Skip to content
×
Pro Members Get
Full Access!
Get off the sidelines and take action in real estate investing with BiggerPockets Pro. Our comprehensive suite of tools and resources minimize mistakes, support informed decisions, and propel you to success.
Advanced networking features
Market and Deal Finder tools
Property analysis calculators
Landlord Command Center
ANNUAL Save 16%
$32.50 /mo
$390 billed annualy
MONTHLY
$39 /mo
billed monthly
7 day free trial. Cancel anytime

Let's keep in touch

Subscribe to our newsletter for timely insights and actionable tips on your real estate journey.

By signing up, you indicate that you agree to the BiggerPockets Terms & Conditions
Followed Discussions Followed Categories Followed People Followed Locations
Rehabbing & House Flipping
All Forum Categories
Followed Discussions
Followed Categories
Followed People
Followed Locations
Market News & Data
General Info
Real Estate Strategies
Landlording & Rental Properties
Real Estate Professionals
Financial, Tax, & Legal
Real Estate Classifieds
Reviews & Feedback

Updated 9 days ago on .

User Stats

81
Posts
83
Votes
Isaac Lane
  • Investor
  • Columbus, OH
83
Votes |
81
Posts

What’s Your Approach to Mid-Project Budget Overruns?

Isaac Lane
  • Investor
  • Columbus, OH
Posted

Investors, curious to hear: what’s the toughest budget overrun you’ve dealt with mid-project, and how did you handle it?

We had a client project where the GC submitted a change order for $18,000 tied to “unforeseen” plumbing reroutes. After reviewing, we discovered a large portion of the work was actually included in the original scope.

    Here’s how we resolved it:

    • Compared the CO against the signed contract scope.

    • Negotiated the CO down to ~$7,500 (actual extras) instead of $18,000.

    • Updated budget tracking to make sure no future “double dips” occurred.


    • How do you push back or validate mid-project cost increases?