Skip to content
Two investors reviewing resources on a laptop

Get industry-leading resources — for free

Unlock resources for every investing strategy and stage with a free account.

By continuing, you agree to BiggerPockets LLC's Terms of Use and Privacy Policy

Followed Discussions Followed Categories Followed People Followed Locations
Rehabbing & House Flipping
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

User Stats

5
Posts
4
Votes
Robert Baron
4
Votes |
5
Posts

Rehabbers: how do you actually track rehab expenses during a project?

Robert Baron
Posted

Good morning — I've done a handful of rehabs, and the part that still trips me up isn't estimating the budget up front, it's tracking the actual spend once you have the keys in your hands. Receipts pile up, I split some costs with a partner, and by the end I'm rebuilding everything in a spreadsheet just to see whether I actually hit the budget.

Curious how everyone here handles it:

  • What do you use to track expenses across a rehab — spreadsheets, QuickBooks, a dedicated app, a shoebox of receipts?
  • How do you deal with receipts from the field (Home Depot runs, subs, materials)?
  • If you flip with partners, how do you keep straight who paid for what and settle up at the end?
  • What's the most annoying part of the whole process — and have you found anything that actually solves it?

Trying to tighten up my own system and figured a lot of you have better setups than my messy spreadsheet. Appreciate any war stories.

Most Popular Reply

User Stats

5
Posts
4
Votes
Replied

I manage large construction projects for my day job, and the habit that transfers: track commitments, not receipts. Your budget doesn't die when a receipt posts, it dies when you say yes to the change order. Log the committed number the day you agree to it and receipts become reconciliation instead of discovery.

Setup that works for me: one card per project, budget lines in the spreadsheet match the scope lines in the GC contract, and a 20 minute reconcile every Friday against the card feed. Field receipts get photographed same day into a shared project folder, then tossed. For partner splits, settle from the ledger monthly, not from memory at the end.

Most annoying part is still subs who text you a price, start work, and invoice something else. Only fix I've found is a one line text back confirming the number before they start. That text has settled more disputes than any spreadsheet.