Line Item
Description
Scope of Work Number of Materials Cost of Materials Number of Labor Hours Cost of Labor Hours $ Budget
Cleanout & Hauloff Any necessary demo & hauloff Light 0 18 $ 50.00 $ 900.00
Wall Texture Repairs Miscellaneous Light 8 $ 8.00 8 $ 20.00 $ 224.00
Interior Paint Repaint Interior Light 1050 $ 0.50 12 $ 40.00 $ 1,005.00
Exterior Paint Repaint exterior if not sheathing Light 1050 $ 0.50 8 $ 50.00 $ 925.00
Carpet & Vinyl Floors Installation of LVP throughout home except BRs. Moderate 1300 $ 2.00 40 $ 20.00 $ 3,400.00
Tile Floors Installation of tile into BRs. Light 80 $ 6.00 10 $ 40.00 $ 880.00
Wood & Laminate Floors N/A 0 $ - 0 $ - $ -
Countertops & Backsplashes Backsplash over kitchen /bathroom sinks Light 4 $ 40.00 4 $ 50.00 $ 360.00
Kitchen Appliances Refrigerator, range, microwave; *Possible dishwasher Moderate 4 $ 250.00 4 $ 50.00 $ 1,200.00
Plumbing Fixtures Miscellaneous Light 8 $ 40.00 8 $ 20.00 $ 480.00
Electrical Fixtures & Devices Miscellaneous Light 8 $ 40.00 8 $ 20.00 $ 480.00
Interior Trim Carpentry N/A 0 $ - 0 $ - $ -
Hardware & Accessories Miscellaneous Light 8 $ 8.00 8 $ 20.00 $ 224.00
Landscaping Trim lawn, bushes, trees Light 0 $ - 10 $ 60.00 $ 600.00
Door replacement N/A 0 $ - 0 $ - $ -
Tub & Surround N/A 0 $ - 0 $ - $ -
Shower Stall *Possible shower tile clean/reglaze Light 0 $ - 0 $ - $ -
Cabinets Full Kitchen Install Moderate 8 $ 160.00 6 $ 80.00 $ 1,760.00
Garage Door *Possible garage door installation Light 1 $ 650.00 8 $ 40.00 $ 970.00
Cut Glass Windows & Mirrors N/A 0 $ - 0 $ - $ -
Hot Water Heater N/A 0 $ - 0 $ - $ -
Electric Service Panel Ground new electrical installs Light 1 $ 250.00 6 $ 40.00 $ 490.00
Roof N/A 0 $ - 0 $ - $ -
HVAC System Replacement of sole heating system for heating/cooling system Moderate 1 $ 3,000.00 30 $ 60.00 $ 4,800.00
Insulation N/A 0 $ - 0 $ - $ -
Sheetrock Replacement *Dependent upon opening main floor plan by removing walls Light 8 $ 35.00 8 $ 35.00 $ 560.00
Plumbing Systems *Dependent upon moving of main BR toilet, sink for better BR layout Light 5 $ 40.00 8 $ 40.00 $ 520.00
Window Replacement Replacement of windows throughout. Expansion of basement window to code to allow basement as living space. Moderate 7 $ 325.00 7 $ 150.00 $ 3,325.00
Electric Rewire Basement outlets, lights wiring; Light 8 $ 9.00 8 $ 9.00 $ 144.00
Exterior Siding & Trim Fix Soffit/Fascia; Gutters Light 11 $ 65.00 20 $ 40.00 $ 1,515.00
Framing N/A 0 $ - 0 $ -
Foundation Repair *Dependent upon if bowed floor is an issue from foundation Moderate 9 $ 80.00 9 $ 80.00 $ 1,440.00
Fireplace & Chimney N/A 0 $ - 0 $ - $ -
Exterminator / Pest Control N/A 0 $ - 0 $ - $ -
Basement Waterproofing Fix Leaks, Mold Remediation Light 8 $ 50.00 16 $ 50.00 $ 1,200.00
Wood Decks & Patios Fix Patio Moderate 16 $ 40.00 18 $ 40.00 $ 1,360.00
Fence N/A 0 $ - 0 $ - $ -
Concrete Flatwork N/A 0 $ - 0 $ - $ -
Pool Demolition or Repairs N/A 0 $ - 0 $ - $ -
Permits & Inspections *Dependent upon basement / basement window, foundation Light 1 $ 82.00 1 $ 82.00 $ 164.00
General Contractor Fees GC Moderate $ 2,300.00
Contingency Miscellaneous Light $ 3,122.60
Total Construction Cost $ 34,348.60