Skip to content

Let's keep in touch

Subscribe to our newsletter for timely insights and actionable tips on your real estate journey.

By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions
BPCON2026 Orlando

October 2 - 4 Early Bird tickets are now ON SALE. Purchase your tickets today and save $100!

Get tickets
BPCON2026 Orlando

October 2 - 4 Early Bird tickets are now ON SALE. Purchase your tickets today and save $100!

Get tickets
Followed Discussions Followed Categories Followed People Followed Locations
Tax, SDIRAs & Cost Segregation
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated over 4 years ago on . Most recent reply presented by

User Stats

2
Posts
0
Votes
Chris Hart
0
Votes |
2
Posts

Contractor breach of contract

Chris Hart
Posted

Hey everyone! love all the help and support this site offers!

 I Hired the wrong contractor to finish my basement. The long and short of it is, he is way behind (7months) and only halfway done with the project. The work he did is shotty at best. I have an inspection tomorrow where I plan to point out all the issues I see with his work and plan on using that date as the day I noticed defects. According to our contract I have 20 days to write a letter with the defective issues I have found (inspectors write up). I would like to include in the letter that not only do I expect money back for the work he did not finish but I would also like to have another contractor finish the work because I don't believe he is capable. According to our contract he has 10 days to respond to my letter. 

Looking for any advice.

Thanks,

Chris 

Most Popular Reply

User Stats

12,633
Posts
14,931
Votes
Bruce Woodruff
#1 Contractors Contributor
  • Contractor/Investor/Consultant
  • San Diego / Phoenix
14,931
Votes |
12,633
Posts
Bruce Woodruff
#1 Contractors Contributor
  • Contractor/Investor/Consultant
  • San Diego / Phoenix
Replied

First thing I notice is that you want money back....? Why would he have money if a part of the project is incomplete? You would only pay him when he has successfully completed a phase of the work satisfactorily, including inspections where applicable.

Secondly, if you have a proper contract, it will be easy to just suspend the work, fire him ,and hire another Contactor. You will have to have your attorney send him a Certified 'cease work' notice. That will stop him from setting foot on the property or contacting you again.

Third - what was the expected date of completion stated in your contract? It isn't usually exact, but should say something like -'work is expected to be substantially complete by 12/01/21'. (If you had no such verbiage, it is still unreasonable for him to not be complete - we assume) but hopefully you did not leave this open-ended....?