What is the order of things to fix
After demo, what to do next to minimize the rehab time?
Framing/Drywall/Trim
Paint
Flooring
Light fixture
Cabnets
etc...
Most Popular Reply

Usually:
roof/foundation
doors windows trim
Tile
plumbing/heating/elec/fans/vents while everything is exposed.
hang and finish sheet rock
Vanity/sinks
Toilet/tub
Paint ceilings and walls.
Then light fixtures/cabinets/flooring/appliances
Finishing touches.