Rehabbers: how do you actually track rehab expenses during a project?
Good morning — I've done a handful of rehabs, and the part that still trips me up isn't estimating the budget up front, it's tracking the actual spend once you have the keys in your hands. Receipts pile up, I split some costs with a partner, and by the end I'm rebuilding everything in a spreadsheet just to see whether I actually hit the budget.
Curious how everyone here handles it:
- What do you use to track expenses across a rehab — spreadsheets, QuickBooks, a dedicated app, a shoebox of receipts?
- How do you deal with receipts from the field (Home Depot runs, subs, materials)?
- If you flip with partners, how do you keep straight who paid for what and settle up at the end?
- What's the most annoying part of the whole process — and have you found anything that actually solves it?
Trying to tighten up my own system and figured a lot of you have better setups than my messy spreadsheet. Appreciate any war stories.
Most Popular Reply
I manage large construction projects for my day job, and the habit that transfers: track commitments, not receipts. Your budget doesn't die when a receipt posts, it dies when you say yes to the change order. Log the committed number the day you agree to it and receipts become reconciliation instead of discovery.
Setup that works for me: one card per project, budget lines in the spreadsheet match the scope lines in the GC contract, and a 20 minute reconcile every Friday against the card feed. Field receipts get photographed same day into a shared project folder, then tossed. For partner splits, settle from the ledger monthly, not from memory at the end.
Most annoying part is still subs who text you a price, start work, and invoice something else. Only fix I've found is a one line text back confirming the number before they start. That text has settled more disputes than any spreadsheet.