Schedule

5 Replies

Anyone have a schedule they use when rehabbing? What do you do 1st, 2nd, etc.? I would imagine painting and floors are last.

Hello Troy,

Here is the order my crews prefer to do the work:

  1. Demo - 1 or 2 days
  2. Framing - 1 to 3 days
  3. Mechanicals (Electric, plumbing, HVAC) - 2 to 3 days
  4. Drywall - 3 to 5 days
  5. Trim and Doors - 1 to 2 days
  6. Paint - 1 to 2 days
  7. Cabinets - 1 day (order far enough in advance)
  8. Flooring - 2-4 days
  9. Counters - 1 day (order when the cabinets are installed)
  10. Fixtures (Fans, faucets, etc) - 1 to 2 days
  11. Cleaning and staging - 1 day

Some touch up paint is needed at the end, but it easier for them to spray the home when there's nothing to worry about getting paint on (no cabinets or flooring). We generally do landscaping after flooring (as the flooring guys and painters will mess up the landscape dumping their buckets), unless we need to grow grass or something that will take a few weeks, in which case the landscaping is done first thing.

Thanks, Marc. What about replacing windows?

It looks like you've got a much more in depth schedule above me, but we do windows during the Framing stage. We do exterior siding during the drywall stage, so that we have people working inside and outside.

To you both, thanks a ton. We are starting on rehab #5 and believe its time for some consistency. Thanks, again!!

Free eBook from BiggerPockets!

Ultimate Beginner's Guide Book Cover

Join BiggerPockets and get The Ultimate Beginner's Guide to Real Estate Investing for FREE - read by more than 100,000 people - AND get exclusive real estate investing tips, tricks and techniques delivered straight to your inbox twice weekly!

  • Actionable advice for getting started,
  • Discover the 10 Most Lucrative Real Estate Niches,
  • Learn how to get started with or without money,
  • Explore Real-Life Strategies for Building Wealth,
  • And a LOT more.

Lock We hate spam just as much as you