Do you add a 10-15% rehab buffer? We stopped. Tell me why I'm wrong

Do you add a 10-15% rehab buffer? We stopped. Tell me why I'm wrong

Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes

Hi everyone, and happy Tuesday!

Here's a take I'm ready to defend, and happy to be corrected on: we don't add a contingency buffer anymore.

Instead, we price everything down to the last screw. And where we can't be sure what's behind a wall, we split the job into blocks. After each block is opened up, we see the real picture and price the next one, so nobody pays for a guess.

The part I think matters most: opening a wall isn't the job, having a solution ready is. On a hotel we renovated in the Alps, before anything came down we checked whether a new partition could go in, what removing the ceiling and the wood paneling on the walls would mean, and what load each change would put on the structure. Every step was priced before the owner decided, so they knew what happens if they do it, and what happens if they don't.

So on a job we act a bit like a referee: we price it, supervise it, build it and guarantee it.

Now I'm curious how you do it. Do you still budget a 10-20% buffer, or do you price in stages? And what's the one thing behind a wall that blew up your numbers?

Have a great day!

0Reply
1,606 views

Most Popular Reply

Realtor · Memphis, Shelby County · Member since 2026 · 235 posts · 79 votes
6d

I think of contingency less as money that comes back or gets spent, and more as a reserve that protects the plan either way. If the work opens up cleanly, the reserve stays available for the next repair or the next project, rather than being treated as extra profit in the original numbers. If a surprise appears, such as old wiring, plumbing, or framing that was not visible at first, the reserve covers it without forcing cuts elsewhere. I do not share the details of a specific client's deal, but the principle I use is simple: the contingency is there so one hidden problem does not derail the whole budget, and any unused portion is still a cushion, not a reason to underwrite the next deal more aggressively.

See this reply in the discussion

41 Replies

Jump to latestLatest
  • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
    6d

    A quick follow-up to make it easy to jump in :)

    What buffer did you use on your last rehab?

    1. Under 10%

    2. 10-15%

    3. 15-20%

    4. More than 20%

    5. No flat buffer, I price in stages

    Just drop the number, and if there's a story behind it, even better. Have a great day!

  • Realtor · Memphis, Shelby County · Member since 2026 · 235 posts · 79 votes
    6d

    I still keep a buffer, and I think of it less as padding and more as protection for the unknowns you cannot price from the outside. Detailed pricing in stages is a great approach, and I would use it too, but a wall can hide plumbing, wiring, or framing problems that no walkthrough will show. I would keep the detailed scope and stage pricing, and still hold a separate contingency that is only released when a surprise is documented and priced. That way the budget stays honest, and you are not forced to cut corners later just to stay on number. For an older home, or a home with limited access for inspection, I would lean toward the higher end of that range.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      6d

      @Ametria Chaney Thank you, Ametria, I really like how you put it: not padding, but protection for what you can't price from the outside. We just build that protection differently. We don't open the whole house and hope 15% will be enough. We open it block by block, and before a wall comes down we already have the options worked out: if the old plumbing is in there, what replacing it costs, and what happens if the owner decides not to. So a surprise is still documented and priced before anyone pays, just like your contingency, but the money stays with the owner until it's really needed, instead of sitting in the budget, where it has a way of getting spent.

      And you're right about older homes. That's exactly where we go in smaller blocks.

      Now I'm curious: on your last older home, did that contingency come back to you, or did it get used up? And what was hiding behind the wall?

      Have a great day!

    • Realtor · Memphis, Shelby County · Member since 2026 · 235 posts · 79 votes
      6d

      I think of contingency less as money that comes back or gets spent, and more as a reserve that protects the plan either way. If the work opens up cleanly, the reserve stays available for the next repair or the next project, rather than being treated as extra profit in the original numbers. If a surprise appears, such as old wiring, plumbing, or framing that was not visible at first, the reserve covers it without forcing cuts elsewhere. I do not share the details of a specific client's deal, but the principle I use is simple: the contingency is there so one hidden problem does not derail the whole budget, and any unused portion is still a cushion, not a reason to underwrite the next deal more aggressively.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      6d

      @Ametria Chaney thank you! I like your point that an unused reserve is a cushion, not a reason to push the next deal harder. I think we're looking at the same thing from two sides: you from the owner's side, me from the side of our app. Here's how the chain looks for us:

      The owner says: I want to renovate the house.

      The app answers: $20,000 as it stands, $22,000 if the pipes need replacing, $24,000 if the wiring needs replacing too.

      That's your 10-20%, just written out as named options with a price on each. So if that's what you mean, I agree with you. We price every option upfront and warn the owner about each possible increase, but we start with the short block we're sure of. When a wall opens up and there's extra work, the owner already knows what it costs and simply says yes or no. And the money for options that never happen just stays in the owner's pocket.

      The calculation takes us about 2 minutes. On our last project in Switzerland the full estimate was CHF 28,000, and we were off by just CHF 132 on materials. We didn't charge that, it was our miss. Everything outside the original scope was paid separately. Even cutting channels in a concrete wall for new switches and outlets, we estimated 24.6 ft and it came out at 26.2 ft.

      So here's a question for everyone: where does unused money do more good, in a reserve line or in the owner's pocket from day one? Is that a debate in the US too? Have a great day!

  • Flipper/Rehabber · Fresno, CA · Member since 2022 · 16 posts · 6 votes
    6d

    I'd keep it. On the lending side, the flips that get into trouble usually aren't the ones with a bad ARV, they're the ones that run 10% over on rehab and the borrower has no cash left to finish. Draws get funded against completed work, so if you're short mid-project the job stalls while holding costs keep running. If you've got tight bids and a crew you've used a bunch of times, you can probably run leaner, but I'd at least keep a line for what you can't see until walls are open: electrical, plumbing, foundation.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      6d

      @Robert Cervantes thank you, a great point from the lending side, and I agree with your diagnosis: the losses start not with a bad ARV but with a rehab that runs over, and with draws paid only against completed work, the job stalls while holding costs keep running. That's why I'd assess all the risks right at the start, not only the construction itself, but also permits and contractor availability. So here's my question: if you had all the cards on the table and could see the whole process on a Gantt chart, with the costs and the hidden costs, every contractor confirmed, and a clear stage-by-stage handover with sign-off and a check at each stage, would you take on more flips, or is the real bottleneck somewhere else? Have a great day!

  • Divin KanyamaBusiness Member
    Accountant · Seattle, WA · Member since 2025 · 630 posts · 264 votes
    6d

    @Vladimirs Veiss I like the staged approach, especially the idea of pricing what happens if the owner says yes and what happens if they say no before anything comes down. That's the part that builds trust, and it turns surprises into decisions instead of arguments. Where I'd push back a little is on dropping the buffer completely. Staged pricing works well when the owner can pause between blocks and approve each step.

    For many investors, though, the budget is tied to a loan, a draw schedule or a fixed sale price, so I'd still keep a smaller reserve at the project level, even if it isn't baked into each line item. The two ideas work well together: price in blocks where the unknowns are real, keep the reserve for what you couldn't have seen, and be open about how much of it you've used. As for the usual suspects behind a wall, the ones that tend to cause trouble are old wiring, hidden water damage, undersized or altered structure and plumbing that doesn't match the drawings. Just keep in mind this is my general take and not professional or financial advice, so confirm structural questions with a licensed engineer.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      6d

      @Divin Kanyama thank you so much, really good to hear your view, and thanks for the list of usual suspects! Your loan point is exactly why I'd skip any reserve, even one the investor holds himself. When people borrow for the work, they need to know exactly what they'll spend, not a number plus a cushion that may or may not get used. So I believe the tool should calculate the exact cost with no percentages added, and every contractor should get a clear plan of work with a set payment for each part. Think of a car on autopilot: it knows exactly what to do, and when an obstacle shows up, it brakes or goes around. That's your "surprises into decisions." Everyone knows what they have to deliver, so together we reach the finish line. In the US, would a lender fund draws against an exact priced plan like that, or still insist on a contingency line? Have a great day!

  • Realtor · Memphis, Shelby County · Member since 2026 · 235 posts · 79 votes
    5d

    Good question, and yes, it is a debate here too. I lean toward keeping the unused money in a reserve line rather than treating it as profit on day one, because a rehab that comes in under budget usually just means the surprise has not shown up yet. Keeping it in reserve means the next problem is already funded, and you are not scrambling or cutting corners to cover it. If the project closes out cleanly and the reserve is still there, then it can move to the owner's pocket with a clear conscience. The buffer is not wasted money; it is the price of sleeping well while the project is still open.

  • Ryan BrownPro Member
    Real Estate Agent · Louisville, KY · Member since 2022 · 79 posts · 25 votes
    5d

    @Vladimirs Veiss, I like the staged approach for an owner who already has the property and wants to renovate it. But I don't think it's practical for the average single-family or small multifamily investor, because our problem shows up earlier.

    We have to come up with a renovation estimate before we buy the property, based on pretty limited information, and that estimate decides what we can offer. We don't get the extended due diligence period a larger commercial deal comes with. Usually it's one walkthrough, maybe a short inspection window, and sometimes not even that. Nobody is opening walls block by block before closing. Once we own it, whatever is behind the walls is our problem, whether we priced it or not.

    So we walk the property and fill out our spreadsheet with everything we can see, plus everything we think needs to be done based on the age and condition of the house. Then we add contingency money on the back end, on top of that. The total is how we know how much we can pay. The contingency isn't padding for a contractor. It's how we avoid overpaying for a house we only got to see for 30 minutes.

    If the walls open up clean, great, that's a little extra margin on the deal. If they don't, the deal still works. For the size of deals most of us are doing, I'd rather build the unknowns into my offer than find out about them after closing.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      5d

      @Ryan Brown thank you, Ryan, good point, and you're right: for an investor the number has to exist before closing, from one walkthrough. That's the case we had in mind. From the photos and the plan we price everything visible, and for what's behind the walls we don't add a percentage; we price the likely scenarios by the age and type of the house: this much if the pipes need replacing, this much if the wiring does too. So the unknowns still go into your offer, as you say, but as named items with a price, and that also gives you a concrete argument when you negotiate the purchase price. Curious: when you fill in that spreadsheet, is your contingency a flat percentage, or does it change with the age of the house? Have a great evening!

    • Ryan BrownPro Member
      Real Estate Agent · Louisville, KY · Member since 2022 · 79 posts · 25 votes
      5d

      @Vladimirs Veiss, it's a flat percentage. I've done several full gut and major addition renovations over the years, and that experience has turned into a pretty detailed spreadsheet. Every line item gets priced from what we see on the walkthrough. Then at the bottom, it automatically adds a 10% contingency.

      I like a percentage over a fixed number because the risk grows with the size of the job. On a $200K renovation, it's a lot more likely I'm $20K off than it is on a $20K renovation that I'm $2K off. A bigger scope means more walls opened, more trades involved and more places for something to go wrong, so the cushion should grow with it. The age and condition of the house mostly show up in the line items themselves. If it's a 1920s house with original plumbing, the plumbing line is already priced for a full replacement before the contingency gets added.

      If my estimate turns out to be good and we don't need the contingency, that just makes it a better deal. I'm fine with that outcome every time.

      You're right about negotiation, though. There have been several times where I decided it was in our best interest to hand my actual spreadsheet to the seller or the seller's agent, so they could see exactly how I got to my offer. It changes the conversation. Instead of arguing over whether my number is too low, we're looking at the roof, the electrical and the kitchen line by line. A seller who can see the math is a lot more likely to accept it than one who just gets a lowball number with no explanation.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      2d

      @Ryan Brown thanks for the detailed answer, Ryan, and sorry I'm only replying now! "The cushion should grow with the job" is a fair argument, and your $20K vs $2K example makes a lot of sense.

      Showing the spreadsheet to the seller is the part I like most. We'd add one thing to it: a photo next to each line. A seller can doubt a number, but it's much harder to dispute it when the cracked tile or the old panel is right there next to it.

      When a seller's agent sees your line-by-line math, which line do they argue about first: the roof, the electrical or the kitchen?

      Have a great weekend!

    • Ryan BrownPro Member
      Real Estate Agent · Louisville, KY · Member since 2022 · 79 posts · 25 votes
      18h

      Oh, I think the most common is the "I could get it done cheaper than that..." which is easily defeated with... "you should do it then!"

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      16h

      @Ryan Brown, ha, that's the best answer to it! Thank you. Does that line usually end the argument, or do they come back with a lower number anyway? Have a great evening!

  • Mark UpdegraffBusiness Member
    Real Estate Broker · Rochester, NY · Member since 2010 · 1k+ posts · 713 votes
    5d

    @Vladimirs Veiss, I would separate estimate accuracy from project liquidity. Stage pricing can make the scope clearer, but it doesn’t eliminate the need for cash that can absorb a permit delay, material lead time, failed inspection or carrying costs while the next block is decided. A precise estimate answers, “What should this work cost?” A reserve answers, “Can the project keep moving when the plan meets the building?” I’d keep the options priced and still protect a project-level reserve that is released only when the risk is gone.

  • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
    5d

    @Mark Updegraff thank you, Mark, good point: what the work should cost and whether the project can keep moving are two different questions. I'd disagree on what goes into that reserve. On our Swiss projects permit timing and material lead times are planned into the schedule before work starts, materials for each stage are ordered ahead, and the next block is already priced, so nobody waits for a new estimate. A failed inspection is caught earlier too: our supervisor accepts each stage before the official check, and nothing is paid until he does. What's left is the owner's financing and holding costs, and that's a real need. But then it's a carrying-cost line the owner can see, not padding on the rehab number. From what you see in the US, do lenders keep those two apart, or is it all one contingency line? Have a great day!

  • Lender · Irvine, CA · Member since 2026 · 26 posts · 10 votes
    5d

    Pricing in blocks makes sense to me, and it actually lines up with how most rehab loans are funded. Draws get released after each stage is inspected, so the money already moves in blocks.

    Where it gets tricky is the start. The rehab budget gets approved before closing and the loan is sized off it. If block two comes back higher than planned, the lender usually isn't adding money mid-project, so the difference comes out of the investor's pocket. That's really what a contingency does for most flippers. It's less about guessing and more about making sure the cash is there when the surprise shows up.

    So if the investor has real reserves sitting there, staged pricing is the cleaner way to run it. If they're stretched just to close, I'd still want that buffer somewhere, even if it isn't in the bid.

    Disclosure, I'm on the lending side, so I see the draw requests when the walls come open.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      5d

      @Cat Rauh thank you, Cat, your point that draws already move in stages is the piece I was missing, and it's great to hear this from the side that actually sees the draw requests. On reserves I agree with you: cash for a surprise is the investor's job, not something hidden in the bid. One thing I keep wondering about is why the second stage comes back higher. On our Swiss jobs the gap was usually the rough starting number, not a surprise behind the wall. There, the estimate is built from the plan and actual material prices before closing, so the budget the financing sits on is the one the work really follows, and each stage is accepted by our supervisor before it's paid, so there is a documented record for every draw. On one CHF 28,000 estimate we were off by only CHF 132 on materials, so on materials there were no surprises. What's left is the true unknown behind the wall, and that goes in as a separate priced line, not a percentage. So, Cat, when a documented find shows up on a draw, what do you actually do: approve it, ask for a new bid, or go back to the investor? And for everyone else here: when the second stage runs over, is it usually a surprise or a bad starting number? Have a great evening!

  • Real Estate Agent · Houston, TX · Member since 2026 · 38 posts · 11 votes
    5d

    That block-by-block approach makes complete sense on custom remodels or commercial projects where an owner values precision over speed, but on residential flips or turns, debt service turns that pause-and-price model into a holding cost nightmare.

    A 10% to 15% contingency buffer isn't necessarily a lazy guess—it’s an operational shock absorber. When hard money is ticking at 11% or 12%, stopping a crew to re-quote and re-scope every time you open up a partition burns more cash in carry costs and lost momentum than the line item variance itself. Lenders also rarely let you close without a locked, front-loaded scope of work and contingency reserve already in place.

    As for the worst thing behind a wall: a previous "handyman" completely severing three load-bearing 2x4 studs to run a 3-inch drain line. A quick cosmetic bathroom turn instantly turned into pulling down the entire wall, sistering studs, and engineering a header to keep the second floor from sagging.

    The stage-pricing method is definitely clean for GCs, but how do your clients handle the timeline drag when a demo block reveals something ugly and the job has to pause for pricing?

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      5d

      @Alejandro Lopez thank you, Alejandro, that bathroom story is a great example, exactly the kind of thing we deal with. On the pause: with us there's no re-pricing step and no long approvals. The whole job is priced from the plan before the first demo day, so a surprise behind a wall doesn't reopen the price. We run both sides at once, the owner and the crew, and we don't wait on anyone. Everyone on the job knows what comes after what, and we go through it together. We've had our own version of your wall: the pull cable got stuck in the electrical conduit, which meant two extra holes, then patching and finishing. We covered it at our own cost, no charge to the client. The system can fail too, just like in your case, and we have our own way of handling that :) An extra worker comes out and closes that problem while the rest of the crew keeps moving, so the schedule doesn't slip. Once the work is rolling, there's no point in stopping and slowing everything down. You just keep moving together. That's why it matters so much to me to understand how each side thinks, and every day until we arrive in the US, your and my future favorite country, your view and the situations you go through are very valuable to me. In Texas, when a find like that adds cost mid-demo, who signs off on it first, the owner, the GC, or the lender, and how many days does that usually take? Thanks again, Alejandro, and have a great evening!

  • Matthew MorrowBusiness Member
    Investor · PA - NY - NJ · Member since 2019 · 924 posts · 329 votes
    5d

    @Vladimirs Veiss you invited me over, so here's my take. With your background, pricing it in blocks probably works because you know what you're looking at. On older houses I still keep money aside, and it's not because I think my estimate is bad. I just assume the last owner didn't take care of things the way I would, and the walls tell you that only after you've bought it. I'd rather have reserves for the big items and not need them. Every property is different, but that's how I'd approach it.

    CORE Team | Realty ONE Group Supreme548 Reviews
    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      5d

      @Matthew Morrow Thank you, Matthew, I really appreciate you coming over! You're right, the walls only talk after you buy, and keeping money aside for the big items makes sense to me. What we try to do is move that moment earlier. In Latvia, for example, in older wooden houses we already expect to open the ceilings, so it's priced into the estimate from day one instead of sitting in a reserve. When something is truly unknown, we open it first and price the next step from what we actually see, and every stage is checked and accepted with photos before the walls close. On your older houses in PA, NY and NJ, which big item most often eats the reserve: plumbing, electrical or the structure? Have a great day!

    • Matthew MorrowBusiness Member
      Investor · PA - NY - NJ · Member since 2019 · 924 posts · 329 votes
      5d

      @Vladimirs Veiss opening it up first and pricing from what you actually see is a smart way to do it. On my first house it was plumbing and electrical both, which is kind of how it goes with the older stock around here. A lot of these houses are 100 plus years old, and the wiring and the pipes have usually been patched by three or four different owners. Structure comes up less often, but when it does it's the one that hurts. That's why I still like a little set aside even when the estimate is tight.

      CORE Team | Realty ONE Group Supreme548 Reviews
    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      5d

      @Matthew Morrow thank you, Matthew. "100 plus years old and patched by three or four owners" says it all, and a little set aside on houses like that makes total sense. Every project shows us our own mistakes, so the next estimates get sharper. You said structure comes up less often but hurts the most: has a structural surprise ever changed a deal for you after you were under contract, and did you renegotiate or walk? Have a great day!

    • Richard NeesePro Member
      Rental Property Investor · South Vinemont, AL · Member since 2026 · 48 posts · 17 votes
      4d

      i'm gonna keep playing tag on your post. Thank you for contributing so much. I know the community as a whole appreciate it. A lot of our houses are in the 50-60 year old range. We dont have quite as much standardization and not near as many 100 year old homes still standing like you do up in your neck of the woods. With the 60 year old houses is just the same though. We run 7.5% capex ad 7.5% maintenance because of the age and quality of build homes on our buy an holds and thats after we've done renovations. good post and smart strategy. We also want to get the best deal possible and if i can build in a 10% contingency and the seller is motivated enough to take it... thats perfect protection for me and profit if it turns out not needed. As i've mentioned before our AAR's help us hone our numbers and we also try to keep a read on trends . review the houses we lost to competitors on and see how far off we are. Are we pricing ourselves out every time by our contingency amount?

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      3d

      @Richard Neese thanks for the tag, Richard!

      The 10% itself doesn't price you out; a vague rehab number under it does. A buffer is a fair tool when the seller takes it. But if the rehab is only a rough guess, the buffer ends up covering the guess, not the house, and that's where offers start losing to competitors.

      We're the control layer between the client and the contractor: we price every stage, track it and check each hidden stage before it's closed up, while the crew does the work. In the US we're building this as a team with flippers, lenders, insurers and investors. Picture us as the car: you choose where to go, we keep the trip on budget and on schedule.

      Back in Switzerland, hidden stages are where budgets usually break on older houses. On your 50 to 60 year old houses, when you lost a deal, was the gap usually one padded line like plumbing, electrical or the roof, or the contingency itself?

      Have a great weekend!

  • Property Manager · Southfield Mi · Member since 2018 · 191 posts · 176 votes
    5d

    In my way of thinking your buffer should be less a percentage of cash reserved, but more of an underlying arrangement built into the relationship you have with your contractor. Your rehab team benefits from your success and as they share in your successes, they should help mitigate losses when there are unforeseen changes. This may seem strange at first glance, but I would try asking your contractor this question "Considering that some of the projects have very thin margins, would you be willing to lock in a price and absorb the cost of any changes (that do not exceed 5%-10% of the project budget) if I commit to using your team as my primary rehab crew and also if I agree to share windfalls on other projects where we save money on repairs or where your bid comes in less than our budget?"

    9 times out of 10 a smart contractor will agree to this. An experienced rehabber will likely catch most of what the untrained eye will miss before the project starts so what is truly "unexpected" will almost always be something trivial. This approach will also make your contractor look more closely at the property considering that he/she has agreed to absorb some of the change in scope.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      5d

      @Leroy K. Williams Thank you, Leroy. I fully agree with your reasoning, and a crew that absorbs part of the changes will look closer at the house. We just use a slightly different mechanic, and we don't push it on anyone. Your way works great with a crew you know well. For us the catch is scale: a deal like that has to be negotiated with each new contractor, and that takes time. So we took the Uber approach: nobody negotiates each job, every side has a clear scenario. Do A, get B. Do C, get D. Each stage is paid once it's accepted, so it runs like clockwork, scales, works remotely under control, and keeps everyone happy :) When you bring on a new contractor, how many conversations does it take before that absorb-and-share deal is actually agreed? Have a great day!

    • Property Manager · Southfield Mi · Member since 2018 · 191 posts · 176 votes
      4d

      @Vladimirs Veiss, I think your model is fair and from your side of the transaction it is extremely equitable. You do A, and get B, the issue arises when your vendor realizes that this is your reaction to change orders. Tactically speaking it opens the door for someone to underbid to win a project only to adjust the actual costs by inserting a series of change orders once the project is underway. If I understand your model correctly and example would be as follows:

      Pockets Big Renovation Systems, LLC bids $15,300.00 to remove existing cabinets, flooring, underlayment, all electrical receptacles and install new cement board underlayment, new large platform porcelain tile, new outlets, repair damages and defects in the walls and ceilings and paint 2 kitchens in a multi-unit residential building all based on a Progressive payment schedule.

      The project starts and upon tearing out the cabinets black mold is discovered along the base of the wall behind the old cabinets. Change order #1 ensues, add $600 for selective mold remediation, day two the flooring is removed and the contractor discovers damp floor sheathing, which is rotted in certain areas, Change Order #2 to replace add $700. etc. This series of additions will become disastrous for most REI projects. These changes also undermine the confidence the investor has in the contractor which leads to a cycle of firings and hiring new vendors and at each occurrence the new tradesperson will criticize the previous guy and explain why they have to undo and redo work which costs even more money.

      I started rehabbing in the world of government contracts about 35 years ago and I watched this cycle play out on multimillion dollar renovations, so my point is that it appears at all scales. You mentioned having a contractor or group of contractors you know well and I think this is the key, building teams and relationships.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      4d

      @Leroy K. Williams thank you, Leroy! "Pockets Big Renovation Systems" made me smile :) And you're right, that underbid-then-change-order spiral can sink a project at any scale. The door opens when the contractor sets the price himself. In our case he doesn't: every stage is priced before he arrives, and the typical surprises, like mold behind the cabinets or soft sheathing, are on the table upfront too. So the owner sees the worst case from day one, and a low bid can't be stretched later. That's how we ran our Swiss projects. And you're right that teams are the real asset. Clear numbers upfront are what keep a good crew together, because nobody feels burned and there's no reason to swap crews midway. In those government jobs, when a contractor lowballed and then buried the owner in change orders, was it usually a deliberate strategy, or an honest surprise behind the walls? Have a great evening!

  • Investor · Milwaukee - Mequon, WI · Member since 2010 · 5k+ posts · 7k+ votes
    4d

    @Vladimirs Veiss I think you have to differentiate by job. If you rehab units in a MF you have a lot of opportunity to optimize, because you are doing the same work over and over again. You can optimize both for material, but also labor: which materials install faster vs what they cost.

    Single family is different. I have always been remodeling single family homes, mostly from the 60s, long term buy and hold.

    We know how much to budget for a roof, for windows, for HVAC, for a new electrical panel. The variable really is what to replace and what to keep. Painting original hollow core doors is a lot cheaper than than installing new solid 6 panel doors. But it is also a major upgrade the the overall look and feel of the property. And for a long term buy and hold that translates into better tenants and higher rents. I always cringe during the rehab, but when I see the house again 5 or 10 years later during a turnover, I am always glad I said yes to doing the bedroom doors, the sump pump, replacing that broken concrete walk, etc

    Say yes 5 times, you spend an extra 10k on a 60k project. I tend say yes a lot..

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      4d

      @Marcus Auerbach thank you, Marcus, what a great answer! I fully agree. Our product is built for exactly that: it's designed to learn from every finished project and give the calculations for the next one based on the houses already done. And the most important thing is that you understand this and don't cut corners on what pays off 5 or 10 years later.

      Mind if I ask a few questions? Do you try to keep your projects local, so you or your people can drive over and check how the work is going? Do you have an established crew that you only work with? And say someone offered you 5 to 10 old houses at a deep discount on the other side of the US, in a town where a big factory is about to open and there's almost no affordable housing nearby. Would you invest, and how would you handle the control from a distance? :)

  • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
    4d

    Thank you all! Over 30 replies already, and this is one of the best debates here. Here's the scoreboard so far, so anyone new can jump right in :)

    Keep the buffer: lenders like @Robert Cervantes, plus Ryan and Ametria (not padding, but protection for what you can't price from the outside).

    Keep it, but separate it: @Mark Updegraff (estimate accuracy is one thing, project liquidity is another).

    Move it to the contractor: @Leroy K. Williams (lock the price, share the windfalls, build a team).

    It depends on the job: @Marcus Auerbach (repeat units vs one-off houses, and upgrades that pay off in 5-10 years).

    No flat percentage, price in stages: that's us, and Cat, Divin and Alejandro see the logic too.

    Quick vote, one letter is enough: A) keep a buffer, B) contractor absorbs the changes, C) price in stages, D) depends on the job. And on your last rehab, did you finish under, on or over budget?

    • Matthew MorrowBusiness Member
      Investor · PA - NY - NJ · Member since 2019 · 924 posts · 329 votes
      4d

      @Vladimirs Veiss honestly, I can't point to one that blew up a deal after we were under contract, and I'd like to keep it that way. What comes up more often is the inspection turning up something on an older house that changes the number, and then it's a conversation with the seller. If the issue is real and documented, most sellers would rather renegotiate than start over. If they won't move and the numbers don't work anymore, walking is fine. Purchase price is the most important number in the deal, so I try not to fall in love with a house before that's settled.

      CORE Team | Realty ONE Group Supreme548 Reviews
    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      4d

      @Matthew Morrow thank you, Matthew! Not falling in love with a house before the price is settled is a great rule :) And I like your order: if the issue is real and documented, most sellers renegotiate; if they won't move and the numbers break, you walk. When you bring that number to the seller, do you ask for a price cut or a repair credit at closing, and does it change how they react? Have a great weekend!

  • Real Estate Agent · Boston, MA · Member since 2025 · 64 posts · 23 votes
    1d

    Vladimirs, great question. In our older Worcester and Warren stock, the scope-changer is usually what you can't see: knob-and-tube wiring that insurance won't accept, and old plumbing — galvanized supply lines and cracked cast-iron stacks — hiding behind plaster. Rot is a close third wherever water has had years to work. On lead: yes, we build it in from day one on pre-1978 buildings. In Massachusetts, if a child under six will live there, deleading isn't optional, and the Letter of Compliance is what protects you — so we get the inspection during diligence, price the deleading into the rehab budget, and have the letter in hand before the unit is listed. Surprises cost less when you assume they're in there.

    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      1d

      @Inder Singh, thank you, this is gold. "Surprises cost less when you assume they're in there" is exactly how we try to price: the likely hidden items get their own line up front instead of hiding inside a buffer. And thanks for walking me through the Letter of Compliance, getting it in hand before listing makes total sense.

      The insurance point is new for me. When an insurer won't accept knob-and-tube, do you have to rewire the whole unit before they'll bind the policy, or can you phase it room by room during the rehab?

      Have a great week!

  • Owen RosenBusiness Member
    Professional · Clinton Township, MI · Member since 2015 · 691 posts · 261 votes
    9h

    Quick take from the insurance side: knob-and-tube really depends on the carrier. A lot of standard carriers won't bind with any of it still live, while others will with an electrician's report or a partial update. During the rehab, a vacant or builder's risk policy usually bridges the gap, and then you move to a regular landlord policy once the rewire's done. Worth calling your agent before you lock in the scope.

    Royal Oath Insurance Group4.9208 Reviews
    • Developer · Riga, Latvia | Switzerland | Florida · Member since 2026 · 129 posts · 20 votes
      1h

      @Owen Rosen, thank you, this is really helpful! The builder's risk policy as a bridge during the rehab was exactly the piece I was missing, and calling the agent before locking in the scope is a rule I'll keep.

      On our Swiss jobs every stage closes with dated photos and a sign-off, so next to the electrician's report there would be a clear record of each stage.

      For a vacant house during a four-week rehab, does builder's risk usually cover materials stolen from the site, or is that a separate add-on?

      Have a great day!