Updated 5 months ago on . Most recent reply

Day 95 Ground Up Duplex
Man!!!! We finally got the meters installed and the rain has stopped so that the machinery doesn't just SINK in the MUD!
This small item of getting the meters installed has meant SIGNIFICANT progress since now we can have clean water. Post inspection, we will be able to do the driveway forms and get that inspected. Then we'll pour the concrete for the driveway and finish the sod. Once that's complete, we'll paint and get all the minor items finished so we can get the Certificate of Occupancy (COO) from the city.
Sat progress is good progress!
Juan-