Order of The Rehab

Wayne Woodson
  • Investor
  • Nashville, TN
Posted May 17 2013, 12:55

As a wholesaler transitioning to rehabber there is something I have always wanted to know. Is there a certain order you follow through the rehab process? For example do you do demo on day 1 then day 2 is cleanup, day 3 is drywall etc, etc. I know the 1st thing would be demo and the last thing would be landscaping but what order do you follow?

User Stats

479
Posts
165
Votes
Ryan R.
  • Real Estate Investor
  • Central, TX
165
Votes |
479
Posts
Ryan R.
  • Real Estate Investor
  • Central, TX
Replied May 17 2013, 13:23

Basically,

1. Plumbing
2. HVAC if necessary
3. Electrical/wiring
4. Windows
5. Insulation.
6. Drywall
From here out some people like to different things, floors then trim, some like trim then floors.

Of course before all of this you address any roofing and or foundation issues.

User Stats

477
Posts
223
Votes
Wayne Woodson
  • Investor
  • Nashville, TN
223
Votes |
477
Posts
Wayne Woodson
  • Investor
  • Nashville, TN
Replied May 17 2013, 13:36

So it's...

1. Demo/ Cleanup
2. Roofing/ Foundation
3. Plumbing
4. HVAC if necessary
5. Electrical/wiring
6. Windows
7. Insulation.
8. Drywall
9. Landscaping
10. Profit $$$

Also I just realized I made the title of this thread sound like a cult for real estate investors.

BiggerPockets logo
BiggerPockets
|
Sponsored
Find an investor-friendly agent in your market TODAY Get matched with our network of trusted, local, investor friendly agents in under 2 minutes

User Stats

3,345
Posts
3,579
Votes
Michael Quarles#1 Marketing Your Property Contributor
  • Flipper/Rehabber
  • Bakersfield, CA
3,579
Votes |
3,345
Posts
Michael Quarles#1 Marketing Your Property Contributor
  • Flipper/Rehabber
  • Bakersfield, CA
Replied May 17 2013, 13:51

We would always tape this to the inside front door with a clear plastic cover.

Here is a link to the form

http://michaelquarles.homestead.com/repair_process.doc

User Stats

477
Posts
223
Votes
Wayne Woodson
  • Investor
  • Nashville, TN
223
Votes |
477
Posts
Wayne Woodson
  • Investor
  • Nashville, TN
Replied May 17 2013, 14:04

Thanks Michael and Ryan. Any tips as far as how to schedule certain trades so you don't have people working on top of each other?

User Stats

13,324
Posts
3,942
Votes
Brandon Turner#2 Questions About BiggerPockets & Official Site Announcements Contributor
  • Investor
  • Maui, HI
3,942
Votes |
13,324
Posts
Brandon Turner#2 Questions About BiggerPockets & Official Site Announcements Contributor
  • Investor
  • Maui, HI
Replied May 17 2013, 17:33

Hey Wayne Woodson looks like you've been given some awesome info already, but I'll add to it that you should definitely check out the new BP book, "The Book on Estimating Rehab Costs" (which comes along with The Book on Flipping Houses." They'll help with a lot of those questions too. You can check those out here - they are both excellent.

User Stats

17,995
Posts
17,164
Votes
J Scott
Pro Member
  • Investor
  • Sarasota, FL
17,164
Votes |
17,995
Posts
J Scott
Pro Member
  • Investor
  • Sarasota, FL
ModeratorReplied May 17 2013, 17:45
Originally posted by Brandon Turner:
...you should definitely check out the new BP book, "The Book on Estimating Rehab Costs" (which comes along with The Book on Flipping Houses." They'll help with a lot of those questions too. You can check those out here - they are both excellent.

The Book on Flipping Houses actually has 25 pages devoted to rehab scheduling, including discussions of dependencies, time frames, rules of thumb for scheduling, etc.

For those who aren't interested in getting the book, here's the gist:

User Stats

446
Posts
171
Votes
Glenn Espinosa
  • Rehabber
  • Alexandria, VA
171
Votes |
446
Posts
Glenn Espinosa
  • Rehabber
  • Alexandria, VA
Replied May 17 2013, 17:51

Michael Quarles - Very nice checklist. It looks like the ideal process for a lipstick flip.

One thing that we like to do is to finish the front facade/landscaping somewhere in the middle of the project as opposed to the very end. That way if a potential buyer happens to drive by they can get an idea for the finished project and add it to their list of homes to see.

User Stats

21,918
Posts
12,856
Votes
Bill Gulley#3 Guru, Book, & Course Reviews Contributor
  • Investor, Entrepreneur, Educator
  • Springfield, MO
12,856
Votes |
21,918
Posts
Bill Gulley#3 Guru, Book, & Course Reviews Contributor
  • Investor, Entrepreneur, Educator
  • Springfield, MO
Replied May 17 2013, 18:15

Nice punch list Michael, as to what might be done, outside it's start form the bottom up, inside start from the top to bottom. Much can be accomplished at the same time. :)

User Stats

351
Posts
193
Votes
Randy F.
  • Contractor
  • Anchorage, AK
193
Votes |
351
Posts
Randy F.
  • Contractor
  • Anchorage, AK
Replied May 17 2013, 20:23

On larger rehabs, it is sometimes better to loose some time by NOT sticking to a common sense production approach. While its nice to do all interior demo at the same time, on a larger job where tight margins exist, I will demo the areas with the greatest potential for unforseen problems... Such as the main bath and any areas where there are known deficiencies but depth of problem is unknown.

Ive just seen too many times when mold and rot and shoddy practices have blown up a budget and if everything is demo'd theres no going back and makes revising the plan near impossible. You know what they say about "best laid plans"! Once the big stuff is opened up and no major setbacks found, all else can procede as planned.

User Stats

13,447
Posts
8,332
Votes
Steve Babiak
  • Real Estate Investor
  • Audubon, PA
8,332
Votes |
13,447
Posts
Steve Babiak
  • Real Estate Investor
  • Audubon, PA
Replied May 17 2013, 22:13

I like the idea with Michael Quarles checklist. I think that there might be some things that could be done in a better sequence though, or maybe that list isn't intended to be totally sequential. For example, "Remove Carpet" appears before "Trash Out" - but the carpet could be tough to get at if lots of bulky stuff needs to go into a dumpster. Another example would be that "Roof Repair" seems to come after the sheetrock work - I would get the roof done before doing any drywall.

There could be some regional variations on this, as well as seasonal variations.

Sometimes up north , in the fall, it makes sense to do landscaping before other things, so that the landscaping has a chance to "take" before it gets too cold. Another seasonal thing would be mudding drywall and interior painting; if the heat isn't on in winter, you won't get things to dry - but in summer you could do those with or without HVAC (at least up north).

User Stats

21,918
Posts
12,856
Votes
Bill Gulley#3 Guru, Book, & Course Reviews Contributor
  • Investor, Entrepreneur, Educator
  • Springfield, MO
12,856
Votes |
21,918
Posts
Bill Gulley#3 Guru, Book, & Course Reviews Contributor
  • Investor, Entrepreneur, Educator
  • Springfield, MO
Replied May 18 2013, 05:30

Good points Steve, if the roof really leaks that can be an asap issue and seasons and weatehr are always an issue.

J. Scott has a good simplified punch list approach too.

While saying outside work from the bottom up, that sounds pretty simplified, it depends on any pressing issues. If you need a house jacked up at a corner, that's a first thing to do issue as it plays on the inside work with floors, trim and walls and flows through to celings and roof. If you have a corner heading down hill you aren't going to get things plub, level and square until that is fixed.

New flooring is usually a last item with me , tear out is just before installation. The old carpet makes a good drop cloth, kneeling pad and protects the hardwood from dropping a hammer until you get ready to refinish it if that's in the cards and reduces construction traffic on new carpet.

Lots of considerations to each job, common sence should prevail and some backward planning needs to be done so you don't put some aspect of the job in front of another making it more difficult. :)

User Stats

3,971
Posts
3,341
Votes
Pat L.
  • Rental Property Investor
  • Upstate, NY
3,341
Votes |
3,971
Posts
Pat L.
  • Rental Property Investor
  • Upstate, NY
Replied May 18 2013, 08:54
Originally posted by Bill Gulley:

New flooring is usually a last item with me , tear out is just before installation. The old carpet makes a good drop cloth, kneeling pad and protects the hardwood from dropping a hammer until you get ready to refinish it if that's in the cards and reduces construction traffic .

We do the same but for my last rehab my guys tore out the 23 yr old carpet first with the padding only to install it (after vacuuming) in one of their Sect8 duplexes.
One man's trash etc etc.

User Stats

816
Posts
228
Votes
David Niles
Pro Member
  • Property Manager
  • DeLand FL
228
Votes |
816
Posts
David Niles
Pro Member
  • Property Manager
  • DeLand FL
Replied May 18 2013, 11:52

Make sure your weather tight and secure, then work your way out the door.

User Stats

37
Posts
2
Votes
Zach Whitt
  • Dallas, TX
2
Votes |
37
Posts
Zach Whitt
  • Dallas, TX
Replied May 20 2013, 19:16

Incredibly helpful thread. I'm knee deep into my first rehab and I'm realizing every day that I wish my list was more comprehensive!

User Stats

198
Posts
25
Votes
Rick L.
  • Investor
  • Saint Louis, MO
25
Votes |
198
Posts
Rick L.
  • Investor
  • Saint Louis, MO
Replied Jun 19 2013, 12:15

Mark, for later reading.

User Stats

13,447
Posts
8,332
Votes
Steve Babiak
  • Real Estate Investor
  • Audubon, PA
8,332
Votes |
13,447
Posts
Steve Babiak
  • Real Estate Investor
  • Audubon, PA
Replied Jun 19 2013, 12:20

Rick L. - you don't have to "mark" a thread by posting in it; you can check the box near the top of the page that says "Monitoring Topic", and then you can find them on the "My Watched Topics" tab on the main forums page.

User Stats

684
Posts
350
Votes
Vincent Crane
Pro Member
  • Realtor
  • Atlanta, GA
350
Votes |
684
Posts
Vincent Crane
Pro Member
  • Realtor
  • Atlanta, GA
Replied Jul 20 2015, 12:24

This is a really great post that could save a lot of people a lot of time and money, thanks for posting and everyone's responses

User Stats

16
Posts
4
Votes
Lucia Matos
  • Mount Prospect, IL
4
Votes |
16
Posts
Lucia Matos
  • Mount Prospect, IL
Replied Dec 29 2017, 10:20

Hi

@Michael Quarles ,

Do you still have the page with the order of remodeling? 

Thanks!!

Lucia

User Stats

2,131
Posts
688
Votes
Kuba F.
Pro Member
  • Real Estate Investor
  • Los Angeles, CA
688
Votes |
2,131
Posts
Kuba F.
Pro Member
  • Real Estate Investor
  • Los Angeles, CA
Replied Dec 31 2017, 10:14

Hey @Lucia Matos

I revisited the subject on a bigger pockets blog post several months ago:

https://www.biggerpockets.com/blogs/8814/63630-how-to-order-the-schedule-of-your-house-flip-construction-tasks

Hope that helps!

Kuba

REIkit.com Logo

User Stats

16
Posts
4
Votes
Lucia Matos
  • Mount Prospect, IL
4
Votes |
16
Posts
Lucia Matos
  • Mount Prospect, IL
Replied Jan 2 2018, 16:53

Dear @Kuba F. ,

That's amazing! It will be so helpful!!