Breaking up with contractor
I am ready to just pay off my current contractor and hire someone else or just finish it myself. My current contractor started back in January 2025. Inside the property is nearly complete. The last major job is the HVAC install. I have a HVAC installer coming to give me an estimate for a complete install, Condenser, Furnace, A-coil, ducting, fuse box. If he can give me a reasonable price I will be looking to pay my contractor for the work he has done so far, and finishing up the rest. I believe 9 months is too long for a BRRRR.
Has anyone else been through this? What kind of problems can I run into?
Most Popular Reply

- Contractor/Investor/Consultant
- West Valley Phoenix
- 14,418
- Votes |
- 12,207
- Posts
No signed contract is both good and bad. Good is that you can just kick him to the curb and move on, The bad might be that you had no terms at all to go by, so how could he have violated anything? Maybe it was assumed to be a 2 yr long job..... :-)
But I would feel comfortable, if I were you, to just move on. Pay him for what he has done of course, but that's all. Send him a cease and desist order (or similar) in writing. Make sure you have a lot of stuff in writing, print your texts, take a lot of pictures....in case he sues you...