What’s Your Approach to Mid-Project Budget Overruns?
Investors, curious to hear: what’s the toughest budget overrun you’ve dealt with mid-project, and how did you handle it?
We had a client project where the GC submitted a change order for $18,000 tied to “unforeseen” plumbing reroutes. After reviewing, we discovered a large portion of the work was actually included in the original scope.
Here’s how we resolved it:
-
Compared the CO against the signed contract scope.
-
Negotiated the CO down to ~$7,500 (actual extras) instead of $18,000.
-
Updated budget tracking to make sure no future “double dips” occurred.
How do you push back or validate mid-project cost increases?