Siahna, the disappearance is usually the end of a payment problem that started weeks earlier. The pattern I see: a big deposit up front, no written phase schedule, and then the contractor is funding your job — or someone else's — out of the next deposit. When the money gets tight, the job that goes quiet is the one with no milestones left to bill against.
What's worked for me is boring: pay in phases, and the next phase doesn't start until the last one is signed off — in person or on video. Deposit small enough that losing it hurts but doesn't kill the job. And the contract names what 'done' means for each phase, because 'almost done' is where the disappearing act starts.
If it happens anyway: document everything, secure the property and the materials you paid for, and get the remaining scope bid by someone new against the written scope — not a fresh negotiation from memory. The written scope is what makes the job resumable. Without it, you're paying a second contractor to guess what the first one promised.
I have a representative who's supposed to be overseeing a project for me, and I found out my contractor was arrested several weeks ago and is in prison and hasn't been on site, but my on-site manager never told me. You can guess what happened to my on-site guy...
That’s a serious breakdown in communication and oversight. Finding out weeks later that your contractor wasn’t even on-site must have been incredibly frustrating, especially when you had someone assigned to monitor the project. It really shows why regular site updates and accountability are so important. How did you handle the project after discovering what happened?
Siahna, the disappearance is usually the end of a payment problem that started weeks earlier. The pattern I see: a big deposit up front, no written phase schedule, and then the contractor is funding your job — or someone else's — out of the next deposit. When the money gets tight, the job that goes quiet is the one with no milestones left to bill against.
What's worked for me is boring: pay in phases, and the next phase doesn't start until the last one is signed off — in person or on video. Deposit small enough that losing it hurts but doesn't kill the job. And the contract names what 'done' means for each phase, because 'almost done' is where the disappearing act starts.
If it happens anyway: document everything, secure the property and the materials you paid for, and get the remaining scope bid by someone new against the written scope — not a fresh negotiation from memory. The written scope is what makes the job resumable. Without it, you're paying a second contractor to guess what the first one promised.
That’s a great point about making the written scope detailed enough for someone else to pick up the project if things go wrong. Payment milestones and clear sign-offs can also help keep everyone accountable before problems escalate. I especially like the reminder that “almost done” needs a clear definition. Have you found that video walkthroughs are just as effective as in-person inspections for approving each phase?
Update — I have crews open this week for multifamily turns + repairs. If you have 10+ units that need to turn fast or a roof / exterior insurance job on a multifamily building, DM me the city + unit count + scope. I can walk it tomorrow and give you a crew timeline.
Hey @Siahna Im Looking at this from the contractor's side - going for the lowest bid is usually the fastest way to get there. To prevent these sort of situations, I recommend getting the bid in writing and broken down by trade. Ask them who is actually doing the work (their own crew or all subs?), and ask to stop by a current job site. Check reviews and ask for referrals too. Speak with homeowners. This last step will help eliminate the ghosting by a lot.
That's a great point! Getting everything in writing and understanding who's actually handling the work can make a huge difference. Visiting an active job site is also a smart way to see how a contractor manages projects firsthand. Sometimes it's not about finding the cheapest bid, but finding someone you can trust to follow through. Thanks for sharing your perspective from the contractor's side!
That's definitely a tough situation, especially when delays can add to your holding costs. It's good that you eventually found someone else to keep the project moving. It also shows how important it is to have a backup plan when working with contractors. Did the replacement contractor manage to get things back on schedule?