ago. ive made SO many mistakes and I'm not close to done.

thank you for your advice

Joshua

https://www.dropbox.com/scl/fi/z2y2r5u7flf0xwb1wfy38/drawings-Oct-2024.pdf?rlkey=u960kzqkjzxv03vri52hrws7e&st=f9a5ak43&dl=0

1Reply
203 views

Most Popular Reply

Real Estate Broker · Sacramento, CA · Member since 2021 · 644 posts · 467 votes
1d

tough spot, and good on you for asking now instead of after the next invoice. with a 2.1 to 2.5 build and 3.3 to 3.5 on the back end the spread is there, but the risk is all in the gap before the construction loan. i wouldnt pull more debt against the land until that loan is actually committed, and i'd get a second opinion on the takeout before i paid the permit fee. have you had a lennder look at the full pro forma yet, or just the broker so far

See this reply in the discussion

9 Replies

Jump to latestLatest
  • Real Estate Broker · Sacramento, CA · Member since 2021 · 644 posts · 467 votes
    1d

    tough spot, and good on you for asking now instead of after the next invoice. with a 2.1 to 2.5 build and 3.3 to 3.5 on the back end the spread is there, but the risk is all in the gap before the construction loan. i wouldnt pull more debt against the land until that loan is actually committed, and i'd get a second opinion on the takeout before i paid the permit fee. have you had a lennder look at the full pro forma yet, or just the broker so far

    • Contractor · victoria, bc · Member since 2014 · 79 posts · 22 votes
      6h

      Hi Noah, thanks for the reply.

      I agree that taking out more debt without a confirmed construction loan is a mistake. I don't think ill get to the construction loan without another cash infusion. ignoring the City's fees, Ill owe approx. 180k in consultant fees, though I've been told some of those fees may be during construction phase. my silver is worth 50k right now, so I need around 130k.

      either I pause the project or I find a partner, i guess. do you see another solution?

      I haven't had direct contact with a lender, and have only the brokers word and his pro forma.

  • Lender · Philadelphia, PA · Member since 2024 · 102 posts · 22 votes
    1d

    Building two fourplexes while rezoning and the development permit are still landing is a hard sequence to manage, especially with so much already spent on consultants. We help builders work through construction financing through Royal Partners and can talk through how lenders like to see the post rezoning value and permit stage lined up before they commit. DM us if you want to walk through where things stand now and what would need to be ready next.

    • Contractor · victoria, bc · Member since 2014 · 79 posts · 22 votes
      6h

      Hi Marc. Thanks for the reply.

      Do you have services in Canada?

  • Technology · New York, NY · Member since 2026 · 93 posts · 29 votes
    17h

    Joshua, Noah is right. Do not add land debt before a takeout is committed. Your broker's "pull enough out" is not a financing plan; it is a hope that an appraiser and credit committee agree with him. The 700-850k rezoning value is paper until permit and appraisal.

    All-in cost: 550k land basis plus 2.1-2.5M hard plus 380k soft plus 200k permit equals 3.23-3.63M. Against 3.3-3.5M stabilized value, spread is 0 to 270k, negative at the high end. At 700-850k land, cost is 3.38-3.93M. That is a donation. Add 5-10% contingency and S-curve carry. Draws are not linear: 20/50/30 means interest reserve peaks before occupancy. Budget horizontal infrastructure per pad, not per building.

    Debt: 70% LTC on 3.0M is 2.1M; 65% LTARV on 3.4M is 2.21M. Proceeds cap near 2.1-2.2M, leaving an 800k-1.0M equity gap plus carry. At 6.5% and 25-year amortization, debt constant is 8.1%. On 2.2M, annual debt service is 178k. A 1.25 DSCR floor needs 223k NOI. At 35% opex, that is 343k gross rent, or 3,575 per unit monthly across eight units.

    Joshua, what signed rent comps support 3,575 per unit, and what DSCR and LTARV cap has a takeout lender committed in writing?

    • Contractor · victoria, bc · Member since 2014 · 79 posts · 22 votes
      6h

      Hi Max, thanks for the reply

      I was told that the soft cost were included in the construction estimate. Am I wrong? I'll have to ask again,

      I sent the project to a property management company and the comps that came back gave me a gross of 235,200, though rents have gone up in the area since I got that estimate. The numbers you have cited mean the project doesn't pencil?

      I have no committed lender.

      What do you mean by budget horizontal infrastructure per pad?

  • Realtor · Columbus, Franklin County · Member since 2026 · 222 posts · 79 votes
    11h

    @Joshua Berube I'd split this into two questions: does the project pencil, and can you survive the gap until a construction loan actually closes? On the first, $2.1-2.5M against $3.3-3.5M looks like room. But the lender will size the loan off its own appraisal and cost review, and it will usually want a hard-cost contingency and an interest reserve in the budget, so rerun the spread at the high cost, the low value and today's rate. On the second, I wouldn't pull more equity off the land until you have a written construction-loan term sheet. That debt has to be paid whether the project moves or stalls. A partner who covers the equity gap can cost less than a stalled site, as long as the terms are in writing and reviewed by a lawyer. Do you have an actual term sheet from a construction lender yet, or only your broker's estimate of what you could borrow?

  • Contractor · victoria, bc · Member since 2014 · 79 posts · 22 votes
    6h

    Hi BJ, thanks for the reply

    With what i have right now, and my estimated income in the next little while, I doubt I can cover the consultant invoices to get me to the construction loan. I've done pretty good so far, but the money needed between the development permit and the building permit is.. impressive. I've been told that some of those fees will be paid during construction, but I'm not sure how much and am hesitant to put much weight there.

    I figure ill need 180k because of what ive already paid, with my silver, which is valued today at about 50k, ill need 130 before the city fees.

    I really don't want to take more debt out on the property. I don't want to put myself in a position where i could lose it. so, i guess that leaves 2 options? pause the project or find a partner. can you see another avenue?

  • Lender · Tampa, FL · Member since 2018 · 50 posts · 10 votes
    3h

    Your numbers have room in them, which is a good start. A few things from the lending side:

    Most construction lenders size the loan on total cost, land plus build plus soft costs, and want the borrower to have some skin in it. The good news is the equity you have in the land after rezoning usually counts toward that. Get the appraisal after the development permit like you're planning, since that's when the land value jumps.

    Use the high end of the build estimate, $2.5M, plus a 10% contingency when you talk to lenders. Projects that come in short of money mid build are the ones that get in trouble, and it's much easier to get the money up front than halfway through. Also ask your broker whether any CMHC rental construction programs apply, since that can change the terms a lot on rental projects in Canada.