Roast me... 11 unit proforma (Almost done) In Salem Oregon. Cluster Cottage
Hello, Chris Blackburn here with Clutch. Let's help each other! Building is hard and expensive. I have more data. Yes, I want to build at a lower price. My goal is to have a cost of $120,000 all in. (DR Horton is SELLING full homes at this price!!). Why is my all in price so HIGH!. Let's break it down. (also, I know bigger pockets hates AI (over-exaggeration). I would like to know why.
Cost Breakdown (Schedule of Values Summary)
Total Development Cost: $2,550,225
1. Hard Costs (Construction): ~$1,990,000 (~78%)
-
Framing / Rough Carpentry: $240,000
-
Siding / Roofing / Exterior: ~$187,000
-
Windows & Doors: ~$101,000
-
Interior Finishes (drywall, paint, flooring, cabinets, countertops): ~$227,000
-
MEP (Plumbing, Electrical, HVAC): ~$270,000
-
Site Work & Utilities (excavation, storm, sewer, grading, paving): ~$330,000
-
Landscaping & Exterior Improvements: $100,000
-
General Contractor O&P: $68,066
-
Contingency: $50,000
2. Soft Costs: ~$340,000 (~13%)
-
Architecture & Engineering: ~$65,000
-
Civil / Survey / Geo / Testing: ~$58,000
-
Permits & SDCs: ~$162,000
-
Professional Fees / Legal: ~$12,500
-
Insurance (Builders Risk, etc.): ~$12,600
-
Development Fee: $50,000
-
Soft Cost Contingency: $15,000
3. General Conditions: ~$65,000 (~3%)
-
Site supervision & project management: ~$39,000
-
Insurance, cleaning, waste, temp utilities, etc.: ~$26,000
4. Financing & Carry Costs: ~$185,000 (~7%)
-
Bank Fees: $62,530
-
Interest Reserve: $103,521
-
Prepaid Interest & Closing Costs: ~$10,000
-
Escrow / Title / Broker Fees: ~$18,000
Quick Takeaways
-
All-in cost: ~$232K/unit
-
Hard cost efficiency: ~$219/SF (very solid for this product)
-
Soft costs + financing: ~20% of total (tight, not bloated)
-