Skip to content
×
PRO Members Get
Full Access
Get off the sidelines and take action in real estate investing with BiggerPockets Pro. Our comprehensive suite of tools and resources minimize mistakes, support informed decisions, and propel you to success.
Advanced networking features
Market and Deal Finder tools
Property analysis calculators
Landlord Command Center
ANNUAL Save 16%
$32.50 /mo
$390 billed annualy
MONTHLY
$39 /mo
billed monthly
7 day free trial. Cancel anytime.
Level up your investing with Pro
Explore exclusive tools and resources to start, grow, or optimize your portfolio.
10+ investment analysis calculators
$1,000+/yr savings on landlord software
Lawyer-reviewed lease forms (annual only)
Unlimited access to the Forums

Let's keep in touch

Subscribe to our newsletter for timely insights and actionable tips on your real estate journey.

By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions
Followed Discussions Followed Categories Followed People Followed Locations
Classifieds
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated about 1 month ago on .

User Stats

1
Posts
0
Votes
Robert Gambee
0
Votes |
1
Posts

Ranking Texas cities by permit processing time

Robert Gambee
Posted

Real estate investors need to consider many factors. But one that's often overlooked is how long it takes to get a renovation permit approved. A permit that takes 30 business days instead of 2 means an extra month of holding costs in mortgage payments, insurance, property taxes, and lost rental income. A delay like that can easily cost thousands of dollars.

However, this information isn't centralized. Each city publishes their permit timelines differently. Some put it on their website. Some bury it in PDF documents. Some don't publish it at all. Compiling this manually would have taken me many hours.

Instead, I used a tool I helped build called everyrow.io/rank to do it in about 5 minutes.

Results

I started with all 75 Texas municipalities with populations over 50,000.

For 45 of the 75 municipalities, I was able to find official processing times, either based on historical performance data or stated targets. For the remaining 30 cities that don't publish this information, I asked everyrow.io/rank to estimate based on contractor reports and comparable cities.

CityPopulationBusiness DaysSource Type
Corpus Christi317,3172Official metrics (FY22 avg: 1.75 days)
San Antonio1,526,6562Official metrics (FY24 avg: 2.3 days)
Waco146,6082City council presentation
Irving258,0603City website
Frisco235,2083City website
McAllen148,7823City website
Grapevine51,3203City website
... 33 more cities with official data ...
Denton165,99812City council audit (2023)
Garland250,43114City website
Sherman50,22915City permit process guide
Georgetown101,34418City website (15-20 day range)
Round Rock135,35930City website

View the full dataset with all 75 cities

Key Findings

At 2 business days average, San Antonio is one of the fastest cities despite being the 7th largest city in America. Their Development Services Department publishes actual performance metrics showing FY2024 averaged 2.3 days against a 3-day goal.

Austin and Houston are in the middle of the pack. Austin processes interior remodels in 5 business days (additions take 15). Houston averages 8 days based on their August 2024 permitting report.

Georgetown (18 days) and Round Rock (30 days), neighboring cities outside Austin, are the slowest at issuing permits.

The research notes contain helpful context. For instance, they explain that Dallas reported its median residential permit time dropped from 68 days in 2022 down to 8 days in 2024.

A Note on Data Quality

Of the 75 cities researched, 45 had official performance metrics or city-stated processing times. The remaining 30 cities don't publish this information, so those values are estimates based on contractor reports and comparable nearby cities. The research notes in the full dataset include the source for each number, including the reasoning behind the estimates.

This inconsistency is itself a finding: 40% of cities in Texas don't publish permit processing timelines at all. This makes it difficult for investors to compare markets and for property owners to plan renovations.

How This Was Done

I started with a list Texas municipalities from Wikipedia and filtered to the 75 cities with populations over 50,000. Then I used everyrow.io/rank to research each city's permit processing time. I prioritized sources in the following order:

1. Official performance metrics (actual measured averages)
2. City-stated standard processing times
3. Contractor/homeowner reports with specific timelines

For each city, the system searched the city's permit office website, development services documentation, and contractor forums. Each result includes sources, which I can use to verify the number.

Cost: $3.89 in total, only 5¢ per row

Time: 5 minutes, 12 seconds

Why This Couldn't Be Done Another Way

This research would be very difficult without everyrow.io/rank.

- There's no aggregator for permit times like there is for home prices. Each city publishes (or doesn't) in their own format.
- Manual research doesn't scale. I could research one city in 10 minutes, but 75 cities would take 12+ hours.
- ChatGPT could find this information for a single city. But it's not set up for researching all 75 at once.

everyrow.io/rank handles all of this: it researches each entity, extracts the relevant number with citations, and ranks them.

Let me know if you have any questions about how everyrow.io works! I'm happy to answer them.